Knox v. Regions Bank

286 S.W.3d 737, 103 Ark. App. 99, 2008 Ark. App. LEXIS 665
CourtCourt of Appeals of Arkansas
DecidedSeptember 3, 2008
DocketCA 08-60
StatusPublished
Cited by4 cases

This text of 286 S.W.3d 737 (Knox v. Regions Bank) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Knox v. Regions Bank, 286 S.W.3d 737, 103 Ark. App. 99, 2008 Ark. App. LEXIS 665 (Ark. Ct. App. 2008).

Opinion

David M. Glover, Judge.

Appellants James and Holly Knox appeal from a summary-judgment order that dismissed their claims against appellee Regions Bank for breach of fiduciary duty, breach of contract, and interference with contractual relations. Appellants contend that the circuit court erred in granting summary judgment because there are issues of material fact to be tried as to each claim. We affirm in part and reverse and remand in part.

Factual Background

On December 18, 2001, appellants contracted with Michael Stewart, d/b/a Stewart Construction, to build a home. The price was to be $120,000. 1 Appellants obtained a construction loan from Regions Bank up to the amount of $128,560. The construction-loan agreement, which is dated January 16, 2002, contained the following provisions relevant to this appeal:

DISBURSEMENT OF LOAN FUNDS. The following provisions relate to the disbursement of funds from the Loan Fund.
Application for Advances. Application shall be stated on a standard AIA payment request form or other form approved by [Regions], executed by [appellants], and supported by such evidence as [Regions] shall reasonably require. [Appellants] shall apply for disbursement with respect to work actually done by [Stewart] and for materials and equipment actually incorporated into the Project. Each application for an Advance shall be deemed a certification of [appellants] that as of the date of such application, all representations contained in the Agreement are true and correct, and that [appellants are] in compliance with all of the provisions of this Agreement.
Payments. At the sole option of [Regions], Advances may be paid in the joint names of [appellants] and [Stewart], subcontractor^), or suppfier(s) in payment of sums due under the Construction Contract. At its sole option, [Regions] may directly pay [Stewart] and any subcontractor^) or other parties the sums due under the Construction Contract. [Appellants] appoint [Regions] as [their] attorney-in-fact to make such payments. This power shall be deemed coupled with an interest, shall be irrevocable, and shall survive an Event of Default under this Agreement.

Construction began shortly after the construction-loan agreement was signed. In May 2002, appellants received a telephone call from Chris Roberts, a Regions vice president, informing them that the loan was overdrawn by $10,615.16. Sometime thereafter, Stewart ceased work on the project.

Appellants filed suit against Regions and Stewart, alleging that Regions breached the construction-loan agreement by disbursing funds directly to Stewart without a request for payment; that Regions assumed a fiduciary duty toward them and breached that duty by failing to complete the house after Stewart abandoned the project; and that Regions interfered with their contract with Stewart because Stewart ceased work after being informed by Regions that the loan was overdrawn and there would be no more money to proceed with construction. 2 Regions denied the material allegations of the complaint, as amended.

On January 29, 2004, Regions filed a counterclaim seeking foreclosure of its mortgage on the property. The circuit court granted summary judgment to Regions on its counterclaim and, on March 17, 2006, entered a foreclosure decree. The property was sold on April 4, 2006, and the court entered an order confirming the sale on that date. Appellants do not appeal from the foreclosure order or the order confirming the sale.

In addition, Regions also filed a motion for summary judgment on appellants’ complaint, as amended. In its supporting brief, Regions asserted that it did not owe appellants any fiduciary duty because the relationship between it and appellants was merely a debtor-creditor relationship. Regions also argued that appellants’ claim for breach of contract was not based on the construction-loan agreement provision regarding application for advances of funds but rather on the fact that Regions paid Stewart directly. Regions argued that the construction-loan agreement specifically gave it the right to do so and, as a result, Regions could not be in breach of the contract for paying Stewart directly. As to the tortious-interference claim, Regions argued that it was entitled to summary judgment because appellants realized that the loan from Regions would be insufficient to pay for both the land and the construction of the home.

Appellants responded by arguing that the provision regarding applications for advances must be read with the provision allowing Regions to make payments directly to Stewart. They also asserted that Regions assumed a fiduciary relationship by paying the money directly to Stewart.

On February 22, 2006, the circuit court issued a letter opinion in which it granted Regions’s motion for summary judgment on appellants’ amended complaint. The court found that there was no basis for the breach-of-fiduciary claim as there was no allegation that would create a fiduciary relationship beyond the construction-loan agreement. The court then addressed the breach-of-contract claim and found that there was no breach because Regions was allowed to pay Stewart directly. The court issued a second letter opinion clarifying its intention to grant summary judgment in favor of Regions on all of appellants’ claims. The court’s order granting summary judgment was entered on March 22, 2006. After this court dismissed appellants’ attempted appeal, see Knox v. Regions Bank, No. CA 06-1198 (Ark. App. Sept. 12, 2007) (unpublished), the circuit court entered a final order that incorporated the prior letter opinions and order granting summary judgment. This appeal followed.

Standard of Review

A motion for summary judgment should be granted when, in light of the pleading, and other documents before the circuit court, there is no genuine issue of material fact and the moving party is entitled to a judgment as a matter of law. Ark. R. Civ. P. 56(c). When reviewing whether a motion for summary judgment should have been granted, this court determines whether the evidentiary items presented by the moving party in support of the motion left a material question of fact unanswered. Bomar v. Moser, 369 Ark. 123, 251 S.W.3d 234 (2007). The burden of sustaining a motion for summary judgment is always the responsibility of the moving party. Id. at 127, 251 S.W.3d at 239. All proof submitted must be viewed in a light most favorable to the party resisting the motion, and any doubts and inferences must be resolved against the moving party. Id.

Arguments on Appeal

Appellants first argue that the circuit court erred in granting summary judgment on their breach-of-contract claim. The court ruled that Regions did not breach the contract because it had the contractual right to pay Stewart directly. We hold that the court erred in granting summary judgment.

Appellants’ argument is not, as Regions argues, that Regions breached the construction-loan agreement by paying the funds directly to Stewart.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L. Walter Quinn v. Richard D. O'Brien
2020 Ark. App. 83 (Court of Appeals of Arkansas, 2020)
Helena Chemical Co. v. Richmond (In Re Richmond)
429 B.R. 263 (E.D. Arkansas, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
286 S.W.3d 737, 103 Ark. App. 99, 2008 Ark. App. LEXIS 665, Counsel Stack Legal Research, https://law.counselstack.com/opinion/knox-v-regions-bank-arkctapp-2008.