Klamath Water Users Protective Ass'n v. Patterson

191 F.3d 1115, 99 Daily Journal DAR 9449, 99 Cal. Daily Op. Serv. 7451, 49 ERC (BNA) 1242, 1999 U.S. App. LEXIS 21567, 1999 WL 695193
Court of Appeals for the Ninth Circuit·Decided September 9, 1999·No. No. 98-35708·Published·Cited by 2 cases

Opinion

TASHIMA, Circuit Judge:

This appeal involves a basic contract issue: whether the Klamath Water Users Protective Association and other irrigators in the Klamath Basin (collectively, the “Ir-rigators”) are third-party beneficiaries to a 1956 contract (the “Contract”) between the United States Bureau of Reclamation (“Reclamation” or “United States”) and the California Oregon Power Company (“Copco”) that governs the management of the Link River Dam (the “Dam”) in the Klamath Basin (the “Project”). We hold that they are not. The district court concluded that the Irrigators do not have third-party beneficiary water rights under the Contract. It granted a declaratory judgment to Reclamation and PacifiCorp, Copco’s successor in interest that now operates and maintains the Dam under the Contract, holding that PacifiCorp is not hable to the Irrigators for implementing Reclamation’s water allocation decisions for the Project. See Klamath Water Users Ass’n v. Patterson, 15 F.Supp.2d 990, 997 (D.Or.1998) (“Klamath”). We have jurisdiction under 28 U.S.C. § 1291, and we affirm.

I. Background

The Project, located within the Upper Klamath and Lost River Basins in Oregon and California, was authorized by Congress in 1905 pursuant to the Reclamation Act of 1902, ch. 1093, 32 Stat. 388 (1902). In 1905, in accordance with state water law and the Reclamation Act, the United States appropriated all available water rights in the Klamath River and Lost River and their tributaries in Oregon and began constructing a series of water diversion projects.

In 1917, the United States and Copco entered into an agreement under which Copco would construct the Dam and then convey it to the United States. In return, Copco and the United States entered into a fifty-year contract (1917-1967) that gave Copco the right to operate the Dam. The Contract was amended in 1920 and 1930, and was renewed in 1956 for an additional fifty years (1956-2006). The United States and Copco are the only named parties to the Contract. The Contract, as renewed in 1956, remains in effect and is the subject of controversy here. The Contract states that it was entered into pursuant to the Reclamation Act and “acts of Congress relating to the preservation and development of fish and wildlife resources.”

The parties do not dispute that the Dam was built to help the United States satisfy its contractual obligations to water users in the basin, including the Irrigators. However, the project served other federal purposes, such as impounding water to flood the adjacent wildlife refuges. Cop-co’s interest related primarily to controlling the flow of water to the Copco-owned hydroelectric facilities downstream from the Dam.

Operation of the Dam is also subject to the requirements of federal statutes, such as the Endangered Species Act (“ESA.”) The coho salmon of the lower Klamath River has been listed as threatened, and two species of sucker fish, the Lost River and shortnose suckers, located in and around the Project, are listed as endangered. In 1992, the United States Fish and Wildlife Service issued a Biological Opinion that required cex-tain minimum elevations for Upper Klamath Lake to avoid jeopardizing these protected species. In addition, the Secretary of the Interior has recognized that a number of Oregon tribes, including the Klamath, Yurok and Hoopa Valley tribes (the “Tribes”), hold [1119]*1119fishing and water treaty rights in the basin.

In recognition of the federal government’s various obligations related to the Project, Reclamation initiated a public process to establish a new operating plan for the Dam. For the next several years, Reclamation intends to issue one-year interim plans while formulating a long term plan for water distribution. Pursuant to this policy, in April, 1997, Reclamation circulated to interested parties a draft of its proposed 1997 interim plan for the Project. In May, 1997, Reclamation issued its final 1997 interim plan. Soon thereafter, Pacifi-Corp stated it would not implement the plan because the required flow levels would force it to violate its Federal Energy Regulatory Commission (“FERC”) license. PacifiCorp’s FERC license required FERC flows1 in September at 1,300 cubic feet per second (“cfs”), while Reclamation’s 1997 plan allowed for only 1,000 cfs.

Reclamation and PacifiCorp agreed upon a short-term modification to the Contract. The modification directed Paci-fiCorp to implement the 1997 plan, contingent upon FERC concurrence. The Irrigators were not included in the negotiations that led to this modification.

The Irrigators filed this action claiming, among other things, breach of the Contract based on their alleged third-party beneficiary status. In response, Pacifi-Corp filed a counterclaim, seeking a declaration of rights with respect to the Irriga-tors’ standing under the Contract. The parties then filed cross-motions for summary judgment.

The district court denied the Irrigators’ motion for summary judgment and granted PacifiCorp’s and Reclamation’s motions for summary judgment on PacifiCorp’s counterclaim. See Klamath, 15 F.Supp.2d at 997. The Irrigators appeal.

II. Discussion

A. Third Party Beneficiaries

The Irrigators argue that under the plain language of the Contract, they are third-party beneficiaries and thus entitled to enforce the Contract’s existing terms. We review the district court’s grant of summary judgment de novo. See Tri-State Dev. v. Johnston, 160 F.3d 528, 529 (9th Cir.1998). Because the facts are not in. dispute, the only question we must decide is whether the district court correctly applied the relevant law in concluding that the Irrigators are not third-party beneficiaries under the Contract. See id. The interpretation of a contract is a mixed question of law and fact subject to de novo review. See O’Neill v. United States, 50 F.3d 677, 682 (9th Cir.1995). In particular, the determination of whether contract language is ambiguous is a question of law. See id.

Federal law controls the interpretation of a contract entered pursuant to federal law when the United States is a party. See id. For guidance, we look to general principles for interpreting contracts. See Kennewick Irrigation Dist. v. United States, 880 F.2d 1018, 1032 (9th Cir.1989). Before a third party can recover under a contract, it must show that the contract was made for its direct benefit— that it is an intended beneficiary of the contract. See Williams v. Fenix & Scisson, Inc., 608 F.2d 1205, 1208 (9th Cir.1979).

A written contract must be read as a whole and every part interpreted with reference to the whole, with preference given to reasonable interpretations. See Kennewick, 880 F.2d at 1032. Contract terms are to be given their ordinary meaning, and when the terms of a contract are clear, the intent of the parties must be ascertained from the contract itself. See Hal Roach Studios, Inc. v. Richard Feiner [1120]*1120& Co., Inc., 896 F.2d 1542, 1549 (9th Cir.1990).

Free access — add to your briefcase to read the full text and ask questions with AI

Klamath Water Users Protective Ass'n v. Patterson, 191 F.3d 1115, 99 Daily Journal DAR 9449, 99 Cal. Daily Op. Serv. 7451, 49 ERC (BNA) 1242, 1999 U.S. App. LEXIS 21567, 1999 WL 695193 (9th Cir. 1999).

191 F.3d 1115 (Klamath Water Users Protective Ass'n v. Patterson) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In Re Dow Corning Corp.
244 B.R. 721 (E.D. Michigan, 1999)
Henzel Properties, Ltd. v. Roger Patterson
191 F.3d 1115 (Ninth Circuit, 1999)