Kitchen Jewels, Inc. v. Beck

513 N.E.2d 1246, 1987 Ind. App. LEXIS 3123
CourtIndiana Court of Appeals
DecidedOctober 14, 1987
Docket63A01-8704-CV-00081
StatusPublished
Cited by5 cases

This text of 513 N.E.2d 1246 (Kitchen Jewels, Inc. v. Beck) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kitchen Jewels, Inc. v. Beck, 513 N.E.2d 1246, 1987 Ind. App. LEXIS 3123 (Ind. Ct. App. 1987).

Opinion

RATLIFF, Chief Judge.

STATEMENT OF THE CASE

Kitchen Jewels, Inc. appeals from the Pike Circuit Court a jury verdict in favor of B and S rentals for breach of a lease agreement. We affirm.

FACTS

On March 1, 1985, Kitchen Jewels, Inc. (Kitchen) entered into a lease agreement with B and S Rentals (B and S). On the date of the lease B and S was a partnership owned by Arnold and Alan Beck. On the date of trial B and S was owned by Arnold and Rose Beck. The lease provided that Kitchen would lease from B and S a tract of real estate and a building that B and S would construct. The lease did not provide for the specific type of building to be erected. However, Kitchen approved B and S’s construction of a twelve thousand (12,000) square foot building which also had a partial basement. Kitchen agreed to lease the building, but not the basement.

B and S substantially completed the building by August 1, 1985. On that date B and S met with and advised Kitchen that Kitchen could move into the building and stated that rent would start on September 1, 1985. Kitchen was reluctant to move into the building. On approximately August 19th of 1985, another meeting took place. Kitchen voiced concern over specific problems with the building and stated that Kitchen would not occupy the building until these problems were corrected. B and S complied with Kitchen’s requests. However, Kitchen again refused to occupy the building. Kitchen apparently refused occupancy because of a separate dispute Kitchen had with Hurricane Construction, a company owned by Alan Beck, Arnold Beck’s son. Kitchen gave no other reason for their refusal. On September 16, 1985, Kitchen’s attorney sent a letter to B and S which indicated that Kitchen deemed the lease null and void for failure of consideration.

On November 19,1985, B and S filed suit against Kitchen and against Virgil Gress, Kenneth C. Mehringer and Joseph Fehri-back personally and as representatives. On November 11, 1986, a jury returned a verdict in favor of B and S against only Kitchen. The trial court entered judgment in favor of B and S for Thirty-Six Thousand Six Hundred and Eighty-Four Dollars ($36,-684). Kitchen appeals this judgment.

ISSUES

While Kitchen raises four (4) issues for review, we renumber and rephrase the issues as follows:

1. Whether the trial court erred by entering judgment in favor of B and S based upon the jury’s verdict.

2. Whether the trial court erred by admitting photographic evidence of a building presently occupied by Kitchen. 1

DISCUSSION AND DECISION

Issue One

Kitchen first argues that the trial court erred by entering judgment in favor of B and S. Kitchen contends that the judg *1248 ment is contrary to law and unsupported by the evidence, because B and S failed to comply with the mandates of the contract. Kitchen correctly acknowledges the court’s well established standard of review. On appeal the court neither reweighs evidence nor judges witness credibility. Martin v. Roberts (1984), Ind., 464 N.E.2d 896, 904; F.D. Borkholder Co. v. Sandock (1980), 274 Ind. 612, 614, 413 N.E.2d 567, 569; Burras v. Canal Construction and Design Co. (1984), Ind.App., 470 N.E.2d 1362, 1365. The court considers only that evidence which supports the judgment. Martin, at 904; Sandock, 274 Ind. at 614, 413 N.E.2d at 569; Burras, at 1365. The judgment will be affirmed if substantial evidence of probative value exists to support the judgment. Martin, at 904; Sandock, 413 N.E.2d at 569; Burras, at 1365.

In the present case, substantial evidence of probative value exists to support the jury’s verdict and court’s judgment. The evidence shows that Kitchen entered into a lease agreement with B and S to rent a tract of land and building. The evidence also shows that although a specific date of occupancy was not established, the agreement clearly contemplated that occupancy would begin around June 1, 1985, or as soon as possible thereafter.. However, because of rain and other circumstances the building was not completed substantially and occupancy was not possible until August 1, 1985. B and S notified Kitchen that Kitchen could occupy the building starting on August 1, 1985. In accordance with the lease agreement, the rent payments became due on the first of the month beginning on September 1, 1985. In addition, B and S advised Kitchen that if any other changes were required, B and S would comply with Kitchen’s requests. Kitchen, however, refused to honor the contract by not occupying the building or paying rent. Based upon this evidence the jury could have determined that B and S fulfilled its contract requirements by substantially completing the building and by delivering possession to Kitchen within a reasonable time after June 1, 1985. Furthermore, the jury could have determined that Kitchen breached the contract by refusing to occupy and pay rent. Therefore, the trial court did not err by entering judgment in favor of B and S.

Kitchen argues that B and S did not fulfill the contract obligations and that a jury’s verdict so holding was contrary to law. Specifically, Kitchen suggests that the jury could not have found that B and S substantially fulfilled all the provisions of the contract. Kitchen is mistaken, and the arguments forwarded merely request that the court reweigh the evidence. This the court cannot do.

Kitchen first suggests that the jury could not have found that B and S complied with the time mandates of the contract. Kitchen relies upon section 1.44 of the lease agreement which provides that, “Time is of the essence of this agreement.” Record at 58. Pursuant, to this section Kitchen argues that since construction of the building was not substantially completed and occupancy was not possible on June 1, 1985, the contract was void. Kitchen’s argument fails.

Kitchen failed to point out several other provisions of the contract which clearly establish that the contract was not void. Section 1.02 of the contract provides as follows:

“Section 1.02. If Lessor shall be unable for any reason whatsoever to deliver possession of the leased premises on the commencement date of the term hereof, it shall not be liable to Lessee for any damages caused thereby, nor shall this lease thereby become void or voidable, nor shall the term hereof in any way be extended, but in such event Lessee shall not be liable for any rent until such time as Lessor can and does deliver possession.”

Record at 46. This provision clearly contradicts Kitchen’s interpretation of the contract. In addition, section 1.43 of the contract provides that:

“Section 1.43. Neither Lessor nor Lessee shall be required to perform any term, condition, or covenant in this lease so long as such performance is delayed or prevented by any acts of God, strikes,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Heredia v. Sandler
605 N.E.2d 1212 (Indiana Court of Appeals, 1993)
P.C. Management, Inc. v. Page Two, Inc.
573 N.E.2d 434 (Indiana Court of Appeals, 1991)
BARTHOLOMEW CTY. BEV. CO. v. Barco Beverage Corp., Inc.
524 N.E.2d 353 (Indiana Court of Appeals, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
513 N.E.2d 1246, 1987 Ind. App. LEXIS 3123, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kitchen-jewels-inc-v-beck-indctapp-1987.