Kingston Constructors, Inc. v. Washington Metropolitan Area Transit Authority

860 F. Supp. 886, 1994 U.S. Dist. LEXIS 12040, 1994 WL 461763
CourtDistrict Court, District of Columbia
DecidedAugust 22, 1994
DocketCiv. A. 93-1812 SSH
StatusPublished
Cited by12 cases

This text of 860 F. Supp. 886 (Kingston Constructors, Inc. v. Washington Metropolitan Area Transit Authority) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kingston Constructors, Inc. v. Washington Metropolitan Area Transit Authority, 860 F. Supp. 886, 1994 U.S. Dist. LEXIS 12040, 1994 WL 461763 (D.D.C. 1994).

Opinion

OPINION

STANLEY S. HARRIS, District Judge.

Before the Court are plaintiffs motion for partial summary judgment, defendant’s opposition thereto and its cross-motion for summary judgment, and the parties’ responses and replies to those pleadings. Summary judgment may be granted only “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.P. 56(c). In considering a summary judgment motion, all evidence and the inferences to be drawn from it must be considered in a light most favorable to the nonmoving party. See Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 1356, 89 L.Ed.2d 538 (1986). Summary judgment cannot be granted “if the evidence is such that a reasonable jury could return a verdict for the nonmoving party.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986). Upon consideration of the entire record, the Court denies plaintiffs motion for partial summary judgment and grants defendant’s motion for summary judgment. Although “findings of fact and conclusions of law are unnecessary on decisions of motions under Rule 12 or 56,” the Court nonetheless sets forth its analysis. See Fed.R.Civ.P. 52(a).

*887 Background

Plaintiff Kingston Constructors, Inc., (“Kingston”) and defendant Washington Metropolitan Area Transit Authority (‘WMA-TA”) entered into three separate contracts (Nos. 1Z1049, 1Z7041, and 1Z704A, hereinafter, “the Kingston Colitracts”) between February 23, 1988, and April 4, 1991. These contracts were for the design, procurement, fabrication, and installation of traction power equipment and cabling for traction power substations and tiebreaker stations. Throughout the performance of these contracts, plaintiff performed extra work and incurred additional costs. In an effort to recover the additional costs from defendant under the “Changes” and “Differing Site Conditions” clauses in the above-mentioned contracts, Kingston submitted claims to WMATA, and appealed the denial of these claims to the Corps of Engineers Board of Contract Appeals (“BCA”).

On August 11, 1992, Kingston and WMA-TA met to negotiate a settlement of the outstanding claims docketed by the BCA as ENG BCA Nos. 5836, 5963, 5954, and 5955. A handwritten contract agreement (“Settlement Agreement”) was prepared whereby WMATA agreed to pay Kingston a liquidated sum of $554,000.00 for settlement of the claims. George Schlesinger, president of Kingston, negotiated and signed the Settlement Agreement on behalf of Kingston, and Francis “Buddy” Watson negotiated, signed, and executed the Settlement Agreement on behalf of WMATA. At the bottom of the Settlement Agreement was written “Pay within 90 days.” With the 90 days running from August 11, 1992, payment was due by November 10, 1992.

At the negotiations, Watson represented that he was authorized by WMATA to negotiate a settlement amount with Kingston. However, Watson understandably informed Schlesinger that he was required to submit the settlement amount to WMATA’s internal funding and review process in order to obtain approval by WMATA’s Board of Directors.

On August 20, 1992, Jeffrey Wharton, Kingston’s Vice President and Managing Partner, signed and forwarded to WMATA a document entitled “MEMORANDUM OF CONTRACT CLOSEOUT AND OTHER CONTRACT ACTIONS” which formalized the Settlement Agreement for the Kingston contracts. The Memorandum included language stating that WMATA agreed “to make payments to [the] Contractor on or before November 10,1992.” However, WMATA declined to sign the Memorandum. Thereafter, a second “MEMORANDUM OF CONTRACT CLOSEOUT AND OTHER CONTRACT ACTIONS” was drafted to memorialize the Settlement Agreement of August 11, 1992. This version was virtually identical to the August 20, 1992, proposed Memorandum (some of the numbers were slightly changed), except that the line indicating when payment was to be made was changed to require WMATA to “make every reasonable effort to make payments to [the] Contractor by November 10, 1992.” Both parties signed the Memorandum on September 2, 1992.

Defendant paid the settlement amount to plaintiff in three installments on May 14, 1993 ($479,000.00), June 4, 1993 ($50,000.00), and June 11, 1993 ($25,000.00). On August 27, 1993, plaintiff filed suit claiming that defendant breached the Settlement Agreement by failing to make payment within 90 days of executing the Settlement Agreement (by November 10, 1992). Plaintiff seeks to recover $33,240.00 in prejudgment interest from defendant WMATA.

Plaintiff now moves for partial summary judgment on the grounds that defendant WMATA is liable for prejudgment interest for defendant’s breach of the Settlement Agreement under both federal and District of Columbia law. Defendant moves for summary judgment on all claims on the ground that WMATA is shielded from awards of prejudgment interest by sovereign immunity, or, alternatively, that there is no contractual basis for liability. 1

*888 Analysis

The dispositive issue is whether defendant WMATA is liable for awards of prejudgment interest. In denying plaintiffs motion for partial summary judgment and granting defendant’s motion for summary judgment, the Court holds that WMATA has sovereign immunity against awards of prejudgment interest for actions taken in its contract negotiating capacity.

WMATA is an instrumentality of each of the signatories—Maryland, Virginia, and the District of Columbia—to the Compact that created WMATA. D.C.Code Ann. § 1-2431 (1981) (‘WMATA Compact”). WMA-TA’s sovereign immunity exists because the signatories have successfully conferred their respective sovereign immunities upon it. Morris v. WMATA, 781 F.2d 218 (D.C.Cir.1986). It is well-settled that a sovereign is immune from liability for interest unless it has waived its immunity by statute or contract. Library of Congress v. Shaw, 478 U.S. 310, 106 S.Ct. 2957, 92 L.Ed.2d 250 (1986). See George Hyman Constr. Co. v. WMATA, 816 F.2d 753 (D.C.Cir.1987).

There are two exceptions to sovereign immunity from awards of prejudgment interest. Spawn v. Western Bank-Westheimer, 989 F.2d 830, 833 (5th Cir.1993), cert, denied, - U.S. -, 114 S.Ct. 1048, 127 L.Ed.2d 371 (1994). First, sovereign immunity can be waived when there is an express contractual or statutory provision consenting to awards of prejudgment interest. Shaw, 478 U.S. at 311-13, 106 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harris v. Wmata
District of Columbia, 2020
Professional Management Consulting Services, LLC
Armed Services Board of Contract Appeals, 2020
Delta Engineering, Inc.
Armed Services Board of Contract Appeals, 2014
Banneker Ventures, LLC v. Graham
20 F. Supp. 3d 184 (District of Columbia, 2013)
Commonwealth of Virginia, etc. v. AMEC Civil, LLC
677 S.E.2d 633 (Court of Appeals of Virginia, 2009)
AMEC Civil, LLC v. Commonwealth of Virginia, etc.
Court of Appeals of Virginia, 2009
Martin v. Washington Metropolitan Area Transit Authority
273 F. Supp. 2d 114 (District of Columbia, 2003)
Bhargava v. Veneman
143 F. Supp. 2d 16 (District of Columbia, 2001)
Gilbert v. Federal Deposit Insurance
950 F. Supp. 1194 (District of Columbia, 1997)
Jones v. Washington Metropolitan Area Transit Authority
946 F. Supp. 1023 (District of Columbia, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
860 F. Supp. 886, 1994 U.S. Dist. LEXIS 12040, 1994 WL 461763, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kingston-constructors-inc-v-washington-metropolitan-area-transit-dcd-1994.