King v. United States

220 F. Supp. 350, 12 A.F.T.R.2d (RIA) 5483, 1963 U.S. Dist. LEXIS 7722
CourtDistrict Court, E.D. Texas
DecidedJuly 31, 1963
DocketCiv. A. No. 775
StatusPublished
Cited by1 cases

This text of 220 F. Supp. 350 (King v. United States) is published on Counsel Stack Legal Research, covering District Court, E.D. Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
King v. United States, 220 F. Supp. 350, 12 A.F.T.R.2d (RIA) 5483, 1963 U.S. Dist. LEXIS 7722 (E.D. Tex. 1963).

Opinion

SHEEHY, Chief Judge.

This is a tax refund case in which the Plaintiffs are seeking to recover income taxes and interest thereon that they contend were wrongfully assessed against and collected from them for the year 1955 by the Commissioner of Internal Revenue, hereinafter referred to as Commissioner.

This case was submitted to the Court on a Stipulation of Facts entered into by the parties and filed in this cause. Such Stipulation of Facts is adopted as the Findings of Fact herein, and only such of those facts as are deemed necessary to an understanding of the Court’s decision will be stated in this opinion.

The Plaintiff, Frank L. King, Jr., d/b/a King Construction Company, hereinafter referred to as the Construction Company, was engaged in the general construction business as a proprietor from 1951 through August 31, 1955. On November 23, 1955, the Housing Authority of the City of Texarkana, Texas, hereinafter referred to as the Housing Authority, under a loan contract with the Public Housing Authority, a Federal agency hereinafter referred to as PHA, entered into a written building contract in the original amount of $937,068.00 with the Construction Company. This contract, designated as Project TEX 14-3, called for the construction of 21 buildings consisting of 125 dwelling units and other facilities to be completed in 400 calendar days.

A notice to the Construction Company to proceed on the contract was issued by the Housing Authority on November 23, 1953. This notice provided that the work under the contract was to commence on November 24, 1953, and established the completion date of the contract as December 28,1954. The Construction Company, as prime contractor and through various [351]*351sub-contractors, proceeded to construct the buildings and other facilities which were the subject of Project TEX 14-3. All of the work on said Project TEX 14-3 was subject to the approval and acceptance thereof by the Housing Authority and PHA.

On December 9, 1954, a final inspection was made by the Construction Supervisor; Mechanical Engineer of PHA’s Field Office; an architect’s representative ; the contractor’s superintendent; the contractor; the timekeeper and Project Engineer for PHA. As a result of this inspection, the contract items yet to be completed or corrected were set forth on a “punch list” and given to the Construction Company. Included among the many items on the punch list was one requiring the finishing of the rolling of the asphalt streets covered by the contract.

By December 13, 1954, all of the buildings and other facilities to be constructed under the contract had been completed and accepted by the Housing Authority except for the completion of several items set forth on the punch list and the completion of the rolling of the asphalt street surface as provided in the contract specifications. By December 31, 1954, all of the work under the contract was completed and accepted by the Housing Authority except for the completion of the asphalt street surface as provided for in the contract specifications. Because of cold weather and lack of traffic, the Construction Company was required to reroll the asphalt street surface when the weather turned warm before that portion of the work could be accepted. The Housing Authority withheld the sum of $750.00 until the rerolling of the asphalt street surface was done. The completion of the rerolling of the asphalt street surface was done in the late Spring of 1955 by Bruce Kennedy Sand and Gravel Company of Texarkana, Texas, to whom the work of street construction had been subcontracted, at a cost of $510.00. Said sum of $510.00 was not paid to the Bruce Kennedy Sand & Gravel Company by the Construction Company until December 31, 1955.

On January 7, 1955, by transmittal letter of the same date, the Executive Director of the Housing Authority forwarded to PHA in Fort Worth, Texas, executed copies of Certificate of Completion — Part I, the Certificate and Release executed by the Construction Company and the Schedule of Change Orders called for in the contract. The Certificate of Completion ■ — Part I, certified to by the Executive Director of the Housing Authority, on December 31,1954, certified that all work covered by the contract was actually completed on December 28, 1954, except for two items. One of the items excepted was the completion of the asphalt street surface. Said Certificate of Completion —Part I was approved by PHA on January 17, 1955.

On December 20, 1954, the first occupancy of said Housing Project commenced. On January 27, 1955, the Executive Director of the Housing Authority executed a notice of full availability of this project as of the last day of December 1954. This notice was duly approved by PHA on January 31,1955.

On November 14, 1955, the Certificate of Completion — Part II was executed by the Housing Authority and approved by PHA on November 30, 1955. This Certificate of Completion shows that as of November 17, 1955, the Construction Company was due a final payment on the construction of $750.00. The sum of $750.00 was paid the Construction Company on November 18, 1955.

The total job costs for the construction was $863,124.16. As of December 31, 1954, the total job costs which had been paid by the Construction Company were $862,614.16. The total amount of job cost remaining unpaid as of December 31, 1954, was the sum of $510.00' which represented the cost of the completion of the asphalt streets. As above indicated, this cost was paid on December 31, 1955.

As of December 31,1954, the Construction Company had received or accrued' [352]*352the entire amount of the contract price with the exception of $750.00, which was the amount withheld pending the completion of the rerolling of the asphalt streets. All money due under the contract was received by the Construction Company in 1954 except the amount of $52,252.75 representing retainage, which was received •on January 10,1955, the sum of $6,875.00 representing retainage, which was received on February 10,1955, and the sum ■of $750.00 which was paid on November 18, 1955, for the work performed in connection with the rerolling of the asphalt streets in the late Spring of 1955.

The Plaintiffs in their business during the periods involved and the years prior thereto consistently used the “completed ■contract method” of accounting for reporting income and expenditures for their general construction business.

On April 16, 1956, the Plaintiffs filed their joint income tax return for the ■calendar year 1955 reporting a tax liability of $11,366.46, which liability was duly ■discharged. The income earned from Project TEX 14-3 was not reported by the Plaintiffs in that return.

On September 1, 1955, the King Construction Company, a Texas corporation, was formed. This corporation was the .successor to the proprietorship herein referred to as Construction Company. The construction contract, known as Project TEX 14-3, was transferred to the new •corporation. The income from Project TEX 14-3 was reported by the corporation on its 1955 corporate tax return.

The 1955 tax returns of the corporation and the Plaintiffs were audited by the Internal Revenue Service, and it was determined that the income and profit from Project TEX 14-3 should have been reported by the Plaintiffs on their 1955 joint tax return rather than by the corporation. This adjustment plus other adjustments not in dispute herein produced a deficiency in taxes due from the Plaintiffs for the year 1955 in the amount •of $68,807.21 which was duly paid by the Plaintiffs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

A. S. Wikstrom, Inc. v. Commissioner
1969 T.C. Memo. 32 (U.S. Tax Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
220 F. Supp. 350, 12 A.F.T.R.2d (RIA) 5483, 1963 U.S. Dist. LEXIS 7722, Counsel Stack Legal Research, https://law.counselstack.com/opinion/king-v-united-states-txed-1963.