A. S. Wikstrom, Inc. v. Commissioner

1969 T.C. Memo. 32, 28 T.C.M. 143, 1969 Tax Ct. Memo LEXIS 265
CourtUnited States Tax Court
DecidedFebruary 13, 1969
DocketDocket No. 5578-67.
StatusUnpublished
Cited by1 cases

This text of 1969 T.C. Memo. 32 (A. S. Wikstrom, Inc. v. Commissioner) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
A. S. Wikstrom, Inc. v. Commissioner, 1969 T.C. Memo. 32, 28 T.C.M. 143, 1969 Tax Ct. Memo LEXIS 265 (tax 1969).

Opinion

A.S. Wikstrom, Inc. v. Commissioner.
A. S. Wikstrom, Inc. v. Commissioner
Docket No. 5578-67.
United States Tax Court
T.C. Memo 1969-32; 1969 Tax Ct. Memo LEXIS 265; 28 T.C.M. (CCH) 143; T.C.M. (RIA) 69032;
February 13, 1969, Filed
John D. Bryant, 2-4 Fennell St., Skaneateles, N. Y., for the petitioner. Stephen M. Miller, for the respondent. 144

DAWSON

Memorandum Findings of Fact and Opinion

DAWSON, Judge: Respondent determined income tax deficiencies against the petitioner for the years 1959 and 1962 in the amounts of $701,927.78 and $91,274.44, respectively.

Petitioner alleges in its petition a net operating loss for 1962, which may be carried back to 1959, greater than the amount determined by respondent and therefore claims that it is entitled to an additional refund of 1959 tax paid of $161,041.93.

Several adjustments contained in the notice of deficiency were not put in issue by the petitioner. The issues presented for decision are:

1. In what year were the Soo and Kittery long-term contracts finally*266 completed and accepted for purposes of the completed contract method of accounting?

2. Should amounts received by petitioner in settlement of disputed claims relating to the Soo and Kittery long-term contracts for extras, changes, changed conditions, suspensions, delays and damages, not a part of the original contract work, be accrued as income in 1962 when the contract work was completed or in later years in which the respective claims were settled?

3. Should an amount withheld by the Navy for payments otherwise due to petitioner on account of possible liquidated damages for delay in completing the Kittery contract work be accrued as income in 1962 when the contract work was completed or in 1963 when settled and payment made?

4. Should an amount withheld by the Corps of Engineers on account of Michigan tax liability from payments otherwise due to petitioner for the Soo contract be accrued as income in 1962 when the contract work was completed or in 1965 when settled and payment made?

Findings of Fact

Many of the facts have been stipulated by the parties. The stipulation of facts and the exhibits attached thereto are incorporated herein by this reference.

A. S. Wikstrom, *267 Inc. (herein called petitioner) is a New York corporation which has had at all times material hereto (including the date on which the petition in this proceeding was filed) its principal place of business in Skaneateles, New York.

Petitioner filed its original Federal corporate income tax returns for the calendar years 1959 and 1962, and an amended return for the year 1962, with the then district director of internal revenue, Syracuse, New York. On its original 1962 return petitioner claimed a net operating loss of $836,537.73, while on its amended 1962 return the net operating loss was increased to $1,351,889.65. The net operating losses shown on petitioner's original and amended returns for 1962 were claimed as carrybacks to petitioner's taxable year 1959, as a result of which refunds were made for 1959 in the total amount of $702,982.61.

Petitioner is a construction contractor in the business of building roads, bridges, power plants and industrial facilities, principally throughout the eastern half of the United States. Although petitioner is an accrual basis taxpayer in all other respects, it reports its income and expense from long-term contracts on the completed contract*268 method. Petitioner received approval from respondent to report its income from long-term contracts under the completed contract method of accounting, commencing for the year 1960. Prior to 1960, petitioner reported its income from long-term contracts under the percentage of completion method.

In 1960, petitioner undertook two multiyear construction contracts. One such contract was awarded by the Corps of Engineers, U.S. Army, for work at Sault Ste. Marie, Michigan (herein referred to as the "Soo" contract); the other such contract was awarded by the Bureau of Yards and Docks, U.S. Navy, for work at Kittery, Maine (herein referred to as the "Kittery" contract). In the performance of construction contracts (in which business petitioner has been engaged for more than 20 years) extras, changes, changed conditions and delays, not a part of the original contract work, commonly arise which are the basis of claims by contractors for additional compensation. One of the reasons for this is that it is impossible to establish exact quantities when drawing up plans and specifications and it is impossible to design and project perfectly. It is standard practice to have disputes between the parties*269 as a result of these claims. In Federal government contracts provisions are made for determination of such claims. Both the Soo and Kittery contracts contained provisions for changes, changed conditions and procedures 145 for resolutions of disputes. Claims are frequently settled as they arise or before completion of the physical contract work. However, some of such claims often remain unsettled at the time of completion of the physical contract work. Resolution of such unsettled claims may not be achieved until months or years after completion of the physical contract work through negotiation, administrative procedures and litigation.

Soo Contract

The Soo contract, No. DA-20-064-CIVENG-61-41, dated December 22, 1960, was for the original contract amount of $4,947,950. The work required was first stage construction of a navigation lock, principally involving cofferdam construction, demolition and excavation of an existing lock. The entire work was required to be completed by January 1, 1963.

In May 1962, the Corps of Engineers suspended a major portion of the work under the contract and, in June 1962, most of the remainder of the work was deleted due to the Corps' desire*270 to redesign the project.

The Corps of Engineers, by letter dated March 1, 1963, accepted the entire Soo contract work as completed November 23, 1962. The letter stated that although the work was completed "because of outstanding claims, the subject of other correspondence, the contract will not be closed."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
1969 T.C. Memo. 32, 28 T.C.M. 143, 1969 Tax Ct. Memo LEXIS 265, Counsel Stack Legal Research, https://law.counselstack.com/opinion/a-s-wikstrom-inc-v-commissioner-tax-1969.