King v. Mahaska County

39 N.W. 636, 75 Iowa 329, 1888 Iowa Sup. LEXIS 338
CourtSupreme Court of Iowa
DecidedOctober 3, 1888
StatusPublished
Cited by6 cases

This text of 39 N.W. 636 (King v. Mahaska County) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
King v. Mahaska County, 39 N.W. 636, 75 Iowa 329, 1888 Iowa Sup. LEXIS 338 (iowa 1888).

Opinion

Rothrock, J.

1. Counties: contract for courthouse: in excess of amount voted: ultra vires. — I. Provision had been made for the erection of the courthouse by a vote of the people the county, authorizing the expenditure of seventy-five thousand dollars for that purpose, and, by the written - contract between the parties, the plaintiff undertook to furnish all the materials and erect the building for that sum. As has been said, the house was to be completed by May 1, 1883, and the contract contained the further provision that if it should not be completed by the first day of November, 1883, then the second party (the county) might employ the necessary workmen, purchase material and complete the work, and deduct the reasonable cost thereof from .the amount which would otherwise be due the plaintiff. The plaintiff was to do the work according to certain plans and specifications, and under the direction of a superintendent of construction, whose determination as to quality of material and manner of workmanship should be final and conclusive between the parties. Payments were to be made upon monthly estimates made by the superintendent or architect, less ten per cent, to be retained until the completion of said building by the party of the first part in accordance with the terms of the contract. The plaintiff claims that he was without fault in failing to complete the building by the time stipulated in the contract, and that such failure occurred solely by reason of the wrongful and corrupt acts of the architect in making insufficient monthly estimates, in rejecting suitable material, and in fraudulently making second estimates, reducing and cutting down estimates that had been already allowed and paid; and that the failure to promptly pay the estimates actually made, and the [332]*332various wrongful, fraudulent and corrupt acts of the architect, delayed the work and the completion of the building. As we have stated, the contract price for the erection of the building was seventy-five thousand dollars, — the full amount of money authorized by the vote of the people. The contract contained the following provision: “ If any alteration should hereafter be made by order of the said party of the second part, varying from the said plans and specifications, either by adding thereto or diminishing therefrom, or otherwise, such alterations shall not vacate this contract; but the value thereof shall be estimated by said superintendent, and added to or deducted from the sum herein agreed to be paid for said building, as the case may be. Nor shall such alterations supersede the conditions for the completion of the whole or several parts of said building by the times hereinbefore provided.” The first work done was the excavation for the foundation. The architect directed the deepening of the trenches beyond the plans adopted, for which he allowed the plaintiff over four hundred dollars. The deepening of the excavation made a corresponding increase in the height of the foundation wall necessary. The architect ordered the wall to be raised, for which he allowed seven hundred and seventy-seven dollars. After the foundation wall was put in according to the plans, the architect ordered it to be taken out, because it was thought to be not thick and solid enough to support the superstructure. A new and heavier wall, of different stone, was substituted, under an agreement that plaintiff should receive forty-six hundred and twenty dollars therefor. These additional expenditures were allowed and paid for, less the ten per cent, retained under the provisions of the contract. These items of extras would have increased the contract price for the building several thousand dollars above the seventy-five thousand authorized by the vote of the people. The defendant, by an amendment to its answer, set out the above sums as having been paid by the county for extra work, and made the following averments in relation thereto: [333]*333“ Said sums were all illegally paid, and paid, in violation of law, on contracts made in excess of said seventy-five thousand dollars, and made after said. original seventy-five thousand dollar contract had been made. Defendant asks that said sums be applied in payment of the amounts due on the original contract, and ask judgment for any balance that may be left, after so applying the said sums, as an offset.”

It will thus be seen that one of the issues presented was whether these extras, and the subsequent contracts in relation thereto, were void as being in excess of the seventy-five thousand dollars authorized to be expended. The court instructed the jury in relation thereto as follows: “Under the law and the record of the vote of the electors of Mahaska county, its board of supervisors, had power to erect a courthouse in the city of Oskaloosa,. Iowa, and to make orders or contracts therefor, or in relation thereto, to the extent of an aggregate cost of seventy-five thousand dollars ; but such board had no power to make orders and contracts for a courthouse the probable cost of which exceeded this sum. And if you find that the board, after making the written contract of date July 21, 1881, made supplemental or additional contracts or orders for changes, increasing the cost beyond seventy-five thousand dollars, the board exceeded its power, and such supplemental or additional contracts and orders are absolutely void, and do not bind the defendant; but in as far as you find any alleged subsequent contract for changes in said building, extension of time for its erection, or other purposes, in relation thereto, proven, whether the same was in writing or not in writing, if it had not the effect to increase the cost of the building above seventy-five thousand dollars, it was authorized, and binds defendant. Should you find that the plaintiff, under the supplemental contract of May 3, 1882, removed a part of the foundation, which he had constructed under the first contract of date July 21, 1881, and substituted a more expensive foundation, • you should allow what is not shown *to be paid for the first contract price of the foundation, or such part as the [334]*334plaintiff constructed thereof prior to his being put off of the building, but no more, for the first construction, its removal and the second construction.” It will be observed from the extract from the contract above set out that the alterations contemplated not only adding to the price, but diminishing therefrom, and that such alterations should not vacate the contract. But the evidence does not show that any changes were at any time contemplated by the parties which would have the effect to diminish the cost from the plans adopted. The plaintiff claims that additional contracts or orders for changes were made, which increased the cost of the building more than ten thousand dollars in addition to the contract price of seventy-five thousand dollars. These additional contracts were clearly illegal and void. The law provides that a board of supervisors have no power to order the erection of a courthouse, where the probable cost will exceed five thousand dollars, without a vote of the people. In this case, the authority given by the vote authorized an expenditure of seventy-five thousand dollars. The plaintiff contracted to erect the building for that sum. He appears to have been an experienced contractor and builder. According to his own claim, some ten thousand dollars was added to the cost of the building, and contracts were made therefor before he completed the basement. This addition to the cost is founded upon illegal and void contracts, which he and the members of the board knew to be void, not as being charged with a knowledge of the law, but they knew as a fact that these contracts were illegal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grady v. City of Livingston
141 P.2d 346 (Montana Supreme Court, 1943)
State Ex Rel. Schlegel v. Munn
250 N.W. 471 (Supreme Court of Iowa, 1933)
Jacks v. Taylor
142 P. 121 (California Court of Appeal, 1914)
Seaman v. Cap-Au-Gris Levee District
117 S.W. 1084 (Supreme Court of Missouri, 1909)
Sparks v. Jasper County
112 S.W. 265 (Supreme Court of Missouri, 1908)
Price v. Garland
4 N.M. 365 (New Mexico Supreme Court, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
39 N.W. 636, 75 Iowa 329, 1888 Iowa Sup. LEXIS 338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/king-v-mahaska-county-iowa-1888.