Kinetic Systems Inc., Plaintiff v. IPS-Integrated Project Services, LLC and Lonza Biologics, Inc., Defendants

2021 DNH 031
CourtDistrict Court, D. New Hampshire
DecidedJune 4, 2021
Docket20-cv-1125-SM
StatusPublished
Cited by1 cases

This text of 2021 DNH 031 (Kinetic Systems Inc., Plaintiff v. IPS-Integrated Project Services, LLC and Lonza Biologics, Inc., Defendants) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kinetic Systems Inc., Plaintiff v. IPS-Integrated Project Services, LLC and Lonza Biologics, Inc., Defendants, 2021 DNH 031 (D.N.H. 2021).

Opinion

UNITED STATES DISTRICT COURT

DISTRICT OF NEW HAMPSHIRE

Kinetic Systems Inc., Plaintiff

v. Case No. 20-cv-1125-SM Opinion No. 2021 DNH 031

IPS-Integrated Project Services, LLC and Lonza Biologics, Inc., Defendants

O R D E R

Kinetic Systems, Inc. brings this action for breach of

contract and quantum meruit, seeking nearly $14 million it

claims to be owed for work it performed on a construction

project in Portsmouth, New Hampshire. In its complaint, Kinetic

advances three claims: breach of contract against the project’s

general contractor, Integrated Project Services (“IPS”) (count

one); quantum meruit/unjust enrichment against IPS (count two);

and, in the alternative, quantum meruit/unjust enrichment

against the project owner, Lonza Biologics (count three).

Defendants move to dismiss, saying Kinetic’s claims are

premature. In short, defendants allege that Kinetic has failed

to follow contractually-mandated prerequisites to filing suit. For the reasons discussed, defendants’ motion to dismiss is

granted in part and denied in part.

Standard of Review

In considering a motion to dismiss, the court accepts all

well-pled facts alleged in the complaint as true, disregarding

legal labels and conclusions, and resolves reasonable inferences

in the plaintiff’s favor. See Galvin v. U.S. Bank, N.A., 852

F.3d 146, 155 (1st Cir. 2017). To avoid dismissal, the

complaint must allege sufficient facts to support a “plausible”

claim for relief. See Ashcroft v. Iqbal, 556 U.S. 662, 678

(2009). To satisfy the plausibility standard, the factual

allegations in the complaint, along with reasonable inferences,

must show more than a mere possibility of liability – that is,

“a formulaic recitation of the elements of a cause of action

will not do.” Bell Atl. Corp. v. Twombly, 550 U.S. 544, 555

(2007). See also Lyman v. Baker, 954 F.3d 351, 359–60 (1st Cir.

2020) (“For the purposes of our [12(b)(6)] review, we isolate

and ignore statements in the complaint that simply offer legal

labels and conclusions or merely rehash cause-of-action

elements.”) (citation and internal punctuation omitted).

In other words, the complaint must include well-pled (i.e.,

non-conclusory, non-speculative) factual allegations that, if

2 assumed to be true, allow the court to draw the reasonable and

plausible inference that the plaintiff is entitled to the relief

sought. See Tasker v. DHL Ret. Savings Plan, 621 F.3d 34, 38-39

(1st Cir. 2010).

Background

Integrated Project Services (“IPS”) was the general

contractor for a construction project owned by Lonza Biologics

in Portsmouth, New Hampshire. Kinetic was a subcontractor on

that project.

IPS and Kinetic entered into two contracts related to the

Portsmouth project. The first was signed in December of 2018,

and concerns mechanical work and plumbing services to be

supplied by Kinetic (document no. 9-3) (the “Early Mechanical

Contract”). The contract provides that, in exchange for its

services, Kinetic will be paid a fixed sum of $2,376,659. The

second contract was signed in April of 2019, and concerns piping

work to be supplied by Kinetic (document no. 9-4) (the “Process

Contract”). That contract provides that, in exchange for its

services, Kinetic will be paid a fixed sum of $1,800,000.

As is customary in the construction industry, both

contracts provide a mechanism by which the parties agreed to

3 resolve issues arising from any changes to the scope of

Kinetic’s work, including the amount Kinetic would be paid for

additional work. Before performing any work beyond that

specified in the contracts, Kinetic is required to first give

IPS notice of a proposed change, submit documentation in support

of it, and obtain IPS’s agreement to it. See Early Mechanical

Contract at Section 6; Process Contract at Section 6. If the

parties are unable to agree upon a price for Kinetic’s

additional work, the contracts allow IPS to compel Kinetic to

perform the work (via “Change Directive”), after which the

parties are committed to agree upon an appropriate adjustment to

the amount to be paid to Kinetic. That process of negotiating,

implementing, and paying for change orders is generally referred

to as the “Section 6 Project Level Negotiations.”

If the parties are unable to fully resolve any

disagreements through the Section 6 Project Level Negotiations,

the contracts provide the means by which they will resolve any

lingering disputes. Section 12 of each contract, entitled

“Claims and Disputes between IPS and Subcontractor,” sets forth

a mandatory three-step dispute resolution process.

The claims or disputes “shall first be attempted to be resolved by good-faith negotiation between senior management of the Parties.”

4 Second, if that process is unsuccessful, “then the Parties agree to try in good faith to settle the claims or disputes (or remaining portion thereof) by mediation administered by the American Arbitration Association.”

Finally, if unresolved disputes remain, the contracts establish a bifurcated dispute resolution process, depending on the amount at issue.

For disputes involving amounts less than $250,000, the parties agree that such disputes shall be resolved by arbitration.

For disputes involving $250,000 or more, the parties agree that they may be resolved, at IPS’s election, by either arbitration or by civil litigation to be filed exclusively in the state or federal courts of the Commonwealth of Pennsylvania.

See Early Mechanical Contract at Section 12.2; Process Contract

at Section 12.2 (“Section 12 Dispute Resolution”) (emphasis

supplied).

The complaint alleges that Kinetic submitted, and IPS

approved, several large change orders for which Kinetic has not

yet been paid:

The Early Mechanical and Process contracts, as amended, are referred to herein as the Contracts. IPS implemented and the parties agreed to several large change orders under the Contracts pursuant to which Kinetics provided a substantial amount of additional labor and materials for consumption and/or use in Lonza’s building(s) and systems.

5 Defendant IPS repeatedly agreed that it would pay Kinetics for its material and labor costs associated with the Contracts, including all change orders.

Kinetics reasonably relied upon these promises and inducements in performing work and providing materials to [the project].

Complaint (document no. 1-2) at paras. 15-17 (emphasis

supplied). Moreover, the complaint alleges that Kinetic has

“complied with all material terms of the Contracts in providing

labor and material” to the project. Id. at para. 24. In total,

says Kinetic, it is owed approximately $3,650,000 under the

Early Mechanical Contract, and $10,320,000 under the Process

Contract. Id. at para. 21.

According to Kinetic, the parties are at an impasse:

Kinetic says it has complied with all of its contractual

obligations, yet IPS refuses to approve its requests for

payment. Moreover, IPS has ignored Kinetic’s request that IPS

Free access — add to your briefcase to read the full text and ask questions with AI