OPINION
RABINOWITZ, Justice.
• This appeal arises from the Department of Corrections’ award of a contract to Allvest, Inc. for the housing of minimum security prisoners in the Fairbanks area. KILA, Inc. (“KILA”), an unsuccessful bidder, contested the award, exhausted its administrative appeals, and then appealed to the superior court. The superior court affirmed the Department of Administration’s decision denying KILA’s protest. This appeal followed.
I.
FACTS AND PROCEEDINGS
In August 1988, the Department of Corrections (“DOC”) received authorization to seek proposals for a provider of professional services in the operation of an adult community
residential center in Fairbanks.
KILA and Allvest, Inc. (“Allvest”) submitted bids. DOC subsequently cancelled its original Request for Proposals (“RFP”), because a change in zoning requirements rendered All-vest’s proposal non-responsive, and because KILA submitted a bid beyond the amount of money that the State had allocated for the contract.
DOC issued a new RFP in August 1989.
At that time, Walter Majoros, the Director of Statewide Programs for DOC, was designated by the Commissioner of DOC, Susan Humphrey-Barnett, to serve as its procurement officer in the matter.
Majoros directed Benjamin J. Fewell, Jr., DOC’s Program Coordinator, to establish and sit as non-voting chair of a Proposal Evaluation Committee (“PEC”) for the purpose of evaluating proposals submitted by KILA and Allvest in response to the new RFP. DOC’s Criminal Justice Planner, Marianne McNabb, submitted suggestions on the “experience and geographic location required for a PEC member to have an adequate understanding" of the needs and limitations” of the residential center. However, she neither participated in the selection of individual PEC members nor contacted them regarding the evaluation of the bids.
Applying the RFP evaluation criteria, four of the PEC’s five voting members rated All-vest’s proposal higher than KILA’s. Based on the majority vote of the PEC, Fewell recommended to Majoros that DOC negotiate a contract with Allvest. DOC then issued a notice of intent to award a contract to Allvest. KILA protested the award.
After issuance of the notice of intent, PEC member Lew Reece submitted a memorandum to Humphrey-Barnett, alleging that Fe-well had imposed his own values on the PEC proceedings and skewed the outcome. He met with Ken Brown, DOC’s Northern Regional Director, and also with Humphrey-Barnett. Majoros immediately investigated Reece’s concerns, contacting the other PEC evaluators to determine if they thought Fe-well was biased. The other four voting members stated that they believed Fewell was impartial and that they had voted independently. Humphrey-Barnett concurred with Majoros’ determination that Reece’s allegations were unfounded.
Allvest’s original bid outlined a plan to develop a facility on Badger Road. After DOC issued the notice of intent to award the contract, local opposition to using the Badger Road site developed. Aware of the pressure regarding the location, DOC begán to discuss its options. Because Allvest had proposed a location that met both the requirements of the RFP and zoning requirements, retracting the intent to award could have caused severe difficulties. Fewell, therefore, advised Majo-ros not to cancel and re-bid but “to continue on course and try to reach a solution” that would provide for use of the proposed Badger Road location.
On November 21, 1989, DOC signed the contract with Allvest to commence January 1, 1990, giving Allvest approximately one month to bring the facility up to specifications.
On the same day Tanana Chiefs Conference, Inc. (“TCC”), the owner of record, was informed
by the United States Department of Housing and Urban Development (“HUD”) of potential lease problems involving the Badger Road location. As the hearing officer found, “There is no evidence outside of the viability of the TCC/HUD lease issue from which to conclude that Allvest was not a responsible proposer.” As public pressure increased, including substantial pressure on HUD, Allvest contacted a local real estate agent to research the availability of other locations. The agent discovered that KILA did not own the facility it was using and eventually a lease was executed between Allvest and the property owner that would enable Allvest to use the existing facilities.
DOC denied KILA’s bid protest on November 16, 1989. KILA appealed the denial of its protest on November 30, 1989. KILA also corresponded with Fewell, Humphrey-Barnett, and Larry McKinstry, an assistant attorney general, requesting “[rjeasonable notice of, and right to attend any and all State meetings addressing the Allvest contract modification requests, or the KILA contract dispute, or any meeting related to such.”
The Department of Administration granted KILA an administrative hearing to address the bid protest issues in dispute. A hearing was held from May 29 to June 2, 1990. Pursuant to the hearing officer’s recommendations, the Commissioner of the Department of Administration denied KILA’s appeal in September 1990.
KILA appealed the decision of the Department of Administration to the superi- or court. The superior court affirmed the Department of Administration’s decision, and this appeal followed. On appeal, KILA raises numerous specifications of error, ultimately seeking to have DOC re-bid the contract and pay KILA’s bid preparation costs.
II.
DISCUSSION
A.
Alleged Bias in the Bidding Process
When soliciting bids for goods and services, a government agency has an implied contractual duty to consider bids in a fair and honest manner:
[I]n exchange for a bidder’s investment of the time and resources involved in bid preparation, a government agency must be held to an implied promise to consider bids honestly and fairly. Breach of this implied contract on the part of an agency entitles a disappointed bidder to recover the costs incurred in preparation of the bid.... [T]he “reasonable basis” standard for review of administrative decisions,
see Jager v. State,
537 P.2d 1100, 1107-08 (Alaska 1975);
Kelly v. Zamarello,
486 P.2d 906, 916-17 (Alaska 1971), is applicable in this situation.[
]
See Keco Industries, Inc. v. United States,
[203 Ct.Cl. 566], 492 F.2d 1200, 1203-04 (1974).
King v. Alaska State Hous. Auth.,
633 P.2d 256, 263 (Alaska 1981)
(King II).
Free access — add to your briefcase to read the full text and ask questions with AI
OPINION
RABINOWITZ, Justice.
• This appeal arises from the Department of Corrections’ award of a contract to Allvest, Inc. for the housing of minimum security prisoners in the Fairbanks area. KILA, Inc. (“KILA”), an unsuccessful bidder, contested the award, exhausted its administrative appeals, and then appealed to the superior court. The superior court affirmed the Department of Administration’s decision denying KILA’s protest. This appeal followed.
I.
FACTS AND PROCEEDINGS
In August 1988, the Department of Corrections (“DOC”) received authorization to seek proposals for a provider of professional services in the operation of an adult community
residential center in Fairbanks.
KILA and Allvest, Inc. (“Allvest”) submitted bids. DOC subsequently cancelled its original Request for Proposals (“RFP”), because a change in zoning requirements rendered All-vest’s proposal non-responsive, and because KILA submitted a bid beyond the amount of money that the State had allocated for the contract.
DOC issued a new RFP in August 1989.
At that time, Walter Majoros, the Director of Statewide Programs for DOC, was designated by the Commissioner of DOC, Susan Humphrey-Barnett, to serve as its procurement officer in the matter.
Majoros directed Benjamin J. Fewell, Jr., DOC’s Program Coordinator, to establish and sit as non-voting chair of a Proposal Evaluation Committee (“PEC”) for the purpose of evaluating proposals submitted by KILA and Allvest in response to the new RFP. DOC’s Criminal Justice Planner, Marianne McNabb, submitted suggestions on the “experience and geographic location required for a PEC member to have an adequate understanding" of the needs and limitations” of the residential center. However, she neither participated in the selection of individual PEC members nor contacted them regarding the evaluation of the bids.
Applying the RFP evaluation criteria, four of the PEC’s five voting members rated All-vest’s proposal higher than KILA’s. Based on the majority vote of the PEC, Fewell recommended to Majoros that DOC negotiate a contract with Allvest. DOC then issued a notice of intent to award a contract to Allvest. KILA protested the award.
After issuance of the notice of intent, PEC member Lew Reece submitted a memorandum to Humphrey-Barnett, alleging that Fe-well had imposed his own values on the PEC proceedings and skewed the outcome. He met with Ken Brown, DOC’s Northern Regional Director, and also with Humphrey-Barnett. Majoros immediately investigated Reece’s concerns, contacting the other PEC evaluators to determine if they thought Fe-well was biased. The other four voting members stated that they believed Fewell was impartial and that they had voted independently. Humphrey-Barnett concurred with Majoros’ determination that Reece’s allegations were unfounded.
Allvest’s original bid outlined a plan to develop a facility on Badger Road. After DOC issued the notice of intent to award the contract, local opposition to using the Badger Road site developed. Aware of the pressure regarding the location, DOC begán to discuss its options. Because Allvest had proposed a location that met both the requirements of the RFP and zoning requirements, retracting the intent to award could have caused severe difficulties. Fewell, therefore, advised Majo-ros not to cancel and re-bid but “to continue on course and try to reach a solution” that would provide for use of the proposed Badger Road location.
On November 21, 1989, DOC signed the contract with Allvest to commence January 1, 1990, giving Allvest approximately one month to bring the facility up to specifications.
On the same day Tanana Chiefs Conference, Inc. (“TCC”), the owner of record, was informed
by the United States Department of Housing and Urban Development (“HUD”) of potential lease problems involving the Badger Road location. As the hearing officer found, “There is no evidence outside of the viability of the TCC/HUD lease issue from which to conclude that Allvest was not a responsible proposer.” As public pressure increased, including substantial pressure on HUD, Allvest contacted a local real estate agent to research the availability of other locations. The agent discovered that KILA did not own the facility it was using and eventually a lease was executed between Allvest and the property owner that would enable Allvest to use the existing facilities.
DOC denied KILA’s bid protest on November 16, 1989. KILA appealed the denial of its protest on November 30, 1989. KILA also corresponded with Fewell, Humphrey-Barnett, and Larry McKinstry, an assistant attorney general, requesting “[rjeasonable notice of, and right to attend any and all State meetings addressing the Allvest contract modification requests, or the KILA contract dispute, or any meeting related to such.”
The Department of Administration granted KILA an administrative hearing to address the bid protest issues in dispute. A hearing was held from May 29 to June 2, 1990. Pursuant to the hearing officer’s recommendations, the Commissioner of the Department of Administration denied KILA’s appeal in September 1990.
KILA appealed the decision of the Department of Administration to the superi- or court. The superior court affirmed the Department of Administration’s decision, and this appeal followed. On appeal, KILA raises numerous specifications of error, ultimately seeking to have DOC re-bid the contract and pay KILA’s bid preparation costs.
II.
DISCUSSION
A.
Alleged Bias in the Bidding Process
When soliciting bids for goods and services, a government agency has an implied contractual duty to consider bids in a fair and honest manner:
[I]n exchange for a bidder’s investment of the time and resources involved in bid preparation, a government agency must be held to an implied promise to consider bids honestly and fairly. Breach of this implied contract on the part of an agency entitles a disappointed bidder to recover the costs incurred in preparation of the bid.... [T]he “reasonable basis” standard for review of administrative decisions,
see Jager v. State,
537 P.2d 1100, 1107-08 (Alaska 1975);
Kelly v. Zamarello,
486 P.2d 906, 916-17 (Alaska 1971), is applicable in this situation.[
]
See Keco Industries, Inc. v. United States,
[203 Ct.Cl. 566], 492 F.2d 1200, 1203-04 (1974).
King v. Alaska State Hous. Auth.,
633 P.2d 256, 263 (Alaska 1981)
(King II).
A review of the entire record persuades us that KILA’s bid was fairly and honestly considered.
1.
KILA’s Contention that Majoros
Was
Not Impartial
Majoros was responsible for all DOC procurements under statewide programs.
KILA objects to Majoros’ participation in the procurement process, claiming that Majoros was not impartial as required by AS 44.62.-350, and that his partiality resulted in a competitive advantage to Allvest.
Alaska Statute 44.62.350 governs the appointment of hearing officers to hear and adjudicate disputes under the Administrative Procedure Act:
The governor shall assign a qualified, unbiased, and impartial hearing officer, with experience in the general practice of law, to conduct hearings, under this chapter.
Relying on this provision, KILA contends that Majoros was required to be impartial in reviewing the protest letter. However, the application of AS 44.62.350 is governed by AS 44.62.330(b), which reads in relevant part:
The procedure of an ágency not listed in (a) of this section shall be conducted under AS 44.62.33CM14.62.630 only as to those functions to which AS 44.62.330-44.62.630 are made applicable by the statutes relating to that agency.
Neither the Department of Administration nor DOC are among the agencies listed in AS 44.62.330(a), and thus they are not covered by the Administrative Procedure Act.
In addition, AS 36.30.670(a) expressly exempts from the Administrative Procedure Act informal hearings such as the one in which the Department of Administration reviewed the denial of KILA’s bid protest. Therefore, AS 44.62.350 does not apply to a procurement officer’s decision regarding a bid protest or to informal hearings held subsequent to a protest appeal. Nevertheless, the inapplicability of AS 44.62.350 does not relieve Majoros of the obligation to review bid protests in an impartial and unbiased manner.
Our review of the record, and in particular our consideration of Majoros’ response to KILA’s letter of protest, persuades us that none of KILA’s objections demonstrate bias or a lack of impartiality on Majo-ros’ part.
KILA has not shown that Majo-
ros was biased either in approving the PEC recommendation to award the contract to Allvest or in reviewing and rejecting KILA’s protest letter.
We further conclude that none of KILA’s objections prove that Allvest gained a competitive advantage by virtue of Majoros’ decision. Taken individually or cumulatively, the alleged “variances” to which KILA objects are not material.
2.
KILA’S Assertion that Marianne McNabb Had a Severe Conflict of Interest in Violation of the Executive Branch Ethics Act
KILA asserts that DOC official Marianne MeNabb’s involvement in the preparation of the RFPs and her involvement in a prior program audit of Allvest’s Cordova Center in Anchorage violated the Executive Branch Ethics Act, AS 39.52.010-.960.
Specifically, KILA argues that McNabb’s prior involvement with Allvest prohibited her from participating in the bid process.
Prior to being hired by DOC, McNabb was employed by Allvest as vice-president of operations from October 1987 through December 1988.
The hearing officer rejected KILA’s contention:
KILA alleges a violation of the State ethics law although no explanation is provided as to what specific provision of AS 39.52 is alleged to have been violated. No evidence was brought forward or even hinted at that would suggest that Ms. McNabb
benefitted in any way from her former association with Allvest or that she was not honest, truthful, and unbiased in her evaluation of Allvest facilities. Ms. McNabb was not a member of the PEC and testimony established that her only involvement with the solicitation, evaluation, or award of the contract was to suggest minor changes in the scope of work section of the RFP after her input was solicited by DOC and suggested some wording changes in the final contract. No evidence was presented to suggest that her input resulted in an advantage or disadvantage for either proposer.
Our review of the record leads us to conclude that substantial evidence supports the hearing officer’s findings. As the State notes, McNabb’s involvement was limited to advancing some suggestions for the “scope of work” section of the RFP and the geographic and professional criteria for selecting the PEC members. McNabb had neither a personal nor a financial interest in the contract in question. Any personal or financial interest she may have had was insignificant. Therefore, her actions did not violate the Act.
See
AS 39.52.110(b)(1).
One final observation should be made in regal’d to this issue: KILA contends that pursuant to AS 39.52.240, McNabb should have requested an opinion from the Attorney General as to her apparent conflict of interest. As indicated above, in the absence of any personal or financial interest in the contract, and given the fact that McNabb did not participate in or influence the PEC’s contract award process, she was not required to contact the Attorney General regarding the alleged conflict.
3.
KILA’s Contention that the Contract Award Process Was Permeated with Illegalities
KILA also claims the State’s allowance of Allvest’s substitution of facilities after the award of the contract resulted in an unlawful competitive advantage to Allvest that requires voiding the contract. In order to establish a competitive advantage, KILA must prove that a “material” variance was effected in the contract:
Not all amendments to competitively bid contracts are prohibited, only those regarded as material. The concept of materiality in this context has not been satisfactorily captured in a single phrase. One court has spoken of “an essential change of such magnitude as to be incompatible with the general scheme” of competitive bidding; another has phrased the question to be whether the amendment “so varied from the original plan, was of such importance, or so altered the essential identity or main purpose of the contract, that it constitutes a new undertaking.” These formulations simply recognize that the materiality concept prohibits those changes which tend to be subversive of the purposes of competitive bidding.
Kenai Lumber v. LeResche,
646 P.2d 215, 221 (Alaska 1982) (footnotes omitted).
Five factors determine whether a contract change constitutes a “material” variance:
(1) the legitimacy of the reasons for the change;
(2) whether the reasons for the change were unforeseen at the time the contract was made;
(3) the timing of the change;
(4) whether the contract contains clauses authorizing modifications; [and]
(5) the extent of the change, relative to the original contract.
Id.
(footnotes omitted).
The hearing officer applied the five factors and concluded that the amendment “was not a major variation of the original plan nor did it so alter the essential identity or main purpose of the contract that it constituted a new undertaking.” Based on the facts, supporting testimony, and evidence presented, the hearing officer determined: (1) that there were legitimate reasons for the change in facilities; (2) that DOC did not foresee the
reasons for the change at the time the contract was signed, and that Allvest acted in good faith; (3) that given the necessity to have an operative facility by January 1,1990, the contract amendment was timely; (4) that the State consistently allows contract modifications when they are in its best interests;
and (5) that the modification did not interfere with the “intent” of the contract — to secure a correctional facility in the Fairbanks area— and that “[t]he specific site of the facility was not relevant to the functioning of the program.” We conclude that the hearing officer’s factual findings have substantial support in the record and that his interpretation of “material variance” has a reasonable basis in law.
KILA advances numerous other improprieties
and
alleged illegalities in the contracting process. Our review of these points in light of the entire record and applicable law persuades us that none have merit.
B.
KILA’s Contention that the State Violated the Open Meetings Act
KILA argues that the Open Meetings Act (“Act”), AS 44.62.310-312, required that it be granted reasonable notice of, and the right to attend and participate in, meetings concerning the disposition of KILA’s contract, the Allvest contract modification requests, and KILA’s contract dispute. Contending that the State failed to give public notice of these meetings and denied KILA’s representatives access to them, KILA urges us to void any actions modifying the contract.
The state argues that neither DOC nor the Department of Administration violated the Act because the Act does not apply to informal groups of state employees who have no power to take collective action by vote. More particularly, the State notes that
McKinstry, Fewell, Weimar and Majoros were not part of any formally appointed or constituted body. No statute, regulation or formal administrative action created this group as a collective entity, nor were these persons appointed or elected to the group. As a collective entity they
had no
powers, and could take no actions. They could not take action by a group vote. The State further contends that no “meet-
ings” to discuss contract modifications by any official or even informal “bodies” took place. The “meetings” in question consist of two separate teleconferences held between Majo-ros, Fewell, McKinstry, and the president of Allvest. The hearing officer declined to apply the Act to KILA’s appeal because of the nature of the meetings at issue. The hearing officer found that the meetings were “informal” and that it would be “impossible to apply [the Act] to the everyday dealings of public employees when they meet with each other and those outside of State government in the day-to-day conduct of this State’s business.”
We agree. Alaska Statute 44.62.310(a) provides in relevant part:
All meetings of a legislative body, of a board of regents, or of an administrative body, board, commission, committee, subcommittee, authority, council, agency, or
other organization, including subordinate units of the above groups, of the state or any of its political subdivisions, including but not limited to municipalities, boroughs, school boards, and all other boards, agencies, assemblies, councils, departments, divisions, bureaus, commissions or organizations, advisory or otherwise, of the state or local government supported in whole or in part by public money or authorized to spend public money, are open to the public except as otherwise provided by this section.[
]
KILA has presented no evidence that these informal meetings were held by governmental units whose actions come within the ambit of AS 44.62.310. This statute contemplates meetings of a governmental body, including subordinate units thereof. Under the particular facts of this record we hold that the Act did not apply to the individuals who participated in the two meetings now questioned.
III.
CONCLUSION
KILA has failed to prove that any of the DOC officials involved acted in bad faith, were biased, or lacked impartiality. Further, KILA failed to demonstrate that the hearing officer for the Department of Administration lacked a reasonable basis for his conclusion that Allvest’s bid was responsive. KILA’s arguments that Majoros was biased, that McNabb had a conflict of interest, and that the process was permeated with illegalities are meritless. Finally, KILA failed to show any violation of the Open Meetings Act. Thus, the contract between DOC and Allvest is not voided, and KILA is not entitled to its bid preparation costs.
AFFIRMED.