Kick v. Doerste

45 Mo. App. 134
CourtMissouri Court of Appeals
DecidedMay 5, 1891
StatusPublished
Cited by11 cases

This text of 45 Mo. App. 134 (Kick v. Doerste) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kick v. Doerste, 45 Mo. App. 134 (Mo. Ct. App. 1891).

Opinions

Biggs, J.

— The matters in controversy on this appeal are between the plaintiff, who is a mechanic, and the appellant Dreste, who is the owner of a building in the city of St.. Louis. The defendant Doerste made a contract with Dreste to construct for him a brick dwelling-house to be erected on a lot belonging to Dreste. The plaintiff, as a subcontractor under Doerste, furnished the materials for, and did the brick work on, the building. Doerste failed to pay him, and in this action he sought a judgment against Doerste, and the enforcement of a mechanic’s lien against the building and the lot upon which it is situated. The petition is in form as for a quantum meruit, and is accompanied by an itemized account. The jury returned a verdict ■against Doerste for $782.20, with interest at six per ■cent, per annum from the seventeenth day of September, 1886, making the total sum of $959, for which judgment was entered against Doerste. The jury also found by their verdict that the plaintiff had perfected his mechanic’s lien against the building, and the court, in making the entry of judgment, provided for the enforcement of the lien against the building in satisfaction of the judgment, if Doerste failed to pay. brom that judgment Dreste alone has appealed.

[136]*136Wherever the common law is in force, it is the general rule that there can be but one suit for one cause of action. The appellant contends that this principle is applicable in this case,- and that under the evidence the action ought to abate. This is the appellant’s first assignment.

To dispose .of this assignment we must first refer to the pleadings and the evidence upon which it is predicated. The defendant, Doerste, made no defense. Dreste filed an answer, in which he averred among other things that the house involved in this suit, and another belonging to him on an adjacent lot, were erected under one contract entered into between him and Doerste; that the plaintiff became a subcontractor under Doerste and agreed to do the brick work and furnish the necessary materials therefor, for both houses for the aggregate sum of $1,997; that all the work performed by him was done under this contract; that on the seventeenth day of September, 1886, the plaintiff instituted another'action in the circuit court of the city of St. Louis against the defendants to recover from Doerste the reasonable value of the work and materials for the other building; that, on the fifteenth day of April, 1890, he recovered a judgment in that action against Doerste for $1,283.75, and he also had a mechanic’s lien established against the building for that amount.

The plaintiff ’ s reply put in issue the new matter contained in the answer.

On the trial it was disclosed by the evidence that the work done by the plaintiff was performed under a parol contract between him and Doerste for both houses, in which the plaintiff agreed to furnish the brick and lay them in the walls for the gross sum of $1,997. Dreste’s counsel assumes in his brief that it was conceded that the houses were built under one general contract between Doerste and his client. This is denied by the respondent. The plans and specifications are for [137]*137two houses, but we find nothing in the evidence tending to show that there was but one contract. For aught that appears there were two contracts, one for each building. The defendant read in evidence the pleadings and judgment entry in the former action, by which it appeared that that suit and this were instituted at the same time. Doerste made default, and the defendant Dreste filed an answer containing a general denial. The proceeding resulted in a judgment a few months prior to the trial of the present action. It is believed that the foregoing statement will be sufficient for a proper understanding of the legal questions under consideration.

There are two questions involved in this inquiry:

First. Whether the rule against the splitting of demands is applicable to mechanic’s lien cases, where the work has been performed by a subcontractor in the construction of two or more buildings situated on contiguous lots ? Second. If the rule applies, is such a defense available to Dreste in this action ?

Under our mechanic’s lien law, as it stood prior to 1877, the first question would under any view have to be answered in the negative. In 1877 the legislature amended the law by adding the following section, designated in the revision of 1889 as section 6729: “ When the improvement consists of two or more buildings united together and erected on the same lot or contiguous lots, or upon separate buildings upon con* tiguous lots, and erected under one general contract, it shall not be necessary to file a separate lien upon each building for the work done or materials furnished in the erection of such improvements.”

The defendant’s contention is that the section must be construed as mandatory in its requirements, and that, where the facts justify its application, but one lien can be filed, — whether the lienor be an original contractor or not. Hence the argument is made that in [138]*138such a case no valid reason can exist against the application of the law, prohibiting the splitting of demands either for suit or for sale or assignment.

We are of the opinion that the defendant’s argument in support of this question is unsound, because it is based on a false, premise. We do not think that the statute is mandatory in its requirements. If it be conceded that there was but one general contract with Dreste for the construction of the houses, the plaintiff might have filed but one lien on both houses, but there was nothing compulsory about it. The legislature intended by the amendment to the law to extend rather than restrict the rights of mechanics and materialmen in filing liens. The object was to afford the contractor or subcontractor the privilege of filing only one lien, if he was satisfied that there was nothing in the way of its enforcement against the entire property. But a case could be readily imagined where it would be impracticable to enforce one lien for work done and materials furnished for two or more houses situated on separate lots. Some third party might have a like lien on only one of the houses, or there might be a mortgage on one of the lots, or different mortgages might exist in favor of different parties against each lot separately. Such conditions or complications might affect materially the enforcement of one general lien. Hence, we conclude that the legislature intended, in such a case, to leave it optional with the contractor or subcontractor to file one or more liens. If separate liens are filed the owner might have the right, where third parties are in nowise interested, to have the actions consolidated under section 2189 of the Revised Statutes of 1889, and thus save the costs of defending two actions. When this view of the statute is considered, it must be admitted that the law against the splitting of demands cannot be made to apply to actions for the enforcement of ¡mechanics’ liens against houses situated on separate lots.

[139]*139Our conclusion on the first proposition makes it unnecessary for us to decide whether the defense touching the splitting of demands could be made by Dreste, or whether it was available only to the original contractor. This assignment will be ruled against the defendant.

It is next insisted that the lien charge is in excess of what the plaintiff was entitled to recover.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Estate of Girvin
370 S.W.2d 163 (Missouri Court of Appeals, 1963)
Red-E-Gas Company v. Meadows
360 S.W.2d 236 (Missouri Court of Appeals, 1962)
Doll v. Purple Shoppe
90 S.W.2d 181 (Missouri Court of Appeals, 1936)
Putthoff v. Walker
248 S.W. 619 (Missouri Court of Appeals, 1923)
Berkshire Lumber Co. v. J. S. Chick Inv. Co.
153 S.W. 1078 (Missouri Court of Appeals, 1913)
Aimee Realty Co. v. Haller
106 S.W. 588 (Missouri Court of Appeals, 1907)
Badger Lumber Co. v. Muehlebach
83 S.W. 546 (Missouri Court of Appeals, 1904)
Christopher & Simpson Architectural Iron & Foundry Co. v. Kelly
91 Mo. App. 93 (Missouri Court of Appeals, 1901)
Flanagan Bros. v. O'Connell
88 Mo. App. 1 (Missouri Court of Appeals, 1901)
Hill v. Gray
81 Mo. App. 456 (Missouri Court of Appeals, 1899)
Fry v. Estes
52 Mo. App. 1 (Missouri Court of Appeals, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
45 Mo. App. 134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kick-v-doerste-moctapp-1891.