Keystone Elevator Co. v. Johnson Wales Univ., 00-767, (r.I. 2002)

CourtSuperior Court of Rhode Island
DecidedJanuary 17, 2002
DocketConsolidated Cases, M.P. No. 00-767, C.A. No. 00-406
StatusPublished

This text of Keystone Elevator Co. v. Johnson Wales Univ., 00-767, (r.I. 2002) (Keystone Elevator Co. v. Johnson Wales Univ., 00-767, (r.I. 2002)) is published on Counsel Stack Legal Research, covering Superior Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Keystone Elevator Co. v. Johnson Wales Univ., 00-767, (r.I. 2002), (R.I. Ct. App. 2002).

Opinion

DECISION
The Defendants,1 Johnson Wales University and Agostini Construction Company, Inc., move for judgment as a matter of law to release the property known as "32 Page Street" from a mechanic's lien in favor of the Plaintiff, Keystone Elevator, Inc. Following a nonjury trial, the Defendants timely renewed their motion for judgment as a matter of law pursuant to Superior Court Rules of Civil Procedure Rule 52. The Plaintiff objects to the Defendants' motion. The ruling on the motion is herein consolidated with a decision on the merits.

Facts and Travel
This case arises out of a contract dispute between Keystone Elevator (Keystone or Plaintiff), as subcontractor, and Agostini Construction Company (ACC), as general contractor, regarding the construction of a new dormitory at Johnson Wales University (JW).

On January 6, 1999, ACC presented Keystone with a proposal for a subcontract agreement to install two electric elevators in a building under construction commonly referred to as "Johnson Wales University — New Residence Hall, 32 Page Street." (Plaintiff's Exhibit #2). ACC would pay Keystone $221,200 for this work. Keystone would receive a 30% deposit and be allowed eight weeks for installation after the elevator shaft was appropriately prepared by ACC. The proposal also specified a completion date of August 1, 1999. Further, the proposal provided a liquidated damages clause of $1,000 per day and stated that the "[p]roject schedule as provided by Agostini Construction must be strictly maintained." Through authorized agents, both parties signed the agreement by January 23. (January 23rd Agreement).

Problems ensued over the course of construction. Apparently, the "agreement" was modified over the course of dealings to account for miscellaneous delays. The scope and effectiveness of these subsequent "agreements" form the "foundation" of this construction dispute.

On July 28, 1999, Keystone drafted "Changeorder Proposal #1," which stated "[p]er your request to expedite completion and turnover of the two (2) passenger elevators . . . there will be a cost of Fifty One Thousand Dollars ($51,000.00)." (Plaintiff's Exhibit #3). Attached to the Changeorder was a list of qualifications. These qualifications specified "[u]ninterrupted electrical power must be available no later than July 30," and that Keystone would "commence with this work and continue uninterrupted until completion August 30, 1999[.]" (Emphasis in original.)

Seven days later, a document entitled "RE: Johnson Wales, Overtime Rate" (August 11th Document) appeared. (Plaintiff's Exhibit #4). It provided:

"All overtime to be performed at double time rates per standard agreement, International Union of Elevator Constructors as follows:

`the regular working day shall consist of eight (8) hours worked consecutively with an unpaid lunch period, between 6 AM and 5 PM five days per week, Monday through Friday inclusive.' Hours of work at this jobsite are 7 AM to 3:30 PM, Monday to Friday.

`Work performed on construction work on Saturdays, Sundays and before and after the regular working day on Monday to Friday, inclusive, shall be classed as overtime, and paid for at double the rate of single time.'"

This agreement continues by listing several specific provisions for ACC's payment of overtime for the labor provided by Keystone. These provisions included a premium time rate payment of $145 per team of men per hour worked; the method of calculating overtime billing, which would be by tickets signed by ACC's site supervisor; and a statement that all other expenses outside the "specifications" would incur an additional cost. There were also three additional lines on the agreement that were crossed-out. The eliminated clauses contained a zone expense provision, a travel expense provision, and a travel time provision. The same list of qualifications that appeared in Keystone Changeorder #1 was attached as part of this second document. Steve Agostini, president of ACC, signed the document on August 11.

Keystone performed "overtime" work from August 6 through August 29. According to Keystone, the bill for this work totaled $39,403.75. To support this total, Keystone submitted time sheets showing the time worked by Keystone teams. (See Plaintiff's Exhibit #7). Some of these time sheets were signed by an ACC representative as specified in the August 11th Document, and some were not. Both elevators were completed by September 8, 1999. Steve Agostini signed Keystone's Final Inspection, Release and Acceptance form on that date. (Plaintiff's Exhibit #6.)

There were additional "Change Orders" drafted by ACC. On December 15, 1999, ACC issued Change Order #2, which authorized an $850 payment to Keystone for the installation of two cameras, one in each elevator. (Plaintiff's Exhibit #18). One week later, Change Order #3 authorized ACC to pay Keystone $1,375.50 for specific invoices covering service calls. (Plaintiff's Exhibit #17). Both of these Change Orders contained nearly identical language, stating: "NOTE: THIS CHANGE ORDER BECOMES PART OF AND IN CONFORMANCE WITH THE EXISTING CONTRACT. . . ." After this language, both Change Orders contain a running tally of the total approved contract price. For instance, Change Order #3 stated that on December 21, the previous contract amount totaled $221,321.38, and with the authorization, the revised contract total would be $222,678.88. Following the tallies, both Change Orders stated: "ACCEPTED: The above prices and specifications of this Change Order are satisfactory and are hereby accepted. All work to be performed under same terms and conditions as specified on original contract unless otherwise accepted." Both of these Change Orders were signed by representatives of Keystone and ACC.

ACC also took several credits through the use of these "Change Orders," which shared the language and form of its other Change Orders. On September 16, ACC issued its own Change Order #1, charging Keystone $728.62 for costs related to hoisting that Keystone was supposed to pay but that were, in fact, paid by ACC. (Defendant's Exhibit E). This Change Order was signed by a representative of ACC but not a representative of Keystone. Further, on January 26, 2000, ACC issued its Change Order #4, which deducted $13,750 from the total bill for a direct payment that ACC made to one of Keystone's suppliers. (Defendant's Exhibit F). According to Change Order #4, the last of the Change Orders, the total contract price after that credit was $208,928.88. Change Order #4 was unsigned.

Keystone also submitted a series of seven invoices to ACC for services that Keystone claims it performed beyond the scope of the original deal. These invoices totaled $13,685.50. Evidence suggests that ACC's "Change Order #3" covered three of these invoices. (See Plaintiff's Exhibits 12, 13, and 15). ACC subsequently paid Keystone $221,000 on the original contract plus $8,000 based on an alleged oral agreement that Keystone was "not to exceed" that amount for these additional services and for overtime.

ACC filed suit on January 25, 2000. (C.A. No. 00-406). In its complaint, ACC claims that Keystone breached its subcontract by failing to complete work in a timely fashion, failing to complete work in accordance with project specifications, failing to pay its vendors, failing to provide releases and waivers of lien forms from all vendors, failing to attend subcontractor coordination meetings, and by failing to repair warranty items.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rotelli v. Catanzaro
686 A.2d 91 (Supreme Court of Rhode Island, 1996)
Rhode Island Five v. Medical Associates of Bristol County, Inc.
668 A.2d 1250 (Supreme Court of Rhode Island, 1996)
Soucy v. Martin
402 A.2d 1167 (Supreme Court of Rhode Island, 1979)
Lisi v. Marra
424 A.2d 1052 (Supreme Court of Rhode Island, 1981)
Eastern Motor Inns, Inc. v. Ricci
565 A.2d 1265 (Supreme Court of Rhode Island, 1989)
Fondedile, S.A. v. C.E. Maguire, Inc.
610 A.2d 87 (Supreme Court of Rhode Island, 1992)
O'CONNOR v. McKanna
359 A.2d 350 (Supreme Court of Rhode Island, 1976)
Hodor v. United Services Automobile Ass'n
637 A.2d 357 (Supreme Court of Rhode Island, 1994)
Toupin v. Laverdiere
729 A.2d 1286 (Supreme Court of Rhode Island, 1999)
State v. Correia
262 A.2d 619 (Supreme Court of Rhode Island, 1970)
McLaughlin v. Moura
754 A.2d 95 (Supreme Court of Rhode Island, 2000)
Rodriques v. Santos
466 A.2d 306 (Supreme Court of Rhode Island, 1983)
Violet v. Travelers Exp. Co., Inc.
502 A.2d 347 (Supreme Court of Rhode Island, 1985)
Colonial Plumbing & Heating Supply Co. v. Contemporary Construction Co.
464 A.2d 741 (Supreme Court of Rhode Island, 1983)
Romano v. Retirement Board of the Employees' Retirement System
767 A.2d 35 (Supreme Court of Rhode Island, 2001)
Supreme Woodworking Co. v. Zuckerberg
107 A.2d 287 (Supreme Court of Rhode Island, 1954)
Long v. Atlantic PBS, Inc.
681 A.2d 249 (Supreme Court of Rhode Island, 1996)
Jonklaas v. Silverman
370 A.2d 1277 (Supreme Court of Rhode Island, 1977)
Richardson v. Smith
691 A.2d 543 (Supreme Court of Rhode Island, 1997)
Walton v. Baird
433 A.2d 963 (Supreme Court of Rhode Island, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
Keystone Elevator Co. v. Johnson Wales Univ., 00-767, (r.I. 2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/keystone-elevator-co-v-johnson-wales-univ-00-767-ri-2002-risuperct-2002.