Key Constructors, Inc. v. Harnett County

315 F.R.D. 179, 2016 U.S. Dist. LEXIS 60488, 2016 WL 2654057
CourtDistrict Court, E.D. North Carolina
DecidedMay 6, 2016
DocketNo. 5:16-CV-25-D
StatusPublished
Cited by5 cases

This text of 315 F.R.D. 179 (Key Constructors, Inc. v. Harnett County) is published on Counsel Stack Legal Research, covering District Court, E.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Key Constructors, Inc. v. Harnett County, 315 F.R.D. 179, 2016 U.S. Dist. LEXIS 60488, 2016 WL 2654057 (E.D.N.C. 2016).

Opinion

ORDER

JAMES C. DEVER III, Chief United States District Judge

On January 14, 2016, Key Constructors, Inc. (“Key Constructors” or “plaintiff’) sued Harnett County, Harnett County Department of Public Utilities (“HCDPU”), South Central Water & Sewer District of Harnett County, North Carolina (“SCWS”), and MBD Consulting Engineers, P.A. (“MBD”). See Compl. [D.E.l].1 The dispute concerns a construction contract to build collection lines for the Harnett County defendants. See id. ¶¶ 9-10. MBD was the owner’s representative and the project engineer. See id. 13-14. The court has jurisdiction based on diversity. Key Constructors alleges breach of contract against the Harnett County defendants (counts one and two), unjust enrichment against the Har-nett County defendants (count three), and negligence against MBD Consulting Engineers, P.A. (“MBD”) (count four). See id. 41-85.

On March 10, 2016, the Harnett County defendants moved to dismiss the claims against them for failure to join a necessary and indispensable party (i.e., Temple Grading and Construction Company, Inc. (“Temple Grading”)) and a motion to strike a portion of the complaint concerning an alleged contract modification as immaterial, impertinent, and irrelevant. See [D.E. 20] 1-6 (moving to dismiss), 6-9 (moving to strike); Fed. R. Civ. P. 12(b)(7), 17, 19. Temple Grading was a subcontractor of Key Constructors on the collection-line construction project. On March 10, 2016, MBD moved to dismiss count four for failure to join a necessary and indispensable party (i.e., Temple Grading). See [D.E. 22]; Fed. R. Civ. P. 17, 19. On March 24, 2016, Key Constructors responded in opposition. See [D.E. 29, 30]. On April 6, 2016, the Harnett County defendants replied. See [D.E. 32]. As explained below, the court denies the motions.

I.

Defendants argue that (1) Temple Grading is the real party in interest under Rule 17(a) and a required party under 19(a); (2) joining Temple Grading is not feasible because Temple Grading is a North Carolina citizen and would destroy diversity jurisdiction; and (3) equity and good conscience require the court to dismiss the action under Rule 19(b) rather than permitting it to proceed in federal court without Temple Grading as a party. See [D.E. 20] 1-2; [D.E. 23] 1-6. According to defendants, during the collection-line construction project, the Harnett County defendants became unsatisfied with Key Constructors’s work. [D.E. 23] 2. Rather than terminate the contract, the Harnett County defendants allowed Key Constructors to add Temple Grading as a subcontractor in order to finish the work. Id. Furthermore, MBD, in its role as owner’s representative and project engineer, frequently interacted with both Key Constructors’s and Temple Grading’s personnel. Id.

In count one, Key Constructors seeks $393,217 plus attorney’s fees, interest, and costs for breach of contract. Compl. ¶¶ 41-49. In count two, Key Constructors seeks at least $1,955,895 exclusive of interest, attorneys’ fees, and costs, for delay, disruption, [182]*182and interference with Key Construetors’s prime contract and Temple Grading’s subcontract. See Id. ¶¶ 50-68. Alternatively, in count three, Key Constructors seeks $2,349,112, plus attorney’s fees and costs, for unjust enrichment. See id. ¶¶ 69-75. Finally, in count four, Key Constructors seeks $2,349,112, exclusive of interest and costs, from MBD for MBD’s alleged negligence as the engineer of record responsible for the design of the collection-line construction project. See id. ¶¶ 76-85.

This court’s subject-matter jurisdiction is based on diversity jurisdiction. Thus, the court applies state substantive principles and federal procedural rules. See Erie R.R. v. Tompkins, 304 U.S. 64, 78-80, 58 S.Ct. 817, 82 L.Ed. 1188 (1938); Dixon v. Edwards, 290 F.3d 699, 710 (4th Cir.2002). Federal law governs who is the real party in interest under Rule 17 and joinder under Rule 19. See, e.g., Provident Tradesmens Bank & Trust Co. v. Patterson, 390 U.S. 102, 125 n. 22, 88 S.Ct. 733, 19 L.Ed.2d 936 (1968). State law, however, informs the relevant interests of the parties and potential parties. See Patterson, 390 U.S. at 125 n. 22, 88 S.Ct. 733; HB Gen. Corp. v. Manchester Partners, L.P., 95 F.3d 1185, 1192 (3d Cir.1996); Krueger v. Cartwright, 996 F.2d 928, 931 (7th Cir.1993); Whalen v. Carter, 954 F.2d 1087, 1096 & n. 8 (5th Cir.1992); 7 Charles Alan Wright & Arthur R. Miller, Federal Practice and Procedure § 1603, Westlaw (3d ed.) (database updated Apr. 2016). Moreover, the parties agree that North Carolina law governs the four claims in Key Constructors’s complaint.

The Harnett County defendants contend that Temple Grading is the real party in interest in count two and count four because Key Constructors seeks to recover damages in count two and four not only for itself but also for damages to its subcontractor Temple Grading. See [D.E. 20] 2. Moreover, the Har-nett County defendants argue that North Carolina law prohibits Temple Grading from suing the Harnett County defendants directly for breach of contract due to a lack of privity, but that North Carolina law permits Temple Grading to sue MBD directly for MBD’s alleged negligence. See id. 1-3 (citing Davidson & Jones, Inc. v. New Hanover Cty., 41 N.C.App. 661, 667, 255 S.E.2d 580, 584 (1979)). MBD also argues that Temple Grading is the real party in interest in count four because Key Constructors is seeking to recover damages for both Key Constructors and Temple Grading for MBD’s alleged negligence, but North Carolina law permits Temple Grading to sue MBD for negligence. See [D.E. 23] 3-4. Accordingly, defendants contend that Temple Grading is the real party in interest under Rule 17.

Key Constructors responds that Rule 17 merely requires this court to assess whether North Carolina law permits Key Constructors to enforce the claims that it seeks to pursue in this ease. See [D.E. 29] 6-7; cf. Fed. R. Civ. P. 17(a)(1) (“An action must be prosecuted in the name of the real party in interest.”). Key Constructors then argues that North Carolina law permits Key Constructors to pursue the claims in counts one through three against the Harnett County defendants and the claim in count four against MBD. See [D.E. 29] 6-7. Furthermore, Key Constructors argues that Rule 17 does not require a prime contractor to join as parties all of its subcontractors or suppliers who might have a claim against the owner or project engineer. See id.

A real party in interest for the purpose of Rule 17(a) is a person authorized to bring a suit in his own name without joining his beneficiaries. See Lester v. McFaddon, 415 F.2d 1101, 1105-06 (4th Cir.1969).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
315 F.R.D. 179, 2016 U.S. Dist. LEXIS 60488, 2016 WL 2654057, Counsel Stack Legal Research, https://law.counselstack.com/opinion/key-constructors-inc-v-harnett-county-nced-2016.