Kessler v. Bowie Machine Works, Inc.

501 F.2d 617
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 19, 1974
DocketNos. 74-1008, 74-1034
StatusPublished
Cited by14 cases

This text of 501 F.2d 617 (Kessler v. Bowie Machine Works, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kessler v. Bowie Machine Works, Inc., 501 F.2d 617 (8th Cir. 1974).

Opinion

PER CURIAM.

Plaintiff-appellee Dan Kessler, who sustained injuries while working on a hydro-mulcher landscaping machine, brought this diversity action against the manufacturer, Bowie Machine Works, Inc. (Bowie) of Bowie, Texas, seeking substantial damages. Bowie in turn im-pleaded Kessler’s employer, J. H. Hilt, doing business as J. H. Hilt Engineering Company (Hilt) of Rapid City, South Dakota, alleging that Bowie as a third party plaintiff was entitled to indemnity under South Dakota law on the theory that Hilt’s substantial alteration of the design of the hydro-mulcher caused the accident.

The issues in the suit were submitted to the jury for a general verdict together with special interrogatories. The jury returned a verdict in favor of Kes-sler for $120,000 in damages, and by answers to special interrogatories indicated that defendant-Bowie’s liability rested on both negligence and strict liability.1 With respect to the third party claim, the trial court submitted a special interrogatory to the jury relating to the third party complaint against Hilt. The jury found Hilt guilty of negligence which contributed 12 percent to Kes-sler’s injury.2

[620]*620Upon receipt of these jury verdicts, the district court entered judgment in favor of Kessler against Bowie for the sum of $120,000, and entered judgment on the third party complaint in favor of Bowie and against Hilt for 12 percent of the total judgment in the main action. Bowie has appealed from the judgment obtained by Kessler in the main action. Hilt has appealed from the judgment against it in the third party proceedings. Upon a careful study of the record, we sustain the award to Dan Kessler in the main action but reverse the judgment in the third party action as one not authorized under South Dakota law.

Hilt purchased the hydro-mulcher from Bowie in 1970. At the time of the accident, the machine was employed in the performance of an erosion-control contract on an interstate construction project near Spearfish, South Dakota. The machine, which was mounted on the platform of a tandem truck, facilitated grass seeding by mixing wood cellulose fiber with fertilizer, seed and water, thereby producing a slurry which was sprayed on the ground. The dry wood cellulose is introduced into the machine through an opening on the platform leading into a shredder. That opening is about 12% inches by 40 inches and has a lip or a buffer plate around the perimeter of the opening which extends up 6 inches above the floor of the platform. A revolving shredder-bar pipe or cyclinder with protruding teeth or spikes grinds the dry cellulose into a mulch before depositing it into a tank carried below the platform.

As delivered from the factory, the shredder opening previously described was surrounded by a safety railing, consisting of a lower rail 17% inches above the platform deck and a top rail 10 inches higher. Some time late in the fall of 1971, the top rail surrounding the shredder opening on the hydro-mulcher owned by Hilt broke, and, early the next year, a superintendent for Hilt, in repairing this rail, hinged it so that it could be swung out of the way at the option of the machine operator.

The wood cellulose material as purchased by Hilt came in 1,800 pound bales and was extremely dense. The operator of the machine would split these bales with an ax into 150-pound chunks and feed them into the shredder opening. Often these chunks would not automatically feed into the shredder but would “ride” on top of the shredder bar. Kessler, like a predecessor who worked on the machine, would then push or kick these “riding” chunks with his foot and force the material into the teeth of the shredder.

Ordinarily, the operator left the top railing around the shredder in an open position because it was easier to get at the material to kick it down into the shredder. On May 21, 1972, while working on the machine, Kessler kicked a chunk of cellulose into the mulcher and in doing so, brought his foot into contact with the revolving shredder bar. The bar pulled his leg into the machinery causing a severe injury which required the amputation of his lower leg. Kessler, thereafter, brought this action.

I.

BOWIE’S APPEAL

Bowie in its appeal raises the following issues:

1) Plaintiff-Kessler was guilty of assumption of risk as a matter of law;

2) The strict liability doctrine was inapplicable because of a material and substantial alteration made in the machine;

3) The court erred in instructing on Bowie’s failure to warn since the law does not require any warning in the face of an obvious danger;

4) The trial court should have granted a mistrial because during his opening statement plaintiff’s attorney made an improper reference to a prior accident involving a Bowie hydro-mulcher; and

5) The trial judge committed prejudicial error in questioning a witness con[621]*621cerning two prior accidents relating to a Bowie hydro-mulcher.

Having examined the record, we find no prejudicial error in the trial of the main action and therefore affirm the judgment against Bowie. We turn to a discussion of these points.

A. To support an assumption of the risk defense under South Dakota law, it is well established that the defendant must show that an employee not only had knowledge of the existence of the risk and an appreciation of its character but also that he voluntarily accepted this risk, i. e., that he had a sufficient amount of time and enough knowledge and experience to make an intelligent choice. Ordinarily, whether the plaintiff assumed the risk is a question for the jury. See Associated Engineers, Inc. v. Job, 370 F.2d 633, 639 (8th Cir. 1966), cert. denied, 389 U.S. 823, 88 S.Ct. 59, 19 L.Ed.2d 77 (1967), and cases cited therein; Smith v. Community Cooperative Ass’n of Murdo, 209 N.W.2d 891, 892 (S.D.1973), and citations cited therein; Bunkers v. Mousel, 83 S.D. 45, 154 N.W.2d 208, 210 (1967).

Kessler, age 23, had been working on the hydro-mulcher for approximately two weeks. A fellow employee, who Kessler considered his superior, had earlier demonstrated how to kick the riding chunks into the shredder when this material did not feed automatically into the machine. Moreover, it appears that Kessler felt that he could safely kick the chunks into the machine. The question of Kessler’s knowledge and appreciation of the risk of kicking the chunks was a fact question properly submitted to the jury, and was resolved against Bowie.

B. Bowie also claims that Hilt’s alteration of the hydro-mulcher by hinging a portion of the upper rail of the double railing surrounding the opening in the platform constituted a material alteration of the machine and thus served to relieve Bowie from strict liability. This claim is without substantial merit.

The testimony indicated that the operators of the machine kicked or pushed the chunks of wood cellulose into the shredder, notwithstanding the existence of the railing, prior to its being hinged.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Roundtree v. Am Manufacturing Co. Inc., No. Cv 92 0338311 S (Sep. 27, 1995)
1995 Conn. Super. Ct. 10636 (Connecticut Superior Court, 1995)
Lovell v. Oahe Electric Cooperative
382 N.W.2d 396 (South Dakota Supreme Court, 1986)
Anderson Banks v. Iron Hustler Corp.
475 A.2d 1243 (Court of Special Appeals of Maryland, 1984)
Sydenstricker v. Unipunch Products, Inc.
288 S.E.2d 511 (West Virginia Supreme Court, 1982)
Thomas v. St. Mary's Roman Catholic Church
283 N.W.2d 254 (South Dakota Supreme Court, 1979)
Therrien v. Safeguard Manufacturing Co.
408 A.2d 273 (Connecticut Superior Court, 1979)
Skinner v. Reed-Prentice Division Package MacHinery Co.
374 N.E.2d 437 (Illinois Supreme Court, 1978)
Roy v. Star Chopper Co., Inc.
442 F. Supp. 1010 (D. Rhode Island, 1977)
Parker v. Stetson-Ross MacH. Co. Inc.
427 F. Supp. 249 (D. South Dakota, 1977)
Harn v. Standard Engineering Co.
416 F. Supp. 1168 (D. South Dakota, 1976)
Johnson v. Clark Equipment Company
547 P.2d 132 (Oregon Supreme Court, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
501 F.2d 617, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kessler-v-bowie-machine-works-inc-ca8-1974.