Kershaw Excavating Co. v. City Systems, Inc.

581 A.2d 1111, 1990 Del. LEXIS 319
CourtSupreme Court of Delaware
DecidedOctober 10, 1990
StatusPublished
Cited by4 cases

This text of 581 A.2d 1111 (Kershaw Excavating Co. v. City Systems, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kershaw Excavating Co. v. City Systems, Inc., 581 A.2d 1111, 1990 Del. LEXIS 319 (Del. 1990).

Opinion

HOLLAND, Justice:

This matter was commenced on May 18, 1989, when the plaintiff-appellant, Kershaw Excavating Company, Inc. (“Kershaw”), filed a mechanic’s lien action against the defendant-appellee, City Systems, Inc. (“City Systems”), as the owner of the Le Parc condominium project (“Le Parc”) and the Westhill townhouse project (“West-hill”). The complaint alleged that a total of approximately $189,353.03 was due and owing to Kershaw from City Systems. In addition to City Systems, subsequent owners of individual Le Parc condominium units and individual Westhill townhouse units were also named as defendants and are now appellees. On October 6, 1989, the Superior Court granted City Systems’ motion to dismiss Kershaw’s mechanics’ lien action. On October 26, 1989, that order was made final. This is Kershaw’s direct appeal from the decision of the Superior Court.

At the time Kershaw filed its complaint, there were ten buildings at Le Parc, containing between six and eight condominium units each. There were three buildings at Westhill, containing nine or ten units each. Kershaw sought to impose a lien of $6,605.66 against each of the ten buildings at Le Parc and a lien of $41,098.82 against each of the three buildings located at West-hill.

City Systems filed a motion to dismiss Kershaw’s mechanic’s lien action on the basis that Kershaw had not properly apportioned its claim among the individual condominium and townhouse units. Kershaw admitted that it had apportioned its claim among each of the buildings or structures located at the Le Parc and Westhill projects, and not the individual units within them. The Superior Court held that, as a matter of law, Kershaw was required to apportion its mechanic’s lien claim among each of the individual units comprising the buildings at Le Parc and Westhill, rather than the buildings in their entirety.

Kershaw contends that the Superior Court’s decision in this matter should be reversed. Kershaw argues that it properly apportioned its claims among the buildings on the Le Parc and Westhill projects, and not the individual units contained in each building, pursuant to the Superior Court’s prior holdings in Wilmington Trust Company v. Branmar, Inc., Del.Super., 353 A.2d 212 (1976), and Ramsey v. DiSabatino, Del.Super., 347 A.2d 659 (1975). We have concluded that Kershaw’s position is correct. Accordingly, the Superior Court’s decision to dismiss Kershaw’s mechanic’s lien action is reversed.

Facts

The basic facts are not in dispute. On April 28, 1987, pursuant to an agreement with City Systems, Kershaw began to perform site work on the Le Parc condominium project. That work included, inter alia, clearing, grading, paving, curbing, manhole installation, raking and seeding. On the date when Kershaw began its work, *1113 City Systems was the sole owner of the Le Pare lands. At a later date, City Systems caused the Le Parc land to become a condominium complex, subject to the Delaware Unit Properties Act, 25 Del.C. § 2201, et seq., by recording a declaration of condominium. The agreement between City Systems and Kershaw for the work did not specify or call for work on a per unit basis. In its complaint, Kershaw alleges that it ceased to work on the Le Parc project as of February 8, 1989, and that it has not been paid for approximately $66,056.56 worth of the work which was performed prior to that date.

On March 16, 1988, pursuant to a separate agreement with City Systems, Ker-shaw began to perform site work on the Westhill townhouse project. That work also included, inter alia, grading, curbing, and utility work. When Kershaw began its work, City Systems was the sole owner of the Westhill land, which consisted of four parcels. City Systems subdivided the Westhill townhouse project after Kershaw began its work. Kershaw’s agreement to perform work at Westhill was also not on a per unit basis. In its complaint, Kershaw alleges that it ceased to work on the West-hill project on February 7, 1989, and that it has not been paid for approximately $123,-296.47 worth of the work which was performed.

Definition of Structure

Under Delaware's Mechanic’s Liens statute, a claimant may file a joint claim against two or more “structures” provided that the claimant “designate the amount which he claims to be due to him on each of such structures.” 25 Del. C. § 2713. Thus, integral to every claim for a mechanic’s lien is the identification of the “structure” against which the lien is sought. 25 Del. C. § 2712(7). The proper method of describing or designating a “structure” in a mechanic’s lien action has become increasingly difficult with the advent of more complex forms of property ownership and sophisticated structural configurations.

When the Superior Court has previously been called upon to decide actions seeking to impose mechanics’ liens against “structures” such as townhouses, apartment buildings, shopping centers, and condominium complexes, it has recognized that “the meaning of ‘structure’ for purposes of the mechanics’ lien statutes is altered according to the nature and purpose of the labor or materials supplied.” Wilmington Trust Company v. Branmar, Inc., Del.Super., 353 A.2d 212, 215 (1976). In Wilmington Trust Company, the Superior Court held that in defining the term “structure” that:

to the extent labor or materials are supplied in and solely for the benefit of a condominium townhouse, each townhouse is a separate “structure” within the meaning of 25 Del.C. § 2713.

Id. However,

[t]o the extent that labor or materials are supplied for the benefit of the common elements of the row of townhouses, however, the entire row may constitute a single “structure” for mechanics’ lien purposes.

Id. (citing Ramsey v. DiSabatino, Del.Super., 347 A.2d 659, 662 (1975)).

In Ramsey, a subcontractor filed a mechanic’s lien action for work performed at a complex of “townhouse units.” Ramsey v. DiSabatino, 347 A.2d at 660. Part of the claim was against certain individual units and part of the claim was against an entire building which consisted of a connected row of individual units. The Superior Court concluded that a mechanic’s lien action could be properly brought against the entire larger structure which was comprised of individual units. Id. at 662. Consequently, in Ramsey, the Superior Court denied a motion to dismiss a mechanic’s lien action filed against the entire structure (the connected row of townhouse units) because “any uncertainty concerning the allegations of the complaint should be resolved for purposes of this motion [to dismiss] in favor of plaintiff [subcontractor].” Id. at 661 (citing Atlas Subsidiaries of Del., Inc. v. Burns,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
581 A.2d 1111, 1990 Del. LEXIS 319, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kershaw-excavating-co-v-city-systems-inc-del-1990.