D. W. Burt Concrete Construction, Inc. v. Dewey Beach Enterprises, Inc.

CourtSuperior Court of Delaware
DecidedFebruary 17, 2016
DocketS13L-10-043-RFS
StatusPublished

This text of D. W. Burt Concrete Construction, Inc. v. Dewey Beach Enterprises, Inc. (D. W. Burt Concrete Construction, Inc. v. Dewey Beach Enterprises, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D. W. Burt Concrete Construction, Inc. v. Dewey Beach Enterprises, Inc., (Del. Ct. App. 2016).

Opinion

IN THE SUPERIOR COURT OF THE STATE OF DELAWARE

: D.W. BURT CONCRETE : CONSTRUCTION, INC. : : Plaintiff, : v. : : DEWEY BEACH ENTERPRISES, : INC., LIGHTHOUSE COVE : C.A. No.: S13L-10-043 RFS DEWEY BEACH LAND UNIT C : LLC, LIGHTHOUSE COVE : DEWEY BEACH LAND UNIT F : LLC, LIGHTHOUSE COVE : DEWEY BEACH LAND UNIT H : LLC, LIGHTHOUSE COVE : DEWEY BEACH LAND UNIT L : LLC, AND DAYSTAR SILLS, : INC. :

Defendants.

MEMORANDUM OPINION

Decision after Bench Trial. Verdict for Plaintiff.

Submitted: November 24, 2015 Decided: February 17, 2016

Robert V. Witsil, Esquire, Robert V.Witsil, Jr. P.A., Georgetown, Delaware, Attorney for the Plaintiff.

Victoria Petrone, Esquire, Logan & Petrone, LLC, New Castle, Delaware, Attorney for the Defendants.

J. STOKES I. INTRODUCTION

This is the Court’s decision following a bench trial on a breach of contract action and a

statement of claim for a mechanics’ lien. Plaintiff D.W. Burt Concrete Construction, Inc.

(“Burt”) filed a Complaint against Defendants Dewey Beach Enterprises, Inc., Lighthouse Cove

Dewey Beach Land Unit C LLC, Lighthouse Cove Dewey Beach Land Unit F LLC, Lighthouse

Cove Dewey Beach Land Unit H LLC, Lighthouse Cove Dewey Beach Land Unit L LLC, and

Daystar Sills, Inc. (collectively “Daystar”) seeking $568,621.00 in satisfaction of a mechanics’

lien. After consideration of the facts in evidence and the applicable law, the Court finds that

Burt properly pleaded its mechanics’ lien claim and proved the commencement date. Further,

the Court finds that Daystar grossly overstated the amount in dispute when it discharged the lien,

and Daystar is not entitled to any set-offs of the contract balance.

II. FACTS AND PROCEDURAL POSTURE

Daystar is a real estate development firm owned by David Sills (“Sills”). Burt is a

concrete construction company owned by Daniel Burt (“Daniel”). 1 In September 2012, Daystar,

as the general contractor, retained Burt, as a subcontractor, to provide concrete installation and

other services for the construction of the Hyatt Hotel (the “Project”) in Dewey Beach, Delaware.

The contract (the “Agreement”) called for work to begin on September 12, 2012. Although the

contract expressed that time was of the essence, it did not provide a specific date by which the

work was to be completed.

In consideration for the work performed, Daystar agreed to pay Burt a total of

$2,300,000.00 pursuant to a payment schedule set forth in the Agreement. Under the terms of

the Agreement, Burt was required to submit a written requisition for payment on or before the

twenty-fifth day of each month showing the proportionate value of the work performed through 1 This Opinion refers to Daniel Burt as “Daniel” to distinguish the person from the company.

2 the end of the month. Daystar would then pay Burt ninety percent of the value of the work

performed by Burt on the twentieth day of the following month. Daystar would keep the

remaining ten percent as retainage. 2 Once Burt completed fifty percent of the Project, the

amount of retainage would be reduced to five percent.

Burt began construction on September 17, 2012. At trial, Daystar submitted a schedule

that indicated Burt’s portion of the Project was to be completed by January 28, 2013. This date

was not met. 3 The relationship between Daystar and Burt began to strain because both parties

believed that the other was not satisfying the terms of the Agreement. Specifically, Daystar

alleged that Burt was not performing in a timely manner, and Burt alleged that Daystar failed to

make payments in accordance with the Agreement.

As a means to mitigate the delay in Burt’s performance, Daystar sought to exercise its

rights under the Agreement by doing whatever was necessary to maintain the work schedule. 4

At trial, Daystar submitted an itemized list of expenses it incurred by exercising this contractual

right. 5 Namely, Daystar incurred expenses on behalf of Burt for the following: (1) constructing

footings; (2) replacing a broken sanitary sewer pipe; (3) labor for removing shoring; (4) grinding

of cast in place walls; (5) finishing of the stair tower and pool area walls; (6) finishing the

underside of balconies; (7) correcting improper elevation on slabs; (8) redesigning the out-of-

plumb stair; and (9) supervising. In total, Daystar alleges it incurred $116,960.35 to remedy

Burt’s alleged delay in performance.

On August 6, 2013, Burt completed its portion of the Project and submitted a payment

requisition form for $224,935.00—the balance of the contract price withheld as retainage. After

2 Retainage is a percentage withheld by the general contractor until the work is satisfactorily completed. 3 In fact, Burt did not complete its portion of the Project until August 2013. Both parties testified that, due to changes, the schedule submitted at trial was not indicative of the actual schedule. 4 See Daystar’s Trial Exhibit (hereinafter “DTX”), Tab 1 at Article IV. 5 Id. at Tab 3.

3 Daystar refused to pay, Burt initiated a mechanics’ lien on the Project. Because the mechanics’

lien prevented Daystar from selling any part of the Project with clear title, Daystar sought a lien

discharge pursuant to 25 Del. C. § 2729.

Burt filed a Complaint for breach of contract and a statement of claim for a mechanics’

lien against Daystar on October 24, 2013, seeking the balance of the contract price as well as

$343,696.00 for “change orders.” 6 In response, Daystar filed an Answer denying Burt’s claims

and asserting a counterclaim seeking damages for breach of contract as well as legal expenses. 7

On October 29, 2014, Daystar filed a motion for partial summary judgment of Burt’s

claims for change orders. This Court granted Daystar’s motion for summary judgment. As a

result, Burt was precluded from seeking $343,696.00 in change orders at trial.

Following a bench trial held on June 1, 2015, the Court reserved decision pending post-

trial briefing.

III. THE PARTIES’ CONTENTIONS

A. Burt’s Contentions

Burt argues that it substantially performed its contract with Daystar and is entitled to the

contract balance of $224,935.00 plus interest. Also, Burt contends that Daystar grossly

overstated the amount of the disputed claim when it posted bond to discharge the mechanics’

lien. 8 Burt further contends that Daystar’s gross overstatement was done in bad faith and, as a

result, this Court should grant double damages pursuant to 25 Del. C. § 2729(a).

6 Am. Compl. ¶ 16. A change order is work that is added to or delete from the original scope of work of a contract that alters the original contract amount. 7 Answ. and Countercl. ¶ 64. 8 Burt’s Post Trial Br. at 13.

4 B. Daystar’s Contentions

Daystar argues that Burt incorrectly established the date construction commenced in its

statement of claim for a mechanics’ lien and, therefore, failed to meet the statutory requirements

of 25 Del. C. § 2712(b). As a result of Burt’s failure to establish the date at trial, Daystar

contends judgment should be entered in its favor. Additionally, Daystar argues that they are

entitled to recover damages as an offset according to the Agreement and if Burt is entitled to any

recovery, that recovery should be limited to $89,229.81. Lastly, Daystar asserts that it is entitled

to legal fees pursuant to a provision in the Agreement.

IV. STANDARD OF REVIEW

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reynolds v. Reynolds
237 A.2d 708 (Supreme Court of Delaware, 1967)
Poole v. Oak Lane Manor, Inc.
118 A.2d 925 (Superior Court of Delaware, 1955)
Carlson v. Hallinan
925 A.2d 506 (Court of Chancery of Delaware, 2006)
First Atlantic Bldg. Corp. v. Neubauer Const. Co.
352 So. 2d 103 (District Court of Appeal of Florida, 1977)
Kershaw Excavating Co. v. City Systems, Inc.
581 A.2d 1111 (Supreme Court of Delaware, 1990)
At&T CORP. v. Lillis
953 A.2d 241 (Supreme Court of Delaware, 2008)
Rhone-Poulenc Basic Chemicals Co. v. American Motorists Insurance Co.
616 A.2d 1192 (Supreme Court of Delaware, 1992)
Di Mondi v. S. & S. Builders, Inc.
124 A.2d 725 (Supreme Court of Delaware, 1956)
Eagle Industries, Inc. v. DeVilbiss Health Care, Inc.
702 A.2d 1228 (Supreme Court of Delaware, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
D. W. Burt Concrete Construction, Inc. v. Dewey Beach Enterprises, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/d-w-burt-concrete-construction-inc-v-dewey-beach-enterprises-inc-delsuperct-2016.