Kenya Spratt v. FCA US LLC

Court of Appeals for the Sixth Circuit·Decided May 13, 2020·No. 19-1420·Unpublished

Opinion

NOT RECOMMENDED FOR PUBLICATION File Name: 20a0269n.06

No. 19-1420

UNITED STATES COURT OF APPEALS FILED FOR THE SIXTH CIRCUIT May 13, 2020 DEBORAH S. HUNT, Clerk

KENYA N. SPRATT, ) ) Plaintiff-Appellant, ) ON APPEAL FROM THE ) UNITED STATES DISTRICT v. ) COURT FOR THE EASTERN ) DISTRICT OF MICHIGAN FCA US LLC, ) ) OPINION Defendant-Appellee. ) )

Before: MERRITT, CLAY, and BUSH, Circuit Judges.

CLAY, Circuit Judge. Plaintiff Kenya Spratt appeals the district court’s order granting

summary judgment in favor of his former employer, Defendant FCA US LLC, on his race

discrimination claim brought pursuant to Title VII of the Civil Rights Act of 1964, 42 U.S.C.

§ 2000e-2(a). For the reasons that follow, we reverse the district court’s judgment and remand for

further proceedings consistent with this opinion.

I. BACKGROUND

This case arises from Defendant’s decision to terminate Plaintiff based on his falsification

of bids that were submitted by potential contractors for a large-scale construction project

renovating the Chrysler Technology Center in Auburn Hills, Michigan. Plaintiff does not dispute

that he falsified the relevant bids. Instead, he argues that Defendant used that falsification as an

excuse to illegally terminate him based on his race. Plaintiff contends that if he was not African

American, but instead was Caucasian, Defendant would not have terminated him for his conduct. No. 19-1420, Kenya Spratt v. FCA US LLC

As evidence of this, Plaintiff points to Defendant’s past decision not to fire a similarly situated

Caucasian employee who engaged in conduct comparable to Plaintiff’s. Based on this differential

treatment, Plaintiff argues that a reasonable jury could conclude that Defendant’s decision to

terminate him was motivated by racial discrimination. For the reasons that follow, we agree.

A. FCA’s Sourcing Process

Prior to his termination in April 2017, Plaintiff Kenya Spratt worked as a Senior

Construction Buyer at FCA US. FCA US is a North American car manufacturer, and is a member

of the Fiat Chrysler Automobiles family of companies. In his role as Senior Construction Buyer,

Plaintiff was responsible for soliciting competitive bids for large-scale construction projects at

FCA US and sourcing the projects based on the bids.

Although FCA US did not have written policies for how the sourcing process should be

conducted, the standard practice that developed over the years was for the Senior Buyer and the

internal client (i.e., the particular department overseeing the respective project) to identify three to

four contractors and invite them to bid. Once the initial bids were received, the Senior Buyer would

then prepare an initial bid comparison summary, which lists the bids from each contractor based

on their respective unit prices (e.g., structural, electrical, plumbing) and item prices (e.g., steel,

lighting, sinks). According to Plaintiff, the initial summary sheet “is an analysis tool used to

identify variances in the cost of specific units . . . between contractors’ bids to determine what

clarifications of the job requirements are necessary” before asking the contractors to submit their

final bids. (Appellant Br. at 5–6.) The initial summary sheet does not contain the names of the

bidding contractors, and it is not used to determine who will be awarded the job.

2 No. 19-1420, Kenya Spratt v. FCA US LLC

After the Senior Buyer prepares the initial summary sheet, he shares it with the internal

client, and the Senior Buyer and internal client then decide whether or not a clarification meeting

is needed. The purpose of a clarification meeting is to review the scope of the project with the

contractors in order to ensure that they understand what the project will entail. At this stage, the

highest bidder may be eliminated from the competitive process.

Following the clarification meeting, the remaining contractors submit their final bids. The

Senior Buyer then prepares a summary of the final bids, and sends that summary to the internal

client. Unlike the initial summary sheet, the summary of the final bids includes the contractors’

names and identifying information. The internal client and the Senior Buyer use the final summary

sheet to determine which contractor will be awarded the job. Usually, the contractor with the

lowest bid is successful.

B. The Museum Project

In late 2016, FCA US decided to renovate the Chrysler Technology Center in Auburn Hills,

Michigan (the “Museum Project”). Plaintiff was the Senior Buyer overseeing the renovation. The

internal client (the Facilities department) suggested three contractors to participate in the bidding

process—Barton Mallow, Walbridge, and Aristeo. Plaintiff suggested a fourth contractor—

Roncelli, which was the contractor who originally built the Chrysler Technology Center. All four

contractors submitted initial bids.

Based on his experience with the Facilities group in a prior project, Plaintiff was concerned

about the integrity of the bidding process for the Museum Project. According to Plaintiff, he had

legitimate reasons to believe that someone in the Facilities group was sharing inside information

about the bidding process with one of the competing contractors—Barton Mallow. Based on his

3 No. 19-1420, Kenya Spratt v. FCA US LLC

suspicion of bias, Plaintiff decided to “massage” some of the numbers in the initial bid summary

sheet. (R. 26-3, Pg. ID 222.) He increased some of the line item bids of Barton Mallow and

Walbridge, but he did not alter the bids of Roncelli or Aristeo. As a result of his interference with

the numbers, the initial bid summary wrongly indicated that the bidder in Column B (Roncelli)

had the lowest overall bid. Prior to Plaintiff’s adjustment of the numbers, Barton Mallow had the

lowest overall bid.

Plaintiff submitted the falsified initial bid summary to Facilities. Based on the summary,

Plaintiff and Facilities decided to eliminate Aristeo (the highest bidder both before and after

Plaintiff’s adjustment of the numbers) and to hold a clarification meeting with the three remaining

bidders. At this time, Facilities still did not know which contractor was associated with which bid

on the initial summary. (Recall that the initial bid summary does not include the contractors’

identifying information in order to prevent bias.) However, around the time of the clarification

meeting, the Facilities project manager for the Museum Project—Slavko Stajninger—discovered

the actual bid numbers of Walbridge and Barton Mallow. Stajninger discovered Walbridge’s bid

number because Walbridge accidentally included its name on an e-mail that included its bid

information. Stajninger discovered Barton Marlow’s bid because Stajninger directly contacted a

representative from Barton Marlow and asked him if his was the lowest bid on the initial summary

sheet. Based on his answers, Stajninger discovered that some of the numbers on the initial

summary sheet had been altered. This triggered an investigation into Plaintiff’s conduct.

After the clarification meeting, the three competing contractors submitted their final bids

for the Museum Project. Plaintiff compiled the bids into a final bid summary sheet, which was

then used to select the contractor who would be awarded the job. Plaintiff did not alter any of the

4 No. 19-1420, Kenya Spratt v. FCA US LLC

Free access — add to your briefcase to read the full text and ask questions with AI

Kenya Spratt v. FCA US LLC, (6th Cir. 2020).

Kenya Spratt v. FCA US LLC (Kenya Spratt v. FCA US LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

McDonnell Douglas Corp. v. Green
411 U.S. 792 (Supreme Court, 1973)
Texas Department of Community Affairs v. Burdine
450 U.S. 248 (Supreme Court, 1981)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Alspaugh v. McConnell
643 F.3d 162 (Sixth Circuit, 2011)
Serge Adamov v. U.S. Bank National Association
726 F.3d 851 (Sixth Circuit, 2013)
Mark Laster v. City of Kalamazoo
746 F.3d 714 (Sixth Circuit, 2014)
Charolette Payne v. Novartis Pharm. Corp.
767 F.3d 526 (Sixth Circuit, 2014)
Curtis Wheat v. Fifth Third Bank
785 F.3d 230 (Sixth Circuit, 2015)
Karon Jackson v. VHS Detroit Receiving Hospital
814 F.3d 769 (Sixth Circuit, 2016)
William Tennial v. United Parcel Serv.
840 F.3d 292 (Sixth Circuit, 2016)
Snyder v. Ohio Department of Rehabilitation & Correction
702 F. App'x 341 (Sixth Circuit, 2017)
Morris Johnson v. Ohio Dep't of Public Safety
942 F.3d 329 (Sixth Circuit, 2019)
Redlin v. Grosse Pointe Pub. Sch. Sys.
921 F.3d 599 (Sixth Circuit, 2019)