Kent v. United States

228 F. Supp. 929, 1964 U.S. Dist. LEXIS 8024
CourtDistrict Court, S.D. New York
DecidedMay 8, 1964
StatusPublished
Cited by5 cases

This text of 228 F. Supp. 929 (Kent v. United States) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kent v. United States, 228 F. Supp. 929, 1964 U.S. Dist. LEXIS 8024 (S.D.N.Y. 1964).

Opinion

WYATT, District Judge.

This is a motion for summary judgment by plaintiff. Fed.R.Civ.P. 56(a).

The government as defendant has asked in an opposing affidavit for summary judgment in its favor and, if otherwise entitled to such judgment, the government may be granted that relief without formal written cross-motion, either (a) on the ground that an oral cross-motion was in effect made at the hearing of the motion or (b) on the ground that no cross-motion is necessary. The proposition last stated is fully supported in 6 Moore’s Federal Practice (2d ed.) 2088-89, where a number of District Court decisions are cited. In Bell v. Waterfront Commission of New York Harbor, 183 F.Supp. 175, 178-179 (S.D. N.Y.1960), Judge Dimock granted a summary judgment to defendant without any cross-motion therefor, declaring: “While defendant has not cross-moved for summary judgment, such a formal motion is not necessary where no issue of fact is in dispute”. This decision was affirmed by our Court of Appeals (279 F.2d 853; 1960) and the practice seems thus inferen tially to have been approved. Judge Dimock followed the same practice in a later case. Banco Nacional de Cuba v. Sabbatino, et al., 193 F.Supp. 375, 386 (S.D.N.Y.1961), affirmed 307 F.2d 845 (1962), reversed on other grounds, 372 U.S. 905, 83 S.Ct. 717, 9 L.Ed.2d 715, 1964.

The action is for $7,803.40 and is by a government contractor for the construction of an approach lighting system and other work at John F. Kennedy International Airport, formerly New York International Airport. The gist of the claim is that the government delayed the completion of the contract, that this delay increased the cost to plaintiff of its performance under the contract, that the delay by the government was a breach of the contract, and that plaintiff is entitled to his increased costs as damages for breach of contract.

[931]*931The jurisdiction of this Court is based on 28 U.S.C. § 1346(a) (2) which ■derives from the Tucker Act of March ■3, 1887, c. 359, 24 Stat. 505, 506. It may be noted that the Tucker Act “for the first time, gave District Courts general authority to hear and determine claims against the Government”. Bates Mfg. Co. v. United States, 303 U.S. 567, 571, 58 S.Ct. 694, 696, 82 L.Ed. 1020 (1938). The purpose was to make it possible for claims against the government for relatively small amounts (less than $10,000) to be prosecuted at the places of residence of the claimants rather than in Washington at the Court of Claims.

Plaintiff bid on the contract on a government bid form which among other things made it clear

(a) that work was to be started within 5 days from the effective date of a Notice to Proceed; and
(b) that work was required to be completed in 75 days from such Notice to Proceed.

The bid form also contained the statement: “Notice to Proceed will be approximately: November 2, 1959”.

The contract was dated September 29, 1959; the date of execution is not stated. The work was primarily the construction of an approach light system and a flasher system for Runway 22L and the dismantling of these two systems on Runways 22R and 4L. A substantial part of the material to be used in the construction on Runway 22L was to come from the dismantling of the systems on Runways 22R and 4L.

The invitation for bids contained this statement: “Estimated Effective date of Notice to Proceed: November 2, 1959.”

The invitation for bids also made clear that the work of dismantling would have to be done in three successive phases, described as follows:

“In order to provide by-directional approach lighting the contractor will be required to carry on work of dismantling in accordance with the following schedule:
“Phase 1 (beginning with the start of construction). The contractor shall be free to dismantle both Systems on Runway 4L.
“Phase 2. (beginning 80 days after the start of construction). The Contractor shall be free to dismantle all components of the flasher system on Runway 22R.
“Phase 3 (beginning with the commissioning of the approach lighting system and the flashers on Runway 22L) The Contractor shall be free to dismantle all components of the Approach Light System on Runway 22R.”

It was also stated that each phase of the work had to be inspected and approved before any work could be done on the next phase.

A “partial” notice to proceed, effective November 9, 1959, was given. The notice was “partial” because it authorized only the commencement of construction of the approach lighting system and flasher system on stations 1 through 10 of Runway 22L.

A notice to proceed — that is, a notice covering all the contract work — was given effective February 8, 1960.

The work was completed on July 5, 1960.

Both plaintiff and the government calculated the days of delay on the assumption that the contract performance time of 75 days began to run on November 9, 1959, the effective date of the “partial” notice to proceed. On this basis, the work should have been completed by February 27, 1960. The date of actual completion — July 5, 1960 — was 129 days later.

The government then took the position that under the stipulated provision in the contract for $50 per day liquidated damages in favor of the government, $6,450 was due the government (129 X $50) and this amount was withheld from plaintiff.

Under date of October 25, 1960 plaintiff asked for an extension of time to cover delays from causes beyond his eon[932]*932trol. Such an extension is provided for in Article 5(c) of the “General Provisions” of the contract.

The contract contained a “disputes” clause (“General Provisions”, Article 6) under which any “dispute concerning a question of fact” must be decided by the Contracting Officer, from whose decision an appeal can be taken to the “head of the department” but the decision on appeal is to be final “unless determined by a court of competent jurisdiction to have been fraudulent, arbitrary, capricious or so grossly erroneous as necessarily to imply bad faith”. (41 U.S.C. § 321)

Apparently plaintiff treated the increased cost to him because of delay as “a question of fact” and submitted this claim to the Contracting Officer.

Under date of November 15, 1960 plaintiff asked for an increase in pay of $7,803.40 under Article 3 (“changes”) of the “General Provisions” of the contract. This article gives the government the right to make changes “in the drawings and/or specifications of this contract” but provides that if “such changes cause an increase or decrease in the amount due under this contract, or in the time required for its performance, an equitable adjustment shall be made * * * ”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M.A. Mortenson Company v. United States
843 F.2d 1360 (Federal Circuit, 1988)
AMERICAN PETROFINA, INCORPORATED v. Brown
391 F. Supp. 757 (E.D. North Carolina, 1974)
Volk v. Zlotoff
285 F. Supp. 650 (S.D. New York, 1968)
Chicora Construction Co. v. United States
252 F. Supp. 910 (E.D. North Carolina, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
228 F. Supp. 929, 1964 U.S. Dist. LEXIS 8024, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kent-v-united-states-nysd-1964.