Kenney v. Pitt

87 A. 480, 111 Me. 26, 1913 Me. LEXIS 77
CourtSupreme Judicial Court of Maine
DecidedJuly 17, 1913
StatusPublished
Cited by1 cases

This text of 87 A. 480 (Kenney v. Pitt) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kenney v. Pitt, 87 A. 480, 111 Me. 26, 1913 Me. LEXIS 77 (Me. 1913).

Opinion

Haley, J.

This is an action of assumpsit, brought on an account annexed to recover a balance of $70 alleged to be due as the balance on a contract for repairing and building an addition to buildings in the town of Wells, and forty-one items claimed to be for extra work and material in repairing the building and building the addition, in all amounting to $528.39. The verdict was for the plaintiff for $453, and the case is before this court on a motion to set aside the verdict as against law and evidence.

Tihe defendant .pleaded the general issue, and recoupment by brief statement.

The defendant claimed at the trial that the plaintiff did not do the work, or furnish the material, according to the contract, that many of the items in the account annexed were for work called for by the contract, and that the plaintiff had been paid more than was due him by the terms of the contract, and for the extra work done and material furnished.

May 14, 1909, the plaintiff entered into a contract with the defendant to build an addition and make repairs to a set of buildings situated in Wells, with specifications attached to the contract. The price named in the contract was $2,060. Another item was afterwards added, making the contract price $2,070, and the plaintiff agreed that the labor and material as per plans was to “give a finished job,” was “to be done in a thorough workmanlike manner,” and that the work was “to be done in good faith and workmanlike manner.”

The testimony clearly shows that the plaintiff’s labor and material did not give a “finished job,” that the work was not done “in a thorough workmanlike manner,” or “in good faith.” The floors were to be of good southern hard pine. It was clearly proved that the floors, when walked upon, buckled for want of sup[28]*28port, so that the grooves broke, and the plaintiff’s explanation of that, was, as the floor was built of short pieces that, if it did break, it ¡could not /break very bad. The plaintiff admitted (after it was proved) that in a room that was nine feet long some of the hard pine flooring was made up of pieces of flooring boards five feet long instead of nine feet in length, as they should have been, and that such work was not good workmanship. The contract called for a “good quality of southern hard pine, .matched,” for the top flooring. The plaintiff admitted that he used for that purpose a quality of southern hard pine known as sea rift flooring, and the testimony is that such pine is ¡one of the poorest grades of southern hard pine, and' that it is not suitable for house floors. In the dado in the dining room, in the space of three widths of the sheathing, there were fifteen knot holes and twelve pitch holes. The skylight in the sun parlor had no bedding for the glass, and in that room the gable end window was nailed together instead of being mortised and tenanted. Some of the glass in the roof of the sun parlor and gable window was not even puttied, but was held in place by brads. The finish was rough, and it was testified that it was all streaked up and torn out as if a rough plane had been used upon some of it. The joints were bad, some of the base boards were flush with the plastering, while other parts of the same board would be three-quarters of an inch from the plastering. Southern pine floors were laid in pieces, some of the pieces as short as eight inches, in the center of the room; the floors were not smoothed after being laid, and the finish and doors were full of knots, one knot in the stile of the door being four inches long and the width of the stile lacking one-quarter of an inch; the floors were marked with -hammer blows; the roof leaked; in the kitchen the floor was laid so that one could look through into the cellar, where there were supposed to have been double floors with paper between; the contract called for the finish to match the finish in the part of the house not repaired, and it did' not. The plaintiff claimed that the leaks came from the gutter of the old house, but it was shown that the water came in the new part built by the plaintiff.

If the jury believed the improbable story of the plaintiff, that the defendant, having a contract with the plaintiff to shingle with [29]*29No. 2 clear cedar shingles, waived that contract and gave consent that the plaintiff might take old pine shingles that came from a shingled wall and use them instead of new cedar shingles, even then, the plaintiff should have laid them in a workmanlike manner, and the evidence proves that they were nailed so close together that when it rained they swelled and broke and blew off the roof, which was not the way shingles do when laid in a workmanlike manner.

To the defendant’s plea of recoupment the plaintiff claimed nothing should be allowed, and it was sought by the examination of the witnesses to prove that the job could not have been done for the contract price, and the same position is taken in the written argument filed in the case. A party who makes a contract to do work for a price certain, cannot come into court and successfully defend his non performance by saying that the contract price is inadequate. Having' agreed to do the work in a certain manner for a certain price, he is bound to do it according to his contract.

The evidence clearly and satisfactorily shows that the plaintiff did not perform his part of the contract. The witnesses who made an examination of the premises described the defects that existed in workmanship and material, and their testimony is attempted to be explained away, not by a denial of the defects and deficiencies, which they enumerated in detail, but by the broad statement of the plaintiff that the material was suitable and the workmanship good, and that the defendant agreed to some of the work now complained of.

The testimony shows that the difference in the value of the property, if the contract had been performed by the plaintiff, and its value as the work was left by him, is from $500 to $700; but what sum the jury should have allowed it is unnecessary for us to discuss, as an examination of other parts of the case shows that, with much less than a reasonable deduction for the poor material and unworkmanlike manner in which the work was performed, the verdict should be set aside.

In the account annexed there is a charge of $116.87 f°r labor and skimming, and one for $40 for lime and plaster of paris. 'The contract called for the plastering to be smoothed to a good surface. The testimony shows that the defendant, by her husband, talked with the mason when he was plastering the rooms and protested [30]*30against the work, that he then protested to the plaintiff and stated that he would not accept the work unless performed according to the contract, that it should be smoothed to a smooth surface. Although the parties do not agree as to what else was said, there is no testimony that the. plaintiff was authorized to skim-coat the rooms and charge the defendant for it as an extra, and the two items, amounting to $156.87, was charged for that work. It was the duty of the plaintiff to plaster the rooms so there would be a smooth surface. With that the defendant was bound to be satisfied, and if the plaintiff could not perform his contract by putting on one coat it was not the defendant’s fault, and as the defendant never authorized, or promised to pay for that labor and material, the two items amounting.to $156.87 should not have been allowed by the jury.

The plaintiff charged in the account for extras for 600 bricks at $18 per thousand that were used in building a chimney in the office built by the plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brunswick Diggers, Inc. v. Anthony Grace & Sons, Inc.
187 A.2d 391 (Supreme Judicial Court of Maine, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
87 A. 480, 111 Me. 26, 1913 Me. LEXIS 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kenney-v-pitt-me-1913.