Brunswick Diggers, Inc. v. Anthony Grace & Sons, Inc.

187 A.2d 391, 159 Me. 21, 1963 Me. LEXIS 3
Supreme Judicial Court of Maine·Decided January 22, 1963·Published·Cited by 3 cases

Opinion

Webber, J.

The defendant, hereinafter called the Builder, was a general contractor employed by the United States Navy to complete land development and the construction in Brunswick of 277 dwelling units for military service personnel. The plaintiff, hereinafter referred to as the Contractor, was organized as a corporation by its owner and sole stockholder, Mr. Allen, to subcontract a portion of the work involved in the project. On July 11, 1959 the parties entered into a written agreement by which the Contractor undertook the initial work of “clearing and grubbing” for the sum of $20,440. Plaintiff actually commenced work a few days before the formal execution of the contract. On July 22, 1959, again by written agreement, plaintiff contracted to excavate and backfill the foundations for the 277 dwelling units for the sum of $55,775. In addition, plaintiff was to excavate, trim and backfill for sewer and water connections (called “laterals”) from the foundations to the street lines for a unit price of 50c per lineal foot. On *23 August 13, 1959 the parties entered into a third written contract by which plaintiff agreed to install certain elements of the surface drainage system for the sum of $38,-500. It is not disputed that some time in November, 1959 the parties entered into an oral agreement by the terms of which the Contractor was to construct roadways, sidewalks and utilities outside the main project location but connected with it. For this “off site” work plaintiff was to receive $28,000. The contracts called for payments by the Builder on monthly requisitions. At the request of the Contractor, however, payments were made weekly in advance, the amount of these advances being determined by separate agreement as to each. On April 18, 1960 the Contractor wrote to the Builder as follows:

“This is to notify you that any contractual relations between your company and Brunswick Diggers, Inc. has been breached and, therefore, I expect your company to advance capital to pay for materials,, rentals, and labor.
It was agreed that your company would supply the necessary capital to expedite the contract. This you have failed to do. Also in order to expedite your work we have cooperated to the extent that we have done much extra work which was not contracted for. The extent of the extra work is so great and intermingled with that contemplated in the contract I can see no other way but to continue work on a cost plus basis or renegociate (sic).
In reference to payments and payment of bills, the only reason that we haven’t paid all bills to date is because we haven’t been paid enough by your company.
Please advise on what basis you wish to settle this situation as Brunswick Diggers, Inc. can work no longer without knowing how you intend to advance operating money.”

*24 It may be noted in passing that the plaintiff adduced no evidence that the defendant had agreed to “supply the necessary capital to expedite the contract.” Before writing the foregoing letter claiming breach of contract, the plaintiff had ceased operations with about 70% of its work completed. The plaintiff had received advances of $118,770.87 and when it ceased operations it owed about $45,000 to material men and suppliers whose claims became an obligation of the defendant under the “Miller Act” so-called. When requested to state its conditions for performance of the contracts, the plaintiff demanded a renegotiation which would provide approximately $73,000 additional for work claimed to have already been done and a further sum of $70,000 for the work remaining. These conditions were rejected by the defendant, which then completed the work at a cost to itself of $53,655.88. Plaintiff brought its action asserting breach of contract and defendant responded by counterclaim. A jury returned a verdict for the plaintiff in the sum of $72,000. Defendant seasonably filed its appeal from the judgment below.

Since the plaintiff has raised some question as to what may be open to the defendant on appeal, we take this occasion to comment on the amendment to M. It. C. P. Rule 73 (a) promulgated August 1, 1962 which provides:

“An appeal from a judgment preserves for review any claim of error in the record including any claim of error in any of the orders specified in the preceding sentence. An appeal shall not be dismissed because it is designated as being taken from such an order, but shall be treated as an appeal from the judgment.”

This amendment was not intended to add to or change the substance of the Rule as it stood before amendment, but was adopted for the purpose of clarification and to resolve any doubts which may have been created by the language *25 of dicta contained in Knowles v. Jenney, 157 Me. 392. See 1962 Supplement to Field & McKusick, Maine Civil Practice, page 58.

Free access — add to your briefcase to read the full text and ask questions with AI

Brunswick Diggers, Inc. v. Anthony Grace & Sons, Inc., 187 A.2d 391, 159 Me. 21, 1963 Me. LEXIS 3 (Me. 1963).

187 A.2d 391 (Brunswick Diggers, Inc. v. Anthony Grace & Sons, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

SHERIFF v. GARDNER
D. Maine, 2022
H&B Realty, LLC v. JJ Cars, LLC
2021 ME 14 (Supreme Judicial Court of Maine, 2021)
Drew Brown Limited v. Joseph Rugo, Inc.
436 F.2d 632 (First Circuit, 1971)