Kelsay Lumber Co. v. Rotsky

178 S.W. 837, 1915 Tex. App. LEXIS 863
CourtCourt of Appeals of Texas
DecidedJune 7, 1915
DocketNo. 803. [fn†]
StatusPublished
Cited by5 cases

This text of 178 S.W. 837 (Kelsay Lumber Co. v. Rotsky) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kelsay Lumber Co. v. Rotsky, 178 S.W. 837, 1915 Tex. App. LEXIS 863 (Tex. Ct. App. 1915).

Opinions

8224 Writ of error pending in Supreme Court. *Page 838 This suit grows out of two building contracts, made between Rotsky, as the owner of the property, one Helms, as the contractor, and Fidelity Deposit Company of Maryland, as surety, upon the contract of Helms. For the sake of brevity, plaintiff in error Kelsay Lumber Company will hereinafter be referred to as the Lumber Company, plaintiff in error Fidelity Deposit Company as the Surety Company, the defendant in error Rotsky as the owner, Helms as the contractor, and the other defendants in error, who sought to foreclose liens for labor and material, as interveners.

On the 6th day of March, 1912, the owner made a contract in writing with the contractor, whereby the said contractor should furnish the material and do all the labor necessary to the construction of a certain twostory brick building, to be erected upon a certain lot in Ft. Worth, Tex. The work and material were to be according to drawings and specifications made by the owner's architect Weinman. A printed form of contract was filled out by the architect and signed by the contractor as principal and by the Surety Company as surety. After the construction of this building had commenced the owner decided to erect a similar building on a lot adjoining the first, so that upon the performance of the contract he would have a building 50 × 97 feet, instead of one 25 × 97 feet, as provided for in the first contract. Accordingly, on the 15th day of April, 1912, the second contract between the same parties was entered into. The contract price of the two buildings was $10,000. The bonds executed by the Surety Company were in the total sum of $5,000. Thereafter the construction of the two buildings was carried out as under one contract. The contracts being identical, save as to the description of the property, and the contract price, among others, contained the following provisions:

"1. The contractor shall well and sufficiently perform and finish, under the direction and to the satisfaction of L. B. Weinman, architect, acting as agent of said owner, all the work included in the plans and specifications of a twostory brick business building (including all plumbing, also to bar fixtures, all wiring and screening of first and second floors, Agee Bros. make). * * * All work and material to be agreeably to the drawings and specifications made by said architect and signed by the parties hereto (copies of which have been delivered to the contractor), and to the dimensions and to the explanations thereon, therein and herein contained, according to the true intent and meaning of said drawings and specifications, and of these presents, including all labor and materials thereto and shall provide all scaffolding, implements and cartage necessary for the due performance of said work."

"13. And it is hereby mutually agreed between the parties hereto that the sum to be paid by the owner to the contractor for said work and materials shall be sixty-two hundred and no/100 ($6,200.00) dollars, subject to the additions or deductions on account of alterations hereinbefore provided, and that such sum shall be paid in current funds by the owner to the contractor in installments as follows: Seventy-five per cent. for material and labor installed in the building, on weekly estimates issued by the architect; it being understood that the final payment shall be made within three days after this contract is completely finished; provided that in each of the said cases the architect shall certify in writing that all the work upon the performance of which the payment is to become due, has been done to his satisfaction; and provided further, that before each payment, if required, the contractor shall give the architect good and sufficient evidence that the premises are free from all liens and claims chargeable to the said contractor; and further that if at any time there shall be any lien or claim for which, if established, the owner of the said premises might be made liable and which would be chargeable to the contractor, the owner shall have the right to retain out of any payment then due or thereafter to become due, an amount sufficient to completely indemnify him against such lien or claim until the claim shall be effectually satisfied, discharged or canceled; and should there prove to be any such claim, after all payments are made, the contractor shall refund to the owner all moneys that the latter may be compelled to pay in discharging any lien on said premises made obligatory in consequence of the former's default."

"15. And the said owner hereby promises and agrees with the said contractor to employ and does hereby employ him to provide the materials to do the said work according to the terms and conditions herein contained and referred to for the price aforesaid and hereby contracts to pay the same at the time and in the manner upon the conditions above set forth."

It was further provided in the contract that in the event the contractor should refuse to supply a sufficient number of skilled workmen, materials of the quantity and quality provided for therein, such neglect or failure being certified by the architect to *Page 839 the owner, then the owner should, at his option, after three days' written notice to the contractor, provide such labor and materials and deduct the costs thereof from any money due or to become due the contractor; or in the event the architect deemed the cause sufficient, the owner, upon the certificate of the architect, was at liberty to terminate the employment of the contractor and to take possession of the premises and complete the building and withhold any further payments to the contractor until the building was completed; thereupon the owner should pay to the contractor any difference between the amount required to complete the building and the contract price. In the event the owner should be unable to complete the building for the amount of the unpaid contract price, then the contractor should repay to the owner such excess.

The conditions of the bonds accompanying the contracts executed by the Surety Company are identical, and are as follows:

"Now, if the said contractor shall well and truly perform and fulfill all and every the covenants, conditions, stipulations and agreements in said contract mentioned, as to be performed and fulfilled by him, and if the said contractor shall repay to the said owner all sums of money which he may pay to other persons on account of work and labor done or materials furnished, which said contractor may fail to do or furnish, and shall pay to the said owner all damages he may sustain and all forfeitures to which he may be entitled by reason of the nonperformance on the part of said contractor of any of the covenants, conditions, stipulations and agreements of said contract, then this obligation shall be void," etc.

The building was completed by the contractor on or about the 1st day of August, 1912. About the middle of June, 1912, some of the interveners filed with the owner notice of their claims, and thereafter liens were filed from time to time until September 1st following. It was discovered by the architect, about the middle of June, that the contractor would not be able to complete the contract by the use of the 75 per cent. payments made upon the weekly estimates. The estimates furnished by the architect are the same except as to the date, the amount due, the balance in the hands of the owner under the contract, and the amount previously paid.

The Lumber Company instituted suit to recover the sum of $3,167.65, and to foreclose the materialman's lien, making the owner, the contractor, and the Surety Company defendants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

American Surety Co. of New York v. Wm. Cameron & Co.
35 S.W.2d 217 (Court of Appeals of Texas, 1930)
Fidelity & Deposit Co. of Maryland v. Kelsay Lumber Co.
29 S.W.2d 1052 (Texas Commission of Appeals, 1930)
Southwest Nat. Bank v. Employers' Indemnity Corp.
12 S.W.2d 189 (Texas Commission of Appeals, 1929)
Rotsky v. Kelsay Lumber Co.
228 S.W. 558 (Texas Commission of Appeals, 1921)

Cite This Page — Counsel Stack

Bluebook (online)
178 S.W. 837, 1915 Tex. App. LEXIS 863, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelsay-lumber-co-v-rotsky-texapp-1915.