American Surety Co. of New York v. Wm. Cameron & Co.

35 S.W.2d 217
CourtCourt of Appeals of Texas
DecidedDecember 31, 1930
DocketNo. 989.
StatusPublished
Cited by1 cases

This text of 35 S.W.2d 217 (American Surety Co. of New York v. Wm. Cameron & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
American Surety Co. of New York v. Wm. Cameron & Co., 35 S.W.2d 217 (Tex. Ct. App. 1930).

Opinion

BARCUS, J.

In November, 1926, Southwell & Abbott, a partnership, made a contract with T. B. Ellison to construct a warehouse at a cost of $28,144. Under article 5 of the contract, it is provided that the final payment would be made when the work was completed and accepted by the architect, and specifically provides:

“Before issuance of final certificate the contractor shall submit evidence satisfactory to the architect that all pay rolls, material bills and other indebtedness connected with the work have been paid.”

Under article 9 the contractors were required to pay for all labor and material used in the construction of the building. Under article 24 the contract provides that the contractor shall submit to the architect, before any receipt or voucher is issued, if required, receipts showing that he has paid for all material, labor, and all subcontractors. Article 25 provides:

“The making and acceptance of the final payment shall constitute a waiver of all claims by the owner other than those arising from unsettled liens from faulty work appearing after final payment or from requirements of the specifications and of all claims by the contractor except those previously made and still unsettled.”

Under article 30 the owner had a right to require the contractors to furnish a bond that they would pay all obligations arising out of the erection of the building. Article 32 of the contract provides that the final payment shall not be due until the contractor has furnished receipted bills. and releases for all-labor and material used for which a lien could be filed. Subdivision “O” of article 37 provided:

"Nothing in this article shall create any obligation on the part of the owner to pay to or to see to the payment of any sums to any sub-contractor.”

At the time the said contract was made, Southwell & Abbott furnished a bond in the sum of $15,000, signed by appellant, American Surety Company of New York as surety, and payable to T. B. Ellison, and made the contract a part thereof. Said bond contains the following condition;

“Now therefore, the condition of this obligation is such that if the principal shall faithfully perform the contract on his part and satisfy all claims and demands incurred for the same and shall fully indemnify and save harmless the owner from all cost and damage which he may suffer by reason of failure so to do and shall fully reimburse and repay the owner all outlay and expense which the owner may incur in making good any such default and shall pay all persons who have contracts directly with the principal for labor or materials, then this obligation shall be null and void, otherwise it shall remain in full force and effect.”

On March 7, 1927, the building, having been completed, was accepted by T. B. Ellison, and he paid Southwell & Abbott the balance due on said contract, to wit, $6,717.80, which was by them deposited in the bank for the purpose of paying same to the subcontractors, ma-terialmen, and laborers, but said money was without the consent of Southwell & Abbott used by the bank to pay debts owing by said contractor to said bank. Southwell & Abbott failed to pay Win. Oameron & Company, Inc., $4,317.34, and Miller Brothers $229.60, and the Southern Ornamental Iron Works $455.54, and the Acme Brick Company $2,-180.32, and the Builders’ Material Company $47.81, and B. S. Matson $606.60, and Chas. T. Davis $111.84, and the North Texas Iron & Steel Company $966.86, and the Fort Worth Sand & Gravel Company $579.38; and the Col-linsville Manufacturing Company $1,074.77, *219 which they owed said parties for material or labor that was furnished in the construction of said building. None of said parties filed or fixed any lien against the building in accordance with the law, neither did T. B. Ellison have any notice within thirty days after he made the final payment to the contractors that said claims were not paid.

Wm. Cameron & Company, Inc., instituted this suit to recover from Southwell & Abbott, the American Surety Company of New York, and T. B. Ellison the amount of its debt and sought to establish a lien against the property. Each of the other claimants filed pleas of intervention seeking the same recovery. T. B. Ellison, the owner, answered denying liability and specifically alleging that none of the .parties were entitled to any lien against the property, and by way of cross-action he sought as trustee for the plaintiff and inter-veners judgment against Southwell & Abbott, the partnership, and the American Surety Company of New York, for the respective amounts as claimed by Wm. Cameron & Company, Inc., and .the various interveners, alleging that he had taken the indemnity bond for their use and benefit and that he was entitled to recover the aggregate of said sums as trustee for said named parties. He further claimed that he was entitled to $1,500 attorney’s fees by reason of his having been forced to employ, attorneys to defend him against the suit as brought by said parties and in the prosecution of his claim as trustee against appellant American Surety Company of New York and that it was liable therefor under and by virtue of the provisions of the bond. Appellant' answered by general demurrer, a number of special exceptions, and specially alleged that it was not liable on the bond to the plaintiff or any of the interveners because the bond was not payable to them and that it was not liable to T. B. Ellison because neither the plaintiff nor any of the interveners had any claim against T. B. Ellison or lien against his property, and it specifically denied the right of T. B. Ellison as owner to recover as trustee for appellees. Southwell & Abbott alleged .that they had filed their petition in bankruptcy and had been discharged.

The cause was tried to .the court and resulted in judgment being entered for Wm. Cameron & Company, Inc., and each of the named interveners for the amount of their debt against the American Surety Company of New York and in favor of T. B. Ellison against the American Surety Company of New York for $750, attorney’s fees, and judgment in favor of Ellison denying any of the parties a personal judgment against him or a lien against his property, and a judgment in favor of Southwell & Abbott on their plea of discharge in bankruptcy. Appellant alone appeals.

Appellant, by various propositions, contends that the judgment against it in favor of the laborers and materialmen is erroneous because the bond was not payable to nor did it inure to their benefit. We sustain this contention. Bonds conditioned almost exactly as the one in controversy here have been before our courts a number of times and all that can be has been written thereon by our .courts. The established rule in Texas seems to be that a bond as the one here being payable only to a private individual does not inure to the benefit of subcontractors, materialmen, or laborers who supply materials for or work on the building. National Bank of Cleburne v. G., C. & S. E. Ry. Co., 95 Tex. 176, 66 S. W. 203; Gen’l Bonding & Casualty Ins. Co. v. Waples Lbr. Co. (Tex. Civ. App.) 176 S. W. 651; Oak Cliff Lbr. Co. v. American Indemnity Co. (Tex. Civ. App.) 266 S. W. 429; Murphy v. Huey & Philp Hdw. Co. (Tex. Civ. App.) 267 S. W. 338; Garrett v. McAdams Lbr. Co. (Tex. Civ. App.) 163 S. W. 320; Foust v. Bibb (Tex. Civ. App.) 258 S. W. 921, reversed on other grounds (Com. App.) 272 S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

WM. Cameron & Co. v. American Surety Co. of New York
55 S.W.2d 1032 (Texas Commission of Appeals, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
35 S.W.2d 217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/american-surety-co-of-new-york-v-wm-cameron-co-texapp-1930.