Kelly v. Thompson, No. Cv95 04 92 83s (Nov. 15, 1995)
This text of 1995 Conn. Super. Ct. 12955 (Kelly v. Thompson, No. Cv95 04 92 83s (Nov. 15, 1995)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
It appears from the facts that the defendants owned property at 71 Hillside Avenue, Milford, which was heavily damaged during a hurricane. The house was damaged to the extent that what remained was the foundation. Some items of plumbing along with a stained glass window were salvaged. The plaintiff agreed to construct a new home on the foundation, installing the items that were salvaged for the sum of $128,000.00. The plaintiff commended work in February of 1994 and continued until sometime in September of the same year when he was ordered off the job. He thereafter filed a Notice of Intention to Lien along with the Mechanic's Lien claiming he was owed the sum of $28,000.00.
Plaintiffs testified that the job was almost complete with about $1,000.00 of the work remaining to be done. The defendant testified that the defendant was late in completing the job and that about $5,000.00 worth of work remained to be done. The work was commenced during a winter of severe storms causing the plaintiff to fall behind in his schedule. Nevertheless, he was behind only two weeks at the time he was taken off the job.
The defendants claim that this was a remodelling or reconstruction of an existing house and, since the agreement was not in writing, it was in violation of the Home Improvement Act, section
The issue for the court to determine is whether the plaintiff established probable cause to sustain the validity of his lien and, if so, whether the defendants have shown by clear and convincing evidence that the plaintiff is not entitled to the lien and that therefore it should be discharged.
Probable cause is a bona fide belief in the existence of the facts essential under the law for the action and such as would warrant a man of ordinary caution, prudence and judgment, under the circumstances in entertaining it. Wall v. Toomey,
To determine whether there is probable cause to grant the CT Page 12957 remedies requested, the trial court is vested with a broad discretion. Price Saveer, Inc. v. Maynard,
The mechanic's lien statute is remedial in nature, designed to furnish security for a contractor's labor and materials.Reve Dry Wall Co. v. Strawberry Hill Associates,
Plaintiff commenced work at the defendants' direction. The work was substantially complete. A significant amount of this work was unpaid for by the defendant despite a demand being made for its payment. Testimony of the plaintiff shows the amount of $28,247.00 being owed with $1,000.00 worth of work remaining.
The testimony of the defendant admits that she engaged the plaintiff to do the work; that he completed a substantial part of the work; the only difference being that the expenditure of $5,000.00 was necessary to complete the work.
The defendant argues that the work in question constituted a renovation and was therefore a home improvement, thus requiring, under the terms of the Home Improvement Act section
Section
The defendant relies on an unreported case, SeaportElectric v. Friedlander, Docket No. CV91 0120366S, (May 24, 1993) Superior Court Judicial District of Stamford/Norwalk at Stamford, wherein a portion of the former home remained but that 90% of the dwelling was new. The court in that instance relied on the standard definition of the word "replace" as meaning "to take or fill the place of something." CT Page 12958
In the case before this court, the only items salvaged were the foundation, a stained glass window, kitchen sink and the bathroom sink and faucet.
With the few items salvaged this can hardly be called a "Home Improvement". It amounts to the construction of a new house. The defendant has not proven by clear and convincing evidence that the lien is invalid. The plaintiff has, however, sustained his burden as to probable cause. The Motion to Discharge the Mechanic's Lien is denied.
The Court Curran, J.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
1995 Conn. Super. Ct. 12955, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kelly-v-thompson-no-cv95-04-92-83s-nov-15-1995-connsuperct-1995.