Kelly v. City of New York

106 A.D. 576, 94 N.Y.S. 872, 1905 N.Y. App. Div. LEXIS 2634
Appellate Division of the Supreme Court of the State of New York·Decided July 1, 1905·Published·Cited by 1 cases

Opinion

McLaughlin, J.:

The aqueduct commissioners of the city of New York, on the-20th of August, 1899, advertised for sealed proposals for “ building overflow and blow-off sewers, water pipes and appurtenances in connection with the Jerome Park Reservoir of the New Croton Aqueduct, * * * and particularly for a sewer on East Two hundred and Fourth street in said city.”

The plaintiffs submitted a proposal, which was accepted, and on the 18th of. September, 1899, ¡a contract was entered into between them and the aqueduct commissioners, acting for and on behalf of' the city, one of the provisions of which required the plaintiffs to commence work within ten days thereafter and to complete the same on or before July 1, 1900. Anticipating, however, that-they would be unable to. finish the work within the time stipulated,, they, bn the 23d of June, 1900, obtained an extension until November 30, 1900.' On the 16th day of November, 1900, they obtained a second extension "to June 1, 1901. The work to be done and the materials to be furnished by the plaintiffs under their contract was to dig a trench: and'place therein water mains and a sewer running-from the easterly end of East Two Hundred and Fourth street at its' j'undtibn with Mosholu Parkway south to Jerome avenue" and north in Jerome avenue to a high service pumping station, and was part; pf the work undertaken by the city to perfect a system of water supply made necessary by the building of the Jerome Park reservoir.

■ As a part of this system, the department of water supply, on the 26th of October, 1899, made a contract with one Gildersleeve to-make the necessary excavation and construct the foundation walls.for a high service pumping station at or near one end of the work agreed, to be performed by the plaintiffs, and to make the necessary connections with such work .when completed. 'Gildersleeve agreed to commence work within ten days after the execution of his contract and to complete the same within 200 days thereafter — Sundays and holidays excluded — unless delayed by the elements or the action of the other party to the contract. He did not complete his contract -Within the time specified, either because the plaintiffs had not completed their work, so that he could make the necessary connections, or for. other reasons. In December, 1900, however, he had excavated sufficiently to, and had built the foundation and cellar walls. [579] and a sewer which extended under the bottom. of the cellar the whole length of the proposed building, and then from it to what is termed “ Manhole 18,” the point or place on the plaintiffs’ work where the pipes and sewers were to be connected. Surface water accumulated from time to time in the excavation made by Gilder-sleeve and during the progress of the work carried on by him it was necessary to pump out the same. When he quit work, however, which he did for a tithe in December, 1900, he stopped pumping and the surface water or some part of it which thereafter accumulated in the cellar, either percolated through the earth or was-thrown by the sewer, or both, into the trench contracted to be dug by the plaintiffs, doing them a large amount of damage, to recover which this action was brought, on the ground that it was an act of negligence on the part of the city in causing or permitting the water to accumulate in the excavation made by Gildersleeve. The particular act of negligence alleged in the complaint was that: “Between March 1, 1900, and January 1, 1901, the defendant caused a large excavation to be made in the earth adjacent to the aforesaid trench excavated by the plaintiffs, and carelessly and negligently connected said excavation and the plaintiffs’ line of work by a sewer, pipes and other openings, with the aforesaid trench, and carelessly and negligently caused or suffered and permitted a great quantity of water to accumulate in said excavation, without taking any means to prevent said water, by percolation through the intervening bank of earth, and by flowing through the aforesaid sewer, pipes and other openings, from flowing in large quantities into the aforesaid trench constructed by the plaintiffs.” The answer put in issue the material allegations of the complaint..

At the trial much evidence was offered by the respective parties bearing upon the issue involved and at the conclusion of which the jury rendered a verdict in favor of the plaintiffs, and from the judgment entered thereon the defendant has appealed.

I am of the opinion that the judgment should be reversed. There is no basis for the claim made by the plaintiffs against the city and the evidence does not sustain the jury’s verdict. Before the plaintiffs could recover they were obligated to show some breach of duty on the part of the defendant either by omission or commission, and this they failed to do. It is conceded that the city has. paid all it [580] agreed to pay under the contract, but it is claimed it is liable for the damages sustained outside and independent of the contract. .

Free access — add to your briefcase to read the full text and ask questions with AI

Kelly v. City of New York, 106 A.D. 576, 94 N.Y.S. 872, 1905 N.Y. App. Div. LEXIS 2634 (N.Y. Ct. App. 1905).

106 A.D. 576 (Kelly v. City of New York) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Leahy v. City of New York
116 A.D. 442 (Appellate Division of the Supreme Court of New York, 1906)