Keith B. Alexander v. Eddie Kent

480 S.W.3d 676, 2015 Tex. App. LEXIS 11521, 2015 WL 6759333
Court of Appeals of Texas·Decided November 5, 2015·No. 02-13-00469-CV·Published·Cited by 10 cases

Opinion

OPINION

ANNE GARDNER, JUSTICE

Eddie Kent sued K.B. Alexander Co. of Texas, Inc. (KBA) and Keith B. Alexander (Alexander), individually, for breach of contract and fraud in the course of performance by KBA of a contract for construction of a car lot. Kent alleged KBA and Alexander obtained progress payments. from Kent based upon false payment .applications misrepresenting that subcontractors had been paid for their work on the project when they had not. When KBA declared bankruptcy, Kent nonsuited KBA and proceeded on his fraud claim against Alexander, individually. After a bench trial, the trial court rendered judgment. in favor of Kent for fraud against Alexander, awarded Kent $20,061.32 in actual damages and $25,249.97 in attorney’s fees, and made findings of fact and conclusions of law to support the judgment. Alexander appeals from the judgment against him.

Alexander presents ' Seven issues, contending that (1) the pay applications’ verbiage did not constitute fraudulent representations; (2) Kent’s .equal access to subcontractor information is fatal to his claim; (3) Kent did not justifiably rely on the pay applications; (4) Kent produced no evidence that Alexander intended at the outset of the contract not to perform; (5) the pay applications were not signed by Alexander, individually, precluding individual fraud liability; (6) there is legally and factually insufficient evidence to support the attorney’s fees awarded to Kent; and (7) there is factually insufficient evidence to support the damages award. We affirm in part and reverse and render in part.

BACKGROUND

Alexander was president and sole stockholder of KBA, a construction company. In 2006, Kent obtained bids from, several contractors and chose KBA as general contractor to construct a car lot and an office building,for his used car business, “Easy Ed’s Autos.” KBA agreed to build a 20,-000-square-foot fenced concrete lot and an 800-square-foot building with a storefront.

The Construction Contract

By a written standard form construction contract entered into between the parties, KBA agreed to act as general contractor on the project and to provide all labor, materials, equipment, and services necessary to complete the work. 1 Whatever work KBA did not perform itself would be performed by subcontractors. The parties agreed on a “lump sum” contract price for the project of $383,871, which Kent would pay through a series of monthly progress payments. Article 9 of the contract set out the specific provisions regarding payment. KBA was to prepare a schedule of values apportioned to the various categories of the work, with the total of all values to equal the contract price. The schedule of values for Kent’s project cpntained seventeen separate categories of work to be performed.

Each month, KBA was to submit an “application for payment” to Kent for payment of an amount that would be itemized and supported by, KBA’s schedule of val *681 ues and any other substantiating data required by the contract. The total of the payments would equal the lump sum contract price.. Kent, agreed to pay the amount due on each payment, application, less retainage, within ten days, of receipt.

•Under the terms of the contract, Kent had the right to require partial lien and claim waivers from KBA in the amount of the payment applications and affidavits from subcontractors and material suppliers for work that had been completed at that time as a prerequisite to .payment. . He also had the right to adjust or reject a payment application or nullify a previously approved application for any failure of KBA to properly pay subcontractors or material suppliers. If Kent made timely payments but a subcontractor filed a lien against Kent’s property, KBA had thirty days to -remove the lien, and if it failed- to do- so, Kent could remove the lien himself and recover his costs and expenses directly from KBA.

The Applications for Payment

Beginning in September 2006 and continuing during the course of construction, KBA presented monthly applications for payment to Kent, each entitled “APPLICATION AND CERTIFICATE FOR PAYMENT,” requesting payment for work completed at the time each application was presented. Alexander signed and swore to each application as “President” of KBA. Only the last three applications for payment are at issue in this case. 2 The first of the three applications at issue was dated November 20, 2006, represented that work had been completed totaling $228,563, less previous certificates of payment by Kent of $96,787, and requested payment from Kent of $120,346. The second application at issue, dated December 20, 2006, stated that work had been completed totaling $359,719, less previous certificates of payment by Kent totaling $217,133, and requested. payment from Kent of $129,307. - The third and final application for payment at issue was dated January 19, 2007, reflected that all work was 100 percent completed, and requested Kent to pay the balance of the contract price.

Each application submitted by KBA to Kent for payment was supported by an itemized schedule of values showing the percentage of work completed to that date for each of the categories of work listed on the schedule, the dollar amounts previously paid by KBA to subcontractors for their work completed, the total dollar amount of previous payment applications presented to and paid by Kent, and the dollar amount being charged to Kent for progress on the job since the previous payment application. Each application contained this certification:

The undersigned Contractor certifies that to the best of the Contractor’s knowledge, information and belief the Work covered by this Application for Payment has been completed in accordance with the Contract Documents, that all amounts have been paid by the Contractor for Work for which previous Certificates of Payment were issued and payments received from Owner, and that current payment shown herein is now due.

Shari Riddle, KBA’s project coordinator, kept the books and prepared the applications. for payment. She would receive information about the work completed to date from pay applications (similar to the payment applications submitted by KBA-to *682 Kent) filled out by the subcontractors and submitted to KBA as to what work they had completed each month, as verified by KBA’s project manager. She would input the information and create a payment application to be submitted by KBA to Kent. The payment applications were presented to the architect to verify the percentage of work completed. She would then present the payment applications to Alexander, who would sign each payment application as “President” of KBA, and Riddle would notarize his signature on each application as “subscribed and sworn to” before her. Each application for payment would then be sent by KBA to Kent by fax or by delivery by a project manager for payment.

When Kent received each payment application, he took it to his bank and drew against his loan for the project and then wrote a check to KBA. He would take the check to KBA’s office and go over the pay-application with Riddle.

Free access — add to your briefcase to read the full text and ask questions with AI

Keith B. Alexander v. Eddie Kent, 480 S.W.3d 676, 2015 Tex. App. LEXIS 11521, 2015 WL 6759333 (Tex. Ct. App. 2015).

480 S.W.3d 676 (Keith B. Alexander v. Eddie Kent) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related