Kearns v. McIntyre Construction Co.

567 P.2d 433, 173 Mont. 239, 1977 Mont. LEXIS 664
CourtMontana Supreme Court
DecidedJuly 28, 1977
Docket13405
StatusPublished
Cited by34 cases

This text of 567 P.2d 433 (Kearns v. McIntyre Construction Co.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kearns v. McIntyre Construction Co., 567 P.2d 433, 173 Mont. 239, 1977 Mont. LEXIS 664 (Mo. 1977).

Opinion

MR. JUSTICE DALY

delivered the opinion of the Court.

Defendants appeal from the final judgment of the district court, Silver Bow County. The district court, sitting without a jury, found for plaintiff and decreed that plaintiff recover from defendants the full amount of plaintiff’s alleged damages, $9,160.01, with interest, plus costs in the amount of $19.40.

Plaintiff brought this action to recover money damages for injuries purportedly caused by defendants to plaintiff’s real and personal property. The injuries occurred on a ranch near Melrose, Montana, owned by plaintiff. A portion of the ranch was condemned by the State of Montana for the purpose of constructing a highway. Defendants, acting in a joint venture, contracted with the State Department of Highways, to construct the new highway. To complete its highway construction contract, it was necessary for defendants to obtain quantities of gravel and borrow (earth taken from one location to be used for fill at another location).

Defendants entered into two written contracts with plaintiff. The first contract, executed on May 17, 1972, hereinafter referred to as the gravel agreement, gave defendants the right to remove rock, gravel, sand and earth from plaintiff’s land for the price of 4C per ton. The contract specified: (1) The area on plaintiff’s land from which these materials were to be take, (2) granted defendants the right of ingress and egress to remove these materials, and (3) that defendants could extract as much gravel material from plaintiff’s property as they deemed necessary to satisfy their construction needs, with a required minimum quantity of 110,000 tons.

The second contract, apparently executed on May 16, 1972, hereinafter referred to as the borrow agreement, gave defendants the right to remove borrow material, consisting of rock, gravel, silt, sand and earth, from a specified tract of plaintiff’s land for the price of 2C per cubic yard. The contract granted defendants *242 the right of ingress and egress to extract as much borrow material as defendants deemed necessary to satisfy their construction needs. Defendants, as additional consideration, agreed to provide the services of land scrapers, levelers and rippers for a specified period of time.

This action was commenced on September 4, 1974, when plaintiff filed his original complaint. The original complaint sought to recover money damages in the amount of $16,611.90, plus costs. Subsequent to the filing of the original complaint, plaintiff and defendants settled certain claims which were asserted. On March 21, 1975, plaintiff filed an amended complaint, recognizing and acknowledging defendants had paid to plaintiff the sum of $3,295.90, and sought further money damages in the following amounts:

“6.

“That in addition to the amount of $288.00 due from Defendants to Plaintiff as alleged in Paragraph 5, there are other sums due by reason of damages caused by Defendants to Plaintiff as follows:

“a. Defendants have failed to restore the Plaintiff’s fields where they were cut down and damaged by Defendants’ trucks;

“b. Defendants damaged a crossing-pipe belonging to Plaintiff when a fuel truck got stuck;

“c. Defendants cut, removed, and destroyed a 12" irrigation pipe 40' long, and in attempting to repair the irrigation line made an improper installation resulting in leaking of the irrigation pipeline and causing dirt, gravel, and rocks to fill in said pipeline.

“d. Defendants failed to put gravel on the ditch road as agreed.

“e. Defendants failed to do repair work on the lane as agreed.

“f. Defendants damaged 43 acres of land because Defendants created a situation where Plaintiff was unable to shut off irrigation water on said lands which will require disking, harrowing, and seeding.

*243 “g. Defendants in connection with backsloping failed, neglected, and refused to do the same in a careful and prudent manner to the Plaintiff’s damage for necessary backsloping, repair of fences, and installing drainage facilities.

“h. Defendants carelessly and negligently shut off, or failed to supply, water for hay production to Plaintiff’s damage.

“And that all of said acts of the Defendants were to the Plaintiff’s additional damage in the amount of $9,258.68.”

Subsequent to the filing of the amended complaint, defendants effected discovery through written interrogatories and plaintiff’s deposition. On April 9, 1975, defendants filed a motion to dismiss. The trial court record fails to disclose any ruling by the district court on this motion.

On April 21, 1975, defendants answered plaintiff’s amended complaint. Defendants’ answer generally denied plaintiff’s allegations yet admitted defendants’ past indebtedness to plaintiff in the amount of $9,611.90, subject to an offset in the amounts of $6,316.00, which comprised the cost of installing 350 feet of irrigation pipe at $12.00 per lineal foot, and $2,116.00, the cost for land leveling services performed by defendants. Defendants further denied any indebtedness alleged in paragraph 6, subsections (a), (b), (c), (f), (g), and (h) of plaintiff’s amended complaint since those claims were barred by the statute of limitations, section 93-2607(2), R.C.M.1947.

On November 12, 1975, defendants filed a motion for summary judgment pursuant to Rule 56, M.R.Civ.P. Briefs were submitted in support of and in opposition to defendants’ motion for summary judgment. On January 9, 1976, the district court issued its order summarily denying defendants’ motion. The district court failed to file any opinion or memorandum in support of its order denying defendants’ motion for summary judgment.

On January 19, 1976, plaintiff filed a motion to amend his amended complaint. The motion specifically sought amendment of subsections (a), (b), (c), (f), (g) and (h) of paragraph 6 of the amended complaint. The district court heard the motion to *244 amend the amended complaint on the morning of trial, January 26, 1976. Defendants objected to any amendment of the amended complaint on the grounds the original complaint and the first amended complaint sought recovery on a tort theory and not on a contract theory, which was the effect of the proposed amendments. Defendants contended the purpose of the amendments was to overcome the obstacle of the statute of limitations, the basis for defendants’ motion for summary judgment. Plaintiff resisted defendants’ objections on the grounds the doctrine of implied provision of written contracts and the doctrine of third-party beneficiary contracts supported the motion to amend.

On January 26, 1976, this cause went to trial on the legal theories set forth in the amended complaint, as further amended by the motion to amend. At the conclusion of trial, both parties submitted proposed findings of fact and conclusions of law. On May 6, 1976, the district court entered judgment in favor of plaintiff, decreeing that plaintiff recover $9,160.01, with interest accruing on item (g) ($667.00) from October 1, 1973, while interest on all other items ($8,493.01), was to accrue “from at least October, 1972, (some of the Items having been in May and June of the same year)”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Saddlebrook v. Krohne Fund
2024 MT 68 (Montana Supreme Court, 2024)
Estate of Schwabe v. Custer's Inn Associates, LLP
2000 MT 325 (Montana Supreme Court, 2000)
Stundal v. Stundal
2000 MT 21 (Montana Supreme Court, 2000)
Peuse v. Malkuch
911 P.2d 1153 (Montana Supreme Court, 1996)
In re Declaring S.P.
786 P.2d 642 (Montana Supreme Court, 1990)
Matter of SP
786 P.2d 642 (Montana Supreme Court, 1990)
Sadler v. Hart
715 P.2d 50 (Montana Supreme Court, 1986)
Bowman v. Prater
692 P.2d 9 (Montana Supreme Court, 1984)
Lazetich v. Miller
671 P.2d 15 (Montana Supreme Court, 1983)
Masse v. STATE, DEPT. OF HIGHWAYS
664 P.2d 890 (Montana Supreme Court, 1983)
Masse v. Dept. of Highways
Montana Supreme Court, 1983
Sunbird Aviation, Inc. v. Anderson
651 P.2d 622 (Montana Supreme Court, 1982)
Craddock v. Berryman
645 P.2d 399 (Montana Supreme Court, 1982)
Blasdel v. Montana Power Co.
640 P.2d 889 (Montana Supreme Court, 1982)
Adkins v. Redeye
639 P.2d 485 (Montana Supreme Court, 1981)
White v. White
636 P.2d 844 (Montana Supreme Court, 1981)
Johnson v. Tindall
635 P.2d 266 (Montana Supreme Court, 1981)
Harris v. Harris
616 P.2d 1099 (Montana Supreme Court, 1980)
Wolfe v. Schulz Refrigeration
614 P.2d 1015 (Montana Supreme Court, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
567 P.2d 433, 173 Mont. 239, 1977 Mont. LEXIS 664, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kearns-v-mcintyre-construction-co-mont-1977.