Kaw Boiler Works Co. v. Refineries

236 P. 654, 118 Kan. 693, 1925 Kan. LEXIS 267
CourtSupreme Court of Kansas
DecidedJune 6, 1925
DocketNo. 25,885
StatusPublished
Cited by8 cases

This text of 236 P. 654 (Kaw Boiler Works Co. v. Refineries) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kaw Boiler Works Co. v. Refineries, 236 P. 654, 118 Kan. 693, 1925 Kan. LEXIS 267 (kan 1925).

Opinion

The opinion of the court was delivered by

Hopkins, J.:

The action was one to recover a balance of the purchase price of certain oil-refinery equipment. The plaintiff prevailed, and defendant appeals.

The plaintiff is a Kansas corporation having its principal place of business in Kansas City, Kan. The defendant is a Delaware corporation engaged in the oil business, with its principal office in Kansas City, Mo. Certain contracts were entered into between the parties, whereby the plaintiff furnished to defendant the equipment for the erection of an oil-cracking refinery at its plant in Kansas City, Mo. The defendant declined to pay for the equipment, chiefly because plaintiff was not authorized under the statute to do business in Missouri. Trial was to a jury. Verdict for plaintiff for $29,915.71, and special findings as follows:

[694]*694“Q. 1. Were written proposals submitted by the plaintiff Kaw Boiler Works to defendant Interstate Refineries in Kansas City, Missouri, for furnishing to defendant the preheaters, pressure stills, dephlegmating towers and storage tanks involved in this lawsuit. A. Yes.
“Q.3. Did the contract between plaintiff and defendant require the plaintiff to construct or erect the three tanks at defendant’s refinery in Kansas City, Missouri? A. Yes.
“Q. 4. Were the proposals for furnishing the pressure stills received through the mail by the defendant at its office in Kansas City, Missouri? A. Yes.
“Q. 5. If you answer question No. 4 Tes,’ then state whether the defendant sent by mail from its office in Kansas City, Missouri, to plaintiff’s office in Kansas City, Kansas, its order based on the proposals mentioned in question No. 4. A. No.'
“Q. 7. What work, if ansq was plaintiff required to do on the pressure stills after their delivery at defendant’s plant in Kansas City, Missouri, before said stills were complete? A. Attach coke pots.
“Q. 8. How much time was consumed (a) in doing the work mentioned in question No. 7? (b) How many men were used? A. (a) Four or five days.
(b) Four men.
“Q.'9. Did the contract require plaintiff t<j do anything on the 10,000,’ the 5,000 and the 2,500 barrels storage tanks after delivery at defendant’s plant in Kansas City, Missouri, before thejr were ready for use? A. Yes.
“Q. 10. If you answer question No. 9 ‘yes,’ state: (a) What work the contract required plaintiff to do on said tanks? (b) How long it took to perform said work? And (c) How many men were required in said work. A. (a) Set them up and test them. (b) About three or four weeks, (c) About fifteen men.
“Q. 11. Were the preheaters, pressure stills, dephlegmators and storage tanks all integral and indispensable parts of the oil refinery being built by defendant at its plant in Kansas City, Missouri? A. Yes.
“Q. 12. If your answer to the preceding question is ‘yes,’ did the plaintiff and defendant mutually intend that plaintiff should furnish all said parts or equipment at the time the order for the preheaters was accepted? A. No.
"Q. 13. How many days was defendant delayed in completing its refinery on account of plaintiff’s failure to furnish the preheaters, pressure stills, dephlegmators and tanks within the time specified in the contracts? A. None.
"Q. 14. What date did the contract require delivery of: (a) Preheaters? (b) Pressure stills? (c) Dephlegmators? (d) Tanks? A. (a) As'soon as possible after delivery of material to Kaw Boiler Works Company.
“Q. 15. When was delivery made at the Interstate Refinery of: (a) Preheaters? (b) Pressure stills?' (c) Dephlegmators? (d) Tanks? A. (a) One May 8th, one May 18th, 1923. (b) April 20, May 2d, 1923. (c) April 11, 1923. (d) About April 30, May 10, May 15, 1923.
“Q. 16. Were the preheaters, the pressure stills, the dephlegmating towers and the tanks all necessary elements in the refining plant being constructed by the defendant at its plant in Kansas City, Missouri? A. Yes.
“Q. 17. Were the instruments sometimes called requisitions, sometimes called acceptances, and sometimes called orders, accepted in writing by plaintiff and mailed to defendant in the course of United-States mail? A. No.”

[695]*695The defendant contends it is not liable for the equipment because the plaintiff was not licensed to do business in Missouri; that the contracts were made in Missouri; that the work performed by plaintiff was, at least in part, performed in Missouri; that Missouri has a statute providing that if a foreign corporation shall, without license, do local business in Missouri it cannot maintain an action on account' thereof.

Plaintiff contends that the contracts were made in Kansas; that the equipment was manufactured or fabricated in Kansas, was accepted by defendant in Kansas; that, as to some of the equipment, while it was fabricated in Kansas, it was too bulky to be shipped set up, and the erection thereof alone was done in Missouri; that, as to this, the erection in Missouri was but an incident of a valid interstate transaction, and hence not within the Missouri statute. The Missouri statutes require, as a condition precedent to doing business in that state, that a foreign corporation shall obtain a license to do business. It is conceded that plaintiff had no such license.

The defendant contends that the plaintiff maintained an office and transacted its business in Missouri. The evidence showed that F. G. Palmer and E. L. Hudson, president and vice president and manager of the plaintiff, are interested in another business known as Weimer Mortgage and Real Estate Company, which has no connection with the plaintiff company. The mortgage company has an office in the Waldheim building in Kansas City, Mo. The plaintiff’s name appears on the office door, and in the office is a telephone listed in plaintiff’s name. The plaintiff company pays a part of the rent of the office and the salary of a stenographer who works at the Kansas plant and occasionally in this Missouri office. Persons coming to Kansas City to transact business with the plaintiff company usually come to the Union Station in Kansas City, Mo., and communicate with this office. But so far as plaintiff’s business is concerned, this Missouri office is used largely as a meeting place. Its directors’ meetings are not held there, no books are kept there, no collections are made or received there, no contracts are made there, no goods sold there, no samples kept there. Plaintiff’s books are kept and the business of the company is transacted in the Kansas office. It clearly appears that the contracts involved in this controversy were made in Kansas. But if they were to be performed in Missouri they were void. (United Shoe Machinery Co. v. Ram-[696]*696lose, 210 Mo. 631; Booth v. Scott, 276 Mo. 1; United Shoe Machinery Co. v. Ramlose, 231 Mo. 508, 545; State, ex rel., v. Robinson, 271 Mo. 475.) If they were to be and actually were performed in Kansas, then they were not void.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Combustion Engineering, Inc. v. Arizona State Tax Commission
371 P.2d 879 (Arizona Supreme Court, 1962)
Riley Stoker Corporation v. State Tax Commission
280 P.2d 967 (Utah Supreme Court, 1955)
Indiana Department of State Revenue v. Surface Combustion Corp.
111 N.E.2d 50 (Indiana Supreme Court, 1953)
Advance-Rumely Thresher Co., Inc. v. Stohl
283 P. 731 (Utah Supreme Court, 1929)
Vilter Manufacturing Co. v. Evans
154 N.E. 677 (Indiana Court of Appeals, 1927)
J. C. Boss Engineering Co. v. Gunderson Brick & Tile Co.
209 N.W. 876 (Supreme Court of Minnesota, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
236 P. 654, 118 Kan. 693, 1925 Kan. LEXIS 267, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kaw-boiler-works-co-v-refineries-kan-1925.