Kansas Quality Construction, Inc. v. Chiasson

250 N.E.2d 785, 112 Ill. App. 2d 277, 1969 Ill. App. LEXIS 1335
CourtAppellate Court of Illinois
DecidedSeptember 3, 1969
DocketGen. 11,040
StatusPublished
Cited by24 cases

This text of 250 N.E.2d 785 (Kansas Quality Construction, Inc. v. Chiasson) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas Quality Construction, Inc. v. Chiasson, 250 N.E.2d 785, 112 Ill. App. 2d 277, 1969 Ill. App. LEXIS 1335 (Ill. Ct. App. 1969).

Opinion

SMITH, J.

Plaintiff, a Kansas corporation, is engaged in the business of building apartments. It purports to have the know-how to get things done. This necessarily includes preliminary assistance and advice just to get things off the ground — literally. Defendants conceived the idea of an apartment and had just the spot. Presumably lacking this know-how, they and plaintiff got together and the following emerged:

it
“1.
“2. Owner (defendants) agrees to retain the services of builder (plaintiff) for the above project, said services to be as follows:
“a. Development of plat layout, to show building placement, total buildings, recreation area, parking, etc.
“b. On approval of area plat by both owner and city, builder will cause plans of proposed buildings to be drawn, for loan submission.
“c. Assist owner in obtaining adequate financing for completion of project, through first and secondary financing.
“d. Erect apartment buildings on owner’s ground in accordance with approved plans and specifications.
“3. Owner agrees to contract with builder to erect all buildings built at the above location, on a turn key basis, as services outlined in paragraphs 2a, b, c and d are performed.
“4. . . .
“5. Cost of the project shall be quoted as a ‘not to exceed figure,’ but in an amount not more than the proceeds from available financing, first and secondary financing. . . .
“. . . In the event owner contracts with a builder other than this company for buildings at the above location it is expressly understood by and between the parties to this agreement that builder shall be due a fee in the amount of $4,000.00, due and payable at that time.”

To us this agreement means that when plaintiff has performed 2a, b and c, defendants can then opt to: (1) have plaintiff “erect all buildings built,” or (2) contract “with a builder other than [plaintiff]” and pay plaintiff a “fee” of $4,000, or (3) build it themselves, or (4) not build at all. Plaintiff did perform 2a, b and c. Defendants opted for (2), another builder, plaintiff says, but failed to pay it the “fee.” It sued and a verdict for $4,000 followed. Plaintiff moved for inclusion of interest in the judgment from the “time” that defendants so opted to judgment, pursuant to § 2 of the Interest Act (Ill Rev Stats 1965, c 74, § 2). The motion was denied. Both appeal.

Defendants’ defenses are many, most in the way of avoidance rather than straight denial. They do deny they opted for (2) and assert it was (3), hence they owe nothing. Did they or didn’t they build it themselves? If they didn’t, then plaintiff is right, for the apartment was built. Our review of the evidence on this point discloses a factual question which was resolved by the verdict, indeed answered specifically. This answer by the jury is not against the manifest weight of the evidence, therefore, defendants’ citation of Pedrick v. Peoria & Eastern R. Co., 37 Ill2d 494, 229 NE2d 504, is not apropos.

In avoidance, defendants argue that plaintiff violated the Illinois Architectural Act (Ill Rev Stats 1965, c 10½) by agreeing to and indeed performing architectural services without being licensed. Plaintiff agrees that it is not a corporation which can offer and engage in such services but denies that it either agreed to or did so. The practice of architecture as defined in the Act, § 2, includes the offering or furnishing of professional services in connection with the construction or erection of any building, structure or project. Is this agreement an offer by plaintiff to perform architectural services? Even if it is not, did they do so in fact? If the answer is yes to either question, plaintiff’s right to recover becomes murky, to say the least.

We are of the opinion that offering to develop a plat layout (2a) to show placement, total buildings, etc., is not so connected with “construction” that it partakes of doing what architects do. If this is so, then performance likewise is outside of the Act. To be sure, there is a nexus between the layout and construction in the sense that placement must precede construction— but then so must the idea itself. “Construction” at the very least, means getting off the ground by going either up or down, not just thinking about it, and plaintiff’s plat layout here, “to show building placement, total buildings, recreation area, parking, etc.” is certainly not construction nor connected with it to the extent that it falls within the statutory definition. The layout was developed first to please defendants and upon their approval, to convince the municipal authorities of the project’s desirability and to gain their approval. To be sure, a plat layout can at times be a very complicated business calling for the collaboration of a battery of experts — surveyors, engineers, planners, landscapers, even lawyers— but in bringing their varied expertise to bear, none are thereby transmogrified into architects — and vice versa. As is said in 5 Am Jur2d 665, § 3, Architects, “[T]he making of a survey of existing conditions, with recommendations and preliminary sketches and layouts, with regard to work needed on a hotel building, constituted nonarchitectural services.”

Likewise with regard to 2b, causing plans of the proposed building to be drawn for loan submission, is not a statement by plaintiff that it will perform architectural services, rather, it is an agreement that they will cause such plans to be drawn for such purpose — loan submission — which may or may not be eventually connected with the projected construction and which may or may not be drawn by an architect — it all depends on how much detail the banker wants. We cannot assume that the implementation of this condition without more renders this contract void from its very beginning. It is neither an “offering” nor a “furnishing” so long as performed for the stated purpose.

The proof is that at plaintiff’s behest a non-Illinois architect prepared these plans for such purposes. In causing such to be prepared and limiting their use to the stated end — loan submission — plaintiff was not playing architect. Of course, since plaintiff did not build the apartment it can hardly be accused of using these plans in “connection” with its “construction,” assuming their suitability. Whether the plans as drawn by the outside architect would have been the ones used had plaintiff been the builder is therefore irrelevant. Likewise, 2c— obtaining financing — has even less to do with architecture — if anything at all. We can only conclude that the contract itself is not void as an agreement by plaintiff itself to play architect, and what it did do, so far as it went, was not the furnishing of architectural services. Recovery cannot be avoided on this score.

Next, defendants say that their contract and plaintiff’s performance of it took place when plaintiff, a foreign corporation, lacked authority to transact business in Illinois, hence plaintiff lacked standing to sue.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McCoy v. MARCorp Financial, LLC
2025 IL App (3d) 240357-U (Appellate Court of Illinois, 2025)
Vision Energy, LLC v. Smith
2025 IL App (3d) 240114 (Appellate Court of Illinois, 2025)
Kehoe v. Wildman, Harrold, Allen & Dixon
Appellate Court of Illinois, 2008
Kehoe v. WILDMAN, HARROLD, ALLEN AND DIXON
899 N.E.2d 1177 (Appellate Court of Illinois, 2008)
Alden Press, Inc. v. Block & Co.
527 N.E.2d 489 (Appellate Court of Illinois, 1988)
Advance Mortgage Corp. v. Concordia Mutual Life Ass'n
481 N.E.2d 1025 (Appellate Court of Illinois, 1985)
Rebaque v. Forsythe Racing, Inc.
480 N.E.2d 1338 (Appellate Court of Illinois, 1985)
Spagat v. Schak
473 N.E.2d 988 (Appellate Court of Illinois, 1985)
Cronel Watch, S.A. v. Peterson State Bank
565 F. Supp. 259 (N.D. Illinois, 1983)
Libco Corp. v. Roland
426 N.E.2d 309 (Appellate Court of Illinois, 1981)
Servbest Foods, Inc. v. Emessee Industries, Inc.
403 N.E.2d 1 (Appellate Court of Illinois, 1980)
Haas v. Cravatta
389 N.E.2d 226 (Appellate Court of Illinois, 1979)
MADISON PARK BK. v. Field
381 N.E.2d 1030 (Appellate Court of Illinois, 1978)
Bise's Supermarket, Inc. v. Valley Forge Insurance
363 N.E.2d 186 (Appellate Court of Illinois, 1977)
First National Bank & Trust Co. v. City of Rockford
361 N.E.2d 832 (Appellate Court of Illinois, 1977)
Russell v. Klein
361 N.E.2d 65 (Appellate Court of Illinois, 1977)
Central National Chicago Corp. v. Lumbermens Mutual Casualty Co.
359 N.E.2d 797 (Appellate Court of Illinois, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
250 N.E.2d 785, 112 Ill. App. 2d 277, 1969 Ill. App. LEXIS 1335, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-quality-construction-inc-v-chiasson-illappct-1969.