Kansas Pipeline Partnership v. Kansas Corporation Comm'n

916 P.2d 76, 22 Kan. App. 2d 410, 1996 Kan. App. LEXIS 55
Court of Appeals of Kansas·Decided May 17, 1996·No. 75,918·Published·Cited by 11 cases

Opinion

Elliott, J.:

Kansas Pipeline Partnership (KPP) and Western Resources, Inc., (WRI) entered into natural gas . sales and transportation contracts. KPP submitted the contracts to the Kansas *412 Corporation Commission (KCC) for approval pursuant to K.S.A. 1995 Supp. 66-117(a). WRI also requested KCC approval of the contracts and requested permission to pass contract costs through to its customers. Complicating matters, the KCC shifted a $5.9 million Linchpin Development cost item from another rate hearing into this KPP application. The other rate hearing is currently pending in this court as appeal No. 75,730.

On judicial review, KPP asserts that because the KCC failed to make a decision on these contracts and the development cost item within time limits established by KCC regulations and K.S.A. 1995 Supp. 66-117(b), the contracts and other requested relief became “deemed approved” by operation of law. This is the ultimate question for us to decide on the merits of this appeal.

We agree with KPP and reverse.

A brief description of the major participants is as follows:

KPP is a natural gas public utility and the applicant before the KCC.

The KCC is the state regulatory agency with the power and authority to supervise and control intrastate natural gas public utilities doing business in Kansas. See K.S.A. 66-101 et seq.

WRI is a class A natural gas public utility, authorized to deliver natural gas to customers in Kansas, and was the other signatory to the KPP contracts for which approval was sought. WRI also sought approval of the contracts, but has not appealed the matter to this court.

Williams Natural Gas Company (WNG) is also a natural gas public utility and is a marketplace competitor of KPP.

The Citizens’ Utility Ratepayer Board (CURB) is a state agency created to look out for the interests of individuals and small businesses in regulating public utilities.

The Federal Energy Regulatory Commission (FERC) is a federal agency regulating interstate pipelines which are within its exclusive jurisdiction.

The five contracts may be summarized thus: The contracts between KPP and WRI call for the sale and transportation of increased volumes of natural gas for deliveiy in Johnson, Wyandotte, Franklin, and Miami Counties in Kansas. Two of the three gas *413 purchase contracts require KPP to deliver natural gas to the city gates at Ottawa, Paola, and Osawatomie for a term of 20 years. The third gas purchase contract calls for KPP to transport and sell natural gas to delivery points in Johnson and Wyandotte Counties for a term of 10 years.

The two transportation contracts call for the construction of a 24-mile pipeline spur to connect the Panhandle Eastern Pipeline Company’s facilities to those of WRI (the “Metcalf Contract”), and for KPP to provide natural gas to WRI for Johnson and Wyandotte Counties commencing in the year 2009 (the “2009 Contract”).

Jurisdiction

Without detailing the various dates on which various pleadings were filed, we have determined the jurisdictional filings by KPP are timely.

We have exclusive jurisdiction to review any action of the KCC arising from a rate hearing. K.S.A. 1995 Supp. 66-118a(b). In KPP’s original filing, it did not request a rate increase, but WRI did. The WRI docket was consolidated with the KPP filing. Additionally, the joinder of the Linchpin Project Development costs into this proceeding made it an action intimately related to a prior rate case. See MAPCO Intrastate Pipeline Co. v. Kansas Corporation Comm'n, 10 Kan. App. 2d 527, 530-31, 704 P.2d 989 (1985); In re Application of Southwestern Bell Tel. Co., 9 Kan. App. 2d 525, 529, 685 P.2d 304, rev. denied 236 Kan. 875 (1984).

The parties seem to agree that this case is closely enough connected to an underlying rate case to give us jurisdiction.

While we have determined we have jurisdiction under K.S.A. 1995 Supp. 66-118a(b), a question still remains whether the KCC order of November 22, 1995, is reviewable.

By applying the relevant considerations of Southwestern Bell, the KCC order is a final agency action entitling KPP to judicial review. The KCC’s denial of KPP’s arguments that the contracts were “deemed approved” due to the expiration of time is a final decision on this issue. It has a direct effect on KPP and presents a legal question for our review. Further, ruling on this issue does not disrupt the orderly process of adjudication in the administrative *414 proceeding. The November 22, 1995, KCC order is final agency action subject to review.

In Southwestern Bell, we did not clearly state whether we were considering a final agency decision or a nonfinal agency decision ripe for interlocutory review. Either way, we have jurisdiction to consider KPFs appeal. See K.S.A. 77-607(b), K.S.A. 77-608.

Merits

In orders mailed April 21 and 24, 1995, the KCC suspended the effective dates of the contracts for 180 days of their filing on March 31,1995; the WRI rate request and the KPP contract dockets were consolidated. After numerous continuances, hearings were finally conducted between August 21, 1995, and September 6, 1995. At the close of the hearings, the KCC closed the record, ordered briefs filed by October 6, 1995, and took the dockets under advisement.

After briefs were filed but before the KCC issued a decision, FERC issued a draft order stating it had jurisdiction over KPP as an interstate pipeline. When FERC asserts jurisdiction, any state regulatory agency loses jurisdiction. As a result, the KCC staff on November 1, 1995, requested a stay pending a final order from FERC. KPP opposed the stay. The KCC issued a stay on November 3, 1995, and on November 22, 1995, issued an order superseding the earlier order, in which it found:

(1) Expiration of the initial 180-day time period set by the KCC did not cause the contracts to be deemed approved because that order was subject to further KCC orders and KPP did not object to the closing of the record as of October 6,1995 (beyond the 180-day period);

Free access — add to your briefcase to read the full text and ask questions with AI

Kansas Pipeline Partnership v. Kansas Corporation Comm'n, 916 P.2d 76, 22 Kan. App. 2d 410, 1996 Kan. App. LEXIS 55 (kanctapp 1996).

916 P.2d 76 (Kansas Pipeline Partnership v. Kansas Corporation Comm'n) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

In re Equalization Appeal of Kansas Star Casino
Court of Appeals of Kansas, 2017
Cimarex Energy Co. v. Seward County Board of County Commissioners
164 P.3d 833 (Court of Appeals of Kansas, 2007)
Attorney General Opinion No.
Kansas Attorney General Reports, 2007
Kansas Energy Group v. State Corp. Commission
40 P.3d 310 (Court of Appeals of Kansas, 2002)
Citizens' Utility Ratepayer Board v. State Corp. Commission
16 P.3d 319 (Court of Appeals of Kansas, 2000)
Williams Gas Pipelines Central, Inc. v. Kansas Corporation Comm'n
7 P.3d 311 (Court of Appeals of Kansas, 2000)
CITIZENS'UTILITY RATEPAYER BD. v. Kansas Corporation Comm'n
941 P.2d 424 (Court of Appeals of Kansas, 1997)
Kansas Pipeline Partnership v. Kansas Corporation Comm'n
941 P.2d 390 (Court of Appeals of Kansas, 1997)
Western Resources, Inc. v. State Corp. Commission
937 P.2d 964 (Court of Appeals of Kansas, 1997)