Kansas City Slate & Tile Roofing Co. v. Poe

114 A. 710, 138 Md. 513, 1921 Md. LEXIS 119
CourtCourt of Appeals of Maryland
DecidedMay 6, 1921
StatusPublished
Cited by3 cases

This text of 114 A. 710 (Kansas City Slate & Tile Roofing Co. v. Poe) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas City Slate & Tile Roofing Co. v. Poe, 114 A. 710, 138 Md. 513, 1921 Md. LEXIS 119 (Md. 1921).

Opinion

Urner, J.,

delivered the opinion of the court.

The United Surety Company, of which the appellees are receivers!, executed, on June 1, 1901, as surety for D: E. Marshall and Company, contractors, a bond for $50,000 to the Board of Regents of the Fifth District Normal School, Mary-ville, Missouri, conditioned for the due performance by the principal obligprs of a contract to erect a Normal S'chool building for the sum of $152,583, and to' pay for all labor and materials required for its construction. The contract included the following provision:

“It is further mutually agreed and understood by the parties hereto that this contract is made subject to the conditions set forth in the attached copy of an agreement with the Governor of Missouri and that, should the fund reserved in said agreement or any part thereof not become available, the operations on the building to be stopped without claim for damage at any time the funds in the State treasury for this work are exhausted. If the work should be stopped as above mentioned, the architects shall determine the value of the labor done and materials furnished up to that time, and payments made accordingly. The architects’ decision to be final and binding on all the parties.”

The agreement with the Governor of Missouri referred to was as follows-:

“We, the undersigned, representing the Board of Regents of the Maryville Normal School, hereby agree that we will not pay out, or contract to pay, the appropriations indicated below, until such time as in the judgment of the Governor there is sufficient revenue in the State treasury to the credit of the general revenue fund to warrant the expenditure of such amounts, *515 and until such time as the Governor gives his consent thereto.
“For building, heating and furnishing academic hall and power plant (deduct) $100,000.00.”

After the building for which, the contract provided had been partially completed, the work was stopped in June, 1908, under the provision quoted, because of tbe exhaustion of the funds available for the purpose. The amount- then due the contractors for work and material was determined in pursuance of the terms- of the contract, relating to that contingency. After the lapse of fourteen months, during which no further work was done on the building, an agreement was executed by the parties to the building contract by which it was declared to be “revived.” The new agreement, extended the time for the completion of the building, but, provided that, in other respects the contract should he performed in accordance with its original terms. The construction work was- resumed in the fall of 1909 and wasi finished about a, year later.

The Kansas City Slate and Tile Roofing Company, a,s a subcontractor, supplied labor and material for the slate roofing, tile trimming* and sheet metal work on the school building to the' amount of $9,374.08, and of this the sum of $3,020.58 represents work and material furnished before the operations were discontinued in 1908. There were payments, aggregating $4,123.27, on account of the sub-contract, and when these are deducted from the claim as a, whole, there is left a balance of $5,250.81 for which the contractor’s- bond is sought to he held liable. There can be no¡ doubt as to the liability of the bond for so much of the claim as may he based on work done and material delivered under the contract prior to the time when its performance ceased, voider its terms, because of the exhaustion of the fund to which it referred. The question to be decided is whether the bond is responsible for the portion of the claim which must be attributed to the period after the building contract was revived and the work resumed.

*516 The obligation of the bond depends upon the nature, extent and duration of the contractual duty for the breach of which it is intended to’ afford indemnity. The contract by which the liability of the bond is to be measured contains a provision for its own termination under specified conditions. It stipulates that if the funds intended for the school building should at any time become exhausted, the work contracted for should be “stopped without claim for damages,” and the value of all work and material theretofore furnished should be determined by the architects and payments made in accordance with their estimates. There was no provision for the resumption of the work after it had been stopped for the reason contemplated. This was a very significant omission. If it had been intended that, notwithstanding the absolute discontinuance of the work for lack of funds, and the final determination of the amount due for the construction then accomplished, the contractors should be bound, for1 an indefinite period and without regard to changing conditions, to resume operations whenever notified that the requisite1 funds had been appropriated by the Legislature, there would certainly have been some expression in the contract to indicate that very important and unusual purpose. The fáct that the contract was altogether silent as to the resumption of the work is consistent only with the recognition by the parties of the obvious difficulties in the way of attempting1 to project the existing contract into a future period of uncertain remoteness in which very different conditions might prevail. It was evidently for this reason that the agreement as to the terms upon which the building operations should be conducted after additional funds had been appropriated was left for subsequent negotiations. The conduct of the parties clearly shows their underL standing that the original contract became extinct when the work was discontinued under its own provisions, for they proceeded to revive it by a new agreement after the money required for the completion of the building was at length made available. Meanwhile there had been a total cessation of the work for a period of fourteen months, and the operating equip1 *517 incut of the contractors liad, been removed. Under the circumstances, an express revival of the old contract or the execution of a new one was manifestly necessary to bring the parties again into an effective contractual relationship. Their agreement renewing the contract under which the building bad been partially • constructed was practically equivalent to its re-execution with an, added provision for the extension of the time of completion. Before the contractual relations of the parties were thus re-established, there appear to have been no duties or liabilities of the contractors, with respect to the undertaking, which had not been fully discharged, except in so far as they may not have paid for labor and material provided prior to the time when the construction work was interrupted. With this exception there was no subsisting obligation on account of the work as to which the contractors could have been said to be in default and with which their bond could be chargeable. It required a new agreement to impose upon the contractors the duty to resume the building operations, and only by a similar expression of assent could the surety on their bond have been subjected to a corresponding liability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Valley National Bank v. Shumway
163 P.2d 676 (Arizona Supreme Court, 1945)
Theiler v. Consolidated Indemnity & Insurance Co.
250 N.W. 433 (Wisconsin Supreme Court, 1933)
Ford Bros. v. Frederick M. Ward Co.
140 A. 754 (Supreme Court of Connecticut, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
114 A. 710, 138 Md. 513, 1921 Md. LEXIS 119, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-city-slate-tile-roofing-co-v-poe-md-1921.