Kansas City Power & Light Co. v. State Corp. Commission

670 P.2d 1369, 9 Kan. App. 2d 49, 1983 Kan. App. LEXIS 196
CourtCourt of Appeals of Kansas
DecidedOctober 27, 1983
Docket55,987
StatusPublished
Cited by5 cases

This text of 670 P.2d 1369 (Kansas City Power & Light Co. v. State Corp. Commission) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kansas City Power & Light Co. v. State Corp. Commission, 670 P.2d 1369, 9 Kan. App. 2d 49, 1983 Kan. App. LEXIS 196 (kanctapp 1983).

Opinion

Parks, J.:

The Kansas City Power and Light Company (KCPL) appeals from the order of the Kansas Corporation Commission (KCC) denying its application for an electric transmission line siting permit. K.S.A. 66-1,177 et seq.

On March 24, 1983, KCPL filed with the KCC its application for a siting permit to construct a 345 kilovolt electric transmission line from the Wolf Creek electric generating station in Coffey County, Kansas, to KCPL’s West Gardner Substation in Johnson County, Kansas. This application was denied by the KCC on June 16. Following the denial of its application for rehearing, KCPL timely filed its application for judicial review in this court. K.S.A. 66-1,181.

Our scope of review is limited to whether the orders or decisions of the KCC are lawful and reasonable. K.S.A. 66-118d. An order is lawful if it is within the statutory authority of the commission and if the prescribed statutory and procedural rules are followed in making the order; it is generally considered *50 reasonable when based upon substantial competent evidence. Ash Grove Cement Co. v. Kansas Corporation Commission, 8 Kan. App. 2d 128, 130, 650 P.2d 747 (1982); Central Kansas Power Co. v. State Corporation Commission, 221 Kan. 505, Syl. ¶ 1, 561 P.2d 779 (1977). The issue in this case is whether the KCC acted within its statutory authority in denying KCPL’s request for a permit to construct an electric transmission line under the Kansas Siting Act.

The Kansas Siting Act prohibits the exercise of eminent domain or site preparation for the construction of electric transmission lines prior to a hearing before the KCC and the grant of a siting permit. Only electric transmission lines which are at least five miles in length and which are used for the bulk transfer of 230 kilovolts or more of electricity are regulated. K.S.A. 66-1,177(h). The application for a siting permit must set forth the proposed location, the names and addresses of the landowners whose land is proposed to be acquired in connection with the construction of the line and such other information as may be required by the commission. The commission shall then fix a time for a public hearing to determine the reasonableness of the location of the proposed electric transmission line. K.S.A. 66-1,178. Within thirty days after the conclusion of the hearing, the commission is required to make its decision with respect to the reasonableness of the location of the proposed electric transmission line and issue or withhold the permit applied for. K.S.A. 66-1,180. An electric utility which complies with the National Environmental Policy Act of 1969 is exempt from the provisions of this act. McGinnis v. Kansas City Power & Light Co., 231 Kan. 672, Syl. ¶ 2, 647 P.2d 1313 (1982); K.S.A. 66-1, 182. Finally, the electric utility which constructs an electric transmission line has a duty to restore the land to the condition which existed prior to such construction. K.S.A. 66-1, 183.

The findings and conclusions filed in this case reveal that the KCC reaffirmed and adopted the same criteria which it had consistently applied in judging the reasonableness of proposed transmission lines; namely, necessity, cost, utility, environmental and aesthetic impact and alternative routes. The KCC further concluded that a line that is unneeded is unreasonable per se and that the applicant in this case had not met its burden of demonstrating the proposed line is necessary. KCPL contends *51 that necessity has no part in a siting permit hearing and that the KCC acted unlawfully in considering any criteria unrelated to the environmental impact of the proposed location of the line.

It was conceded at oral argument that the KCC in making its decision relied upon the provisions of the Kansas Siting Act (K.S.A. 66-1,177 et seq.) and not K.S.A. 66-131 which authorizes the commission to issue a certificate of convenience and authority to do business in this state. Therefore, we must determine what authority the legislature conferred on the commission when it enacted the Kansas Siting Act in 1979 by construing the act itself.

The fundamental rule of statutory construction to which all others are subordinate is that the purpose and intent of the legislature governs when that intent can be ascertained from the statute. When a statute is plain and unambiguous the court must give effect to the intention of the legislature as expressed, rather than determine what the law should or should not be. Szoboszlay v. Glessner, 233 Kan. 475, 478, 664 P.2d 1327 (1983).

The provisions of the Kansas Siting Act only direct a determination of the reasonableness of the location of the proposed electric transmission line. K.S.A. 66-1,178 and K.S.A. 66-1,180. No authority is granted to determine the necessity or public convenience of the line. In addition, the provision relating to the notice to be given landowners indicates that the focus of the inquiry is to be centered on the impact of the proposed line on the specific tracts it would cross.

By contrast, a similar act pertaining to electric generation facilities known as the Plant Siting Act, K.S.A. 66-1,158 et seq., requires the KCC to consider the necessity for the proposed plant or addition on a number of specified levels. K.S.A. 66-1,162. This act was passed in 1976 but amended in 1979, the same year the siting act for transmission lines was enacted. Interestingly, an early version of the Kansas Siting Act, H.B.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bailey v. Kenney
791 F. Supp. 1511 (D. Kansas, 1992)
In Re the Adoption of Baby Girl H.
739 P.2d 1 (Court of Appeals of Kansas, 1987)
Chris Hunt Water Hauling Contractor, Inc. v. State Corp. Commission
706 P.2d 825 (Court of Appeals of Kansas, 1985)
In Re the Adoption of J. G.
702 P.2d 1385 (Court of Appeals of Kansas, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
670 P.2d 1369, 9 Kan. App. 2d 49, 1983 Kan. App. LEXIS 196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kansas-city-power-light-co-v-state-corp-commission-kanctapp-1983.