JW Fowler Company v. Ephraim Irrigation

District Court, D. Utah·Decided December 11, 2020·No. 4:20-cv-00015·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF UTAH

J.W. FOWLER COMPANY, MEMORANDUM DECISION AND ORDER DENYING Plaintiff, MOTION TO DISMISS

v. Case No. 4:20-cv-00015-DN-PK EPHRIAM IRRIGATION COMPANY, District Judge David Nuffer Defendant.

Plaintiff J.W. Fowler Company (“JWF”) asserts a claim for breach of contract against Defendant Ephraim Irrigation Company (“EIC”) arising from the installation of a corrugated metal pipe (“CMP”) in a drainage tunnel near Ephraim, Utah.1 JWF alleges EIC breached implied warranties in the parties’ contract by supplying an inadequate CMP and negligently prepared plans and specifications, which caused JWF to incur delays and increased work and expenses.2 EIC seeks dismissal of JWF’s Amended Complaint for failure to state a claim.3 Because JWF alleges sufficient facts to state a plausible claim against EIC for breach of an implied warranty, EIC’s Motion to Dismiss4 is DENIED.

1 First Amended Complaint (“Amended Complaint”) ¶¶ 4.1-4.9 at 15-16, docket no. 21, filed Aug. 13, 2020. 2 Id. 3 Motion to Dismiss First Amended Complaint (“Motion to Dismiss”), docket no. 22, filed Aug. 27, 2020. EIC previously sought dismissal of JWF’s original complaint for failure to state a claim, raising many of the same arguments raised in its current Motion to Dismiss. Motion to Dismiss, docket no. 13, filed Apr. 22, 2020. EIC’s first motion to dismiss was granted, but JWF was given leave to file an amended complaint to correct the deficiencies in its breach of contract claim. Memorandum Decision and Order Granting Motion to Dismiss, docket no. 20, filed July 23, 2020. 4 Docket no. 22, filed Aug. 27, 2020. DISCUSSION EIC seeks dismissal of JWF’s Amended Complaint under FED. R. CIV. P. 12(b)(6).5 Dismissal is appropriate under Rule 12(b)(6) when the complaint, standing alone, is legally insufficient to state a claim on which relief may be granted.6 A cause of action must be supported by sufficient, well-pleaded facts to be plausible on its face.7 And in reviewing a complaint,

factual allegations are accepted as true and reasonable inferences are drawn in a light most favorable to the plaintiff.8 However, “assertions devoid of factual allegations” that are nothing more than “conclusory” or “formulaic recitation” of the law are disregarded.9 JWF’s alleges that because EIC supplied an inadequate CMP and negligently prepared plans and specifications, JWF had to undertake extraordinary efforts and increased costs to complete its work.10 The parties agree that JWF’s breach of contract claim is a claim for breach of implied warranty under the Spearin doctrine.11 To state a plausible claim for breach of a Spearin implied warranty under Utah law, JWF must allege: (1) the parties entered a valid and enforceable contract; (2) EIC made an affirmative representation regarding the project’s plans and specifications that was inaccurate or misleading;

5 Id. at 1. 6 FED. R. CIV. P. 12(b)(6); Sutton v. Utah State Sch. for the Deaf & Blind, 173 F.3d 1226, 1236 (10th Cir. 1999). 7 Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007). 8 GFF Corp. v. Associated Wholesale Grocers, Inc., 130 F.3d 1381, 1384 (10th Cir. 1997). 9 Ashcroft v. Iqbal, 556 U.S. 662, 678, 681 (2009). 10 Amended Complaint ¶¶ 4.1-4.9 at 15-16. 11 Motion to Dismiss at 10; Opposition to Defendant Ephraim Irrigation Company’s Motion to Dismiss First Amended Complaint (“Response”) at 1, docket no. 23, filed September 24, 2020. (3) JWF reasonably relied on the inaccurate or misleading representation in entering the contract; and (4) the inaccurate or misleading representation caused JWF to incur extra work or expenses.12 JWF’s Amended Complaint contains sufficient factual allegations to meet this threshold. JWF alleges that it entered a public works contract with EIC for the installation of a CMP in a drainage tunnel near Ephraim, Utah.13 JWF alleges that EIC made the following affirmative representations regarding the CMP and the project’s plans and specifications that were inaccurate or misleading: • The CMP that EIC supplied for the project would be adequate to build the project as laid out in the plans and specifications; • The CMP’s “manufacturer says the [CMP] should be supported at least every 20 feet.”; • EIC’s engineer “spoke with two cellular concrete contractors during the design process to determine the feasibility of pumping cellular concrete up to 7,100 fee. Both contractors thought this was feasible.”; • EIC had talked to cellular concrete contractors” who “agreed that the cellular concrete can reach the end of the tunnel.”; and • The project could be completed within the time allowed under the contract.14 JFW also alleges that the following aspects of the project’s plans and specifications were negligently prepared and defective: • the requirement to use the CMP that EIC supplied; • the requirement not to displace or damage the CMP while installing backfill material;

12 Jack B. Parson Constr. Co. v. State by & through Dep’t of Transp., 725 P.2d 614, 616 (Utah 1986); Frontier Founds., Inc. v. Layton Constr. Co., 818 P.2d 1040, 1043 (Utah Ct. App. 1991). 13 Amended Complaint ¶¶ 3.29-3.33 at 8. 14 Id. ¶¶ 3.66 at 14, 4.4 at 16. • the requirement that the CMP be installed in a specific location in the tunnel on a precise grade; • the requirement that the CMP have only one grout port; • the requirement that the CMP be encased with two inches of grout; and • the requirement that weep holes be installed at 1:30 and 10:30.15 JWF alleges that EIC’s representations were inaccurate or misleading and that the plans and specifications were negligently prepared and defective because the CMP that EIC supplied was not suitable for the project.16 JWF alleges the CMP was too thin, too flexible, and lacked the rigidity necessary for the project.17 This was because the contract required JWF to install supports for the CMP at a “minimum [of] every 20 feet along [the] pipe.”18 But due to the tunnel’s configuration, the support spacing was conditioned on the length of the CMP itself, as intermediate supports could not be installed.19 JWF further alleges that the CMP frequently

arrived on site in damaged or defective condition.20 This caused delays and grout leaks during the CMP’s installation because the grout ports and connections between the CMP’s sections were not “grout-tight.”21

Free access — add to your briefcase to read the full text and ask questions with AI

JW Fowler Company v. Ephraim Irrigation, (D. Utah 2020).

JW Fowler Company v. Ephraim Irrigation (JW Fowler Company v. Ephraim Irrigation) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Sutton v. Utah State School for the Deaf & Blind
173 F.3d 1226 (Tenth Circuit, 1999)
Frontier Foundations, Inc. v. Layton Construction Co.
818 P.2d 1040 (Court of Appeals of Utah, 1991)