Jurgens Real Estate Co. v. R.E.D. Construction Corp.

659 N.E.2d 353, 103 Ohio App. 3d 292, 1995 Ohio App. LEXIS 1897
CourtOhio Court of Appeals
DecidedMay 8, 1995
DocketNo. CA93-11-083.
StatusPublished
Cited by8 cases

This text of 659 N.E.2d 353 (Jurgens Real Estate Co. v. R.E.D. Construction Corp.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jurgens Real Estate Co. v. R.E.D. Construction Corp., 659 N.E.2d 353, 103 Ohio App. 3d 292, 1995 Ohio App. LEXIS 1897 (Ohio Ct. App. 1995).

Opinions

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 294 This appeal is from judgments entered by the Clermont County Court of Common Pleas upon the verdicts of a jury in actions claiming damages for the alleged faulty construction of a three-building complex known as Eastgate Commercial Park.

Prior to the construction of the three-building complex, the planned development was divided into three phases for construction purposes, and separate bids were taken for each phase of the project. Subsequently, the bid of R.E.D. Construction Corporation was accepted for all three phases, and separate contracts dated August 4, 1989 were entered into for each phase of the project. At the time, Stanford Joseph was the architect of record who had prepared the plans and specifications for the construction of all three buildings, but he maintained that his contract only required the preparation of permit drawings.

On September 3, 1991, plaintiff, Jurgens Real Estate Company, initiated these proceedings when it filed a complaint against defendants, R.E.D. Construction Corporation and Stanford Joseph, seeking damages relative to the construction of an office warehouse building ("Phase II"), and on April 3, 1992, R.E.D. Construction Corporation commenced an action against Eastgate Development Partnership and Stanford Joseph relative to the construction of an office warehouse *Page 295 building ("Phase I") and a public storage rental building ("Phase III"). Thereafter, on June 15, 1992, the two cases were consolidated, with various claims and counterclaims being asserted among the various parties to the actions, and the cause came on to be heard by jury on September 14, 1993.

After a lengthy trial, the jury returned its verdict on October 1, 1993. As to Phase I, the jury found against Eastgate upon its claim against R.E.D. and Joseph, and for R.E.D. and against Eastgate in the amount of $19,892. As to Phase II, the jury found against Jurgens upon its claim against R.E.D. and Joseph, and for R.E.D. and against Jurgens in the amount of $121,463. As to Phase III, the jury found in favor of R.E.D. and against Eastgate in the amount of $122,650, and for Eastgate and against R.E.D. and Joseph in the amount of $30,000. Subsequently, posttrial motions filed by Jurgens and Eastgate were overruled, and both have appealed to this court pursuant to a notice of appeal filed on November 29, 1993.

In this court, appellants, Jurgens and Eastgate, have set forth six assignments of error, the first of which has been stated as follows:

"The trial court erred to the prejudice of appellants by refusing to instruct the jury on the issue of appellees' negligence and apportionment of negligence among them."

In the trial court, appellants argued that they were entitled to jury instructions on both breach of contract and comparative negligence, whereas appellees argued that their only duties in this case arose from their contractual obligations. Subsequently, the trial court confined its instruction to the law applicable to the contracts entered into by the parties to the actions.

In support of their respective positions, both appellants and appellees have submitted numerous cases, but upon analysis, none of such cases appear to have any more than peripheral application to the particular facts of this case. Here, a strict adherence to the request for a charge on comparative negligence would immediately introduce the possibility of overemphasis and/or double recovery. Moreover, such a charge, in fairness to all, would have to be framed to include the comparative negligence of appellants as well as both appellees. Furthermore, a proper charge on comparative negligence would tend to obscure the rights and duties specifically outlined in the written contracts.

During the proceedings, the trial court also observed that an instruction on contract liability for failure to perform in a workmanlike manner would convey substantially the same message as an instruction upon tort liability for failure to use due care, thus reducing the possibility of any prejudice from the refusal to charge upon both issues. *Page 296

When this case was orally argued to this court, appellants referred with some particularity to Cincinnati RiverfrontColiseum, Inc. v. McNulty Co. (1986), 28 Ohio St.3d 333, 28 OBR 400, 504 N.E.2d 415, but in that case, the resolution of the disputed factual issues was confined solely to the principles of comparative negligence. Likewise, the cases of Marshall v.Gibson (1985), 19 Ohio St.3d 10, 19 OBR 8, 482 N.E.2d 583, andMcMillan v. Brune-Harpenau-Torbeck Builders, Inc. (1983), 8 Ohio St.3d 3,8 OBR 73, 455 N.E.2d 1276, which were particularly relied upon by appellants, were based solely upon negligence.

In the present case, however, the central theme projected by the evidence revolves almost entirely around breach of contract. In fact, the only duty owed by appellees to appellants is solely traceable to the contracts introduced as exhibits at the trial. While the same evidence may tend to prove a breach of some duty imposed by law as well as the breach of a specific duty imposed by contract, the critical distinction between the two theories was recognized by the Supreme Court of Ohio in Floor Craft FloorCovering, Inc. v. Parma Community Gen. Hosp. Assn. (1990),54 Ohio St.3d 1, 7, 560 N.E.2d 206, 211, as follows:

"`The law of torts is well equipped to offer redress for losses suffered by reason of a "breach of some duty imposed by law to protect the broad interests of social policy." * * * Tort law is not designed, however, to compensate parties for losses suffered as a result of a breach of duties assumed only by agreement. * * * It remains the particular province of the law of contracts. * * *

"`The controlling policy consideration underlying tort law is the safety of persons and property — the protection of persons and property from losses resulting from injury. The controlling policy consideration underlying the law of contracts is the protection of expectations bargained for. * * *'" (Citation omitted.) Quoting Sensenbrenner v. Rust, Orling Neale (1988),236 Va. 419, 425, 374 S.E.2d 55, 58.

During the discussion of this matter in the trial court, appellants candidly stated that the cost of repairs was the only measure of damages in the case, thus admitting that a negligence charge was not indispensable to a complete recovery. And the relationship of all of the parties to the action was based essentially upon contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Saha v. Ohio State Univ.
2010 Ohio 5906 (Ohio Court of Claims, 2010)
State Farm Mutual Automobile Insurance v. Kia Motors America, Inc.
828 N.E.2d 701 (Ohio Court of Appeals, 2005)
Floyd v. United Home Improvement Center, Inc.
696 N.E.2d 254 (Ohio Court of Appeals, 1997)
Titanium Industries v. S.E.A., Inc.
691 N.E.2d 1087 (Ohio Court of Appeals, 1997)
Labate v. National City Corp.
680 N.E.2d 693 (Ohio Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
659 N.E.2d 353, 103 Ohio App. 3d 292, 1995 Ohio App. LEXIS 1897, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jurgens-real-estate-co-v-red-construction-corp-ohioctapp-1995.