Opinions

Mount, J.

This action was brought against the city of Seattle to recover the amount of a special assessment warrant, on the ground that the city negligently and wrongfully permitted the fund to become depleted and had paid warrants drawn on said fund subsequent to plaintiff’s warrant, leaving plaintiff’s warrant unpaid. The trial court sustained a demurrer to , the complaint upon the ground that the complaint failed to state a cause of action, and dismissed the action. The plaintiff appeals.

[273]*273The facts as alleged are, in substance, as follows: In June, 1890, an ordinance was passed, providing for the improvement of Rainier street, and creating a local improvement district to pay therefor. Assessments were levied upon the property of the district, and a special fund was created into which the assessments were paid as collected. Warrants were issued against this fund and delivered to the contractor in payment for the improvement. These warrants upon their face recited that they were payable only out of the special fund and constituted no liability against the city. The assessment became delinquent on February 23, 1891, and on January 3, 1891, the warrant in question was presented and not paid for want of funds. Again, in 1904, the warrant was presented by the appellant and payment refused for the same reason. In 1908 this action was begun. The allegations upon which the appellant seeks to charge the city are as follows :

“That the defendant city undertook and agreed with the owners and holders of the said warrants, and it was its duty under and by virtue of the laws of the state of Washington, said ordinance No. 1394, the charter and ordinances of the defendant city, and the said contract for the making of said improvements, to proceed with all reasonable diligence, care and caution to collect the said assessments, interest, and penalty made upon the said property included within the said district for the payment of said improvement, and pay the same into the said special fund, and pay out the same upon the said warrants issued and delivered against said fund as aforesaid, for the payment of said improvement according to and in the order of the issue, number and preference right of payment of said warrants; that pursuant thereto the defendant city did collect and receive certain of the assessments aforesaid upon certain of the property within said district and assessed as aforesaid, in cash and cash value, and paid the same into the said special fund or applied the same on account thereof, and did commence suits to foreclose the lien of the remainder of said assessments upon the remainder of the said property so assessed and within said district, and [274]*274to collect the same, but failed, neglected and refused to diligently prosecute said suits and to prosecute said suits at all, and carelessly and negligently and wrongfully compromised and settled the said suits and the judgments rendered in some thereof, and all of the remainder of unpaid assessments for said improvement, for sums far less than the amount due and collectible on said assessments sued on, or compromised and settled, and carelessly and negligently and wrongfully in such compromises and settlements released and discharged the property included within said district and upon which the assessments so compromised and settled were levied and a lien, from the lien of such assessments thereon, and carelessly and negligently and wrongfully caused and suffered the balance of the principal, interest and penalty due and collectible on said assessments on said property, together with the lien thereof on said property to be wholly and totally released, discharged, destroyed and lost; that the defendant city carelessly and negligently and wrongfully paid out of said special fund, interest on warrants against the same to the amount of more than $100 in excess of the sum lawfully and rightfully due and owing on such account; that the defendant city carelessly and negligently and wrongfully in the settlements and compromises aforesaid received and accepted as cash warrants issued against said special fund subsequent in date, number and preference right of payment to the said warrant owned by plaintiff; that by reason and because of the negligent and careless and wrongful acts of the defendant city aforesaid and the release and discharge of the lien of such assessments upon the property within said district more than the sum of $6,494.29 remaining due and collectible as principal, interest and penalty on the said assessments has been wholly and totally destroyed and lost to the said special fund and to the owners and holders of said warrants, and which said sum so destroyed and lost to said special fund is more than sufficient to pay in full all of the principal and interest due and payable upon all of the outstanding and unpaid warrants issued as aforesaid against said special fund, prior in date of issuance, number and preference right of payment to the said warrant held by plaintiff, and to pay in full the balance of principal and interest due and payable on the said warrant owned by plaintiff; that the defendant city carelessly and negligently and wrongfully paid out and applied to the [275]*275payment, satisfaction and cancellation of warrants' issued against said special fund as aforesaid, and subsequent in date of issuance, number and preference right of payment, to the said warrant held by plaintiff, cash and cash value, received and accepted by the defendant city in the compromises and settlements of assessments aforesaid, and collections on said assessments, more than the sum of $2,567.46 and more than sufficient to pay in full all of the principal and interest due and payable on all of the outstanding and unpaid warrants issued as aforesaid against said special fund, prior in date of issuance, number and preference right of payment, to the warrant so held by plaintiff, and to pay in full the balance of principal and interest due and payable on the said warrant held by plaintiff.”

According to the allegations of the complaint, the depletion of the fund arose from four causes: (1) The failure of the city to collect certain assessments; (2) the compromising of other assessments so that only a part thereof was paid into the fund; (3) the payment of warrants subsequent in order of right to that owned by plaintiff, and (4) the acceptance of warrants in payment of assessments. It is by reason of these alleged wrongful and negligent acts that the appellant now seeks to hold the city liable for the amount of the warrant in question. The complaint does not allege that any claim for damages was presented to the city prior to the bringing of this action. The city charter provides as follows:

“All claims for damages against the city must be presented to the city council and filed with the clerk within thirty days after the time when such claim for damages accrued, and no ordinance shall be passed allowing any such claim or any part thereof, or appropriating money or other property to pay or satisfy the same or any part thereof, until such claim has first been referred to the proper department, nor until such department has made its report to the city council thereon, pursuant to such reference.
“All such claims for damages must accurately locate and desci’ibe the defect that caused the injury, accurately describe the injux’y, give the residence for one year last past of claimant, contain the items of damages claimed, and be sworn to by the claimant.
[276]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Puget Construction Co. v. Pierce County
392 P.2d 227 (Washington Supreme Court, 1964)
Amende v. City of Bremerton
217 P.2d 1049 (Washington Supreme Court, 1950)
State Ex Rel. Amende v. City of Bremerton
205 P.2d 1212 (Washington Supreme Court, 1949)
City of Longview v. Longview Co.
150 P.2d 395 (Washington Supreme Court, 1944)
State v. McCollum
136 P.2d 165 (Washington Supreme Court, 1943)
State Ex Rel. Rand v. City of Seattle
124 P.2d 207 (Washington Supreme Court, 1942)
Boyer v. City of Yakima
273 P. 188 (Washington Supreme Court, 1928)
Perkins v. City of South Bend
233 P. 655 (Washington Supreme Court, 1925)
Johnson v. Town of Endicott
211 P. 717 (Washington Supreme Court, 1923)
Neely v. City of Seattle
186 P. 880 (Washington Supreme Court, 1920)
Barker v. City of Seattle
166 P. 1143 (Washington Supreme Court, 1917)
Jorguson v. City of Seattle
141 P. 334 (Washington Supreme Court, 1914)
Williams v. City of Seattle
138 P. 300 (Washington Supreme Court, 1914)
Connor v. City of Seattle
135 P. 617 (Washington Supreme Court, 1913)
Casassa v. City of Seattle
134 P. 1080 (Washington Supreme Court, 1913)
Kiser v. Douglas County
41 L.R.A.N.S. 1066 (Washington Supreme Court, 1912)
International Contract Co. v. City of Seattle
125 P. 152 (Washington Supreme Court, 1912)
Shaw & Hodgins v. Waldron
104 P. 272 (Washington Supreme Court, 1909)

Cite This Page — Counsel Stack

Bluebook (online)
97 P. 107, 50 Wash. 272, 1908 Wash. LEXIS 711, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jurey-v-city-of-seattle-wash-1908.