Julius Keller Construction Co. v. Herkless

109 N.E. 797, 59 Ind. App. 472, 1915 Ind. App. LEXIS 217
CourtIndiana Court of Appeals
DecidedOctober 7, 1915
DocketNo. 8,647
StatusPublished
Cited by6 cases

This text of 109 N.E. 797 (Julius Keller Construction Co. v. Herkless) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Julius Keller Construction Co. v. Herkless, 109 N.E. 797, 59 Ind. App. 472, 1915 Ind. App. LEXIS 217 (Ind. Ct. App. 1915).

Opinion

Caldwell, J.

The substance of appellees’ complaint is as follows: In 1906, appellant city of Rushville by regular proceedings contracted with appellees, to furnish the-material and perform the work in the improvement of Arthur Street in said city from Third Street north to the corporation line. The work consisted of grading the roadway and surfacing it with broken stone, and constructing cement gutters and stone curbing along the line of the roadway on each side. The cost of the work was to be assessed against the abutting owners as provided by statute. Appellees after the work had commenced were regularly granted extensions of time, within which to complete it, the extended periods expiring September 1, 1908. On July 1, 1907, appellees were prosecuting the work,, and at that time had completed most of the curbing and guttering, and had graded and surfaced a large part of the roadway. On April 23, 1907, appellant city, by regular proceedings, contracted with appellant company for the construction of a sewer system in said city, including a sanitary sewer the entire length of Arthur Street. Commencing about July 1,1907, appellant company, as a part of the work of constructing the sewer .on Arthur Street, made an excavation the entire length of that street north of Third Street, eighteen feet .deep and four feet wide, the west edge of which was within four feet of the east edge of the curb and gutter theretofore constructed by appellees, and placed therein a row of eighteen-inch sewer pipe as required by the contract, and thereupon, using loose dirt, filled the excavation not more than half full, and thereafter did nothing further at the work until April, 1908, all of which was done before appellees had completed • their [476]*476contract. As a result of the manner in which appellant company did its work, the trench caved, causing extensive portions of the completed curb and gutter and the surfacing stone to fall into the excavation, thereby necessitating the reconstruction of parts of the work. In making the excavations appellant company at certain points destroyed the grade of the subsoil theretofore prepared by appellees for receiving the broken stone, and mixed loose dirt with the stone with which other parts of the grade had been surfaced, thereby necessitating extra work on appellees’ part. As a result of the conduct complained of, appellees were required to restore the work so destroyed, to purchase extra stone, employ additional labor, pay demurrage on cars, retain a large road roller for a time otherwise unnecessary at an expensive rental, as a result of all which and other injuries specifically alleged, appellees were damaged $3,000, for which they ask judgment. It is alleged that the acts complained of were done in a careless and negligent manner, and that appellees were not guilty of negligence contributing thereto. The charge against the city is that “all the officers and agents of said city of Rushville had full knowledge a.t the time of the occurrence of all said acts and omissions of said defendant construction company when the same occurred and then and there did negligently consent to and acquiesce in the same, and did then and there direct said defendant construction company to do said acts.”

1. The cause having been placed at issue, a trial resulted in a verdict and judgment against both appellants for $2,251.83, from which both appeal. Appellants jointly and also each separately assign error. Appellant company’s first assignment is based on the overruling of its alleged motion to require that the complaint be made more specific. At the time when such a motion was filed, and also when it was ruled on; the stockholders of appellant company .also were defendants, the cause having been subsequently dismissed as to them. Respecting said motion, we [477]*477are in harmony with appellees in their contention that while it appears from the record that snch a motion was filed and overruled, it cannot be determined from the record with any satisfactory degree of certainty that appellant company rather than some other defendant filed such motion. The assignment under consideration therefore presents no question. . •

2. Appellant city seeks to challenge the complaint by an independent assignment of error for insufficiency of facts. This action was commenced in November, 1911, and therefore after the amendment of 1911 to the practice act became effective. Such assignment therefore presents no question for our consideration. §§344, 348 Burns 1914, Acts 1911 p. 415; Combs v. Combs (1914), 56 Ind. App. 656, 105 N. E. 944; Robinson v. State (1912), 177 Ind. 263, 97 N. E. 929.

3. Each appellant challenges instructions Nos. 9, 11 and 13. Appellant company challenges also No. 10, and appellant city No. 8. Instruction No. 9 is as follows: “I instruct you that municipal corporations are within the operation of the general rule of law, that the superior or employer must answer civilly for the negligence or want of skill of an agent or servant in the course of their employment, by which another is injured. It is essential, however, to establish such a liability that the act or acts complained of must be within the scope of the corporate powers of such municipality. It was within the scope of the corporate powers of the city of Rushville to contract for the construction of a sewer, and I instruct you that if you find that the defendant, the city of Rushville, did on the-day of April, 1907, enter into a contract with the Julius Keller Construction Company for the construction of the sewer as referred to in plaintiff’s complaint, and that said defendant company, pursuant to said contract, constructed said sewer on and along said Arthur Street, as alleged in plaintiff’s complaint, and if you further find .that in eon[478]*478structing said sewer said defendant company was negligent in any one or more particulars as described in the complaint relative to any one or more of the acts as therein alleged, then not only said defendant company, but also the defendant, the city of Rushville, would be liable to compensate the plaintiffs for all damages sustained by them, if any, which are alleged in the complaint, and are shown by a preponderance of the evidence to have been sustained by them as a proximate result of the act or acts so complained of.” It is urged against instruction No. 9 that by it the court instructed the jury that appellants must be held liable for all damages resulting from the work of the construction company, if it should be found to have been guilty of negligence in but one of the particulars specified in the complaint and regardless of whether such negligence was a proximate cause of all such damage. We do not believe that the instruction is open to this objection. Fairly construed, it is to the effect that if the construction company was shown to have been negligent in but one of the particulars alleged, appellants were liable for all the damages resulting from such negligence as a proximate cause thereof, alleged in the complaint and established by a preponderance of the evidence; but if there were other acts of negligence proven as alleged resulting proximately in other injuries alleged and shown by a preponderance of the evidence, appellants were liable for these also.

4. It is urged against instruction No. 9 also that by it the court ignored the issue of contributory negligence formed by the complaint and the answers in general denial filed thereto. The court gave no instruction on the subject of contributory negligence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Winston-Salem v. Ferrell
338 S.E.2d 794 (Court of Appeals of North Carolina, 1986)
Safety Cab, Inc. v. Indiana Employment Security Board
242 N.E.2d 25 (Indiana Court of Appeals, 1968)
Henderson v. Couch
274 S.W.2d 844 (Court of Appeals of Texas, 1955)
Crane v. Pangere & Logan, Inc.
95 N.E.2d 216 (Indiana Court of Appeals, 1950)
Nash v. Meguschar
91 N.E.2d 361 (Indiana Supreme Court, 1950)
Deep Vein Coal Co. v. Rainey
112 N.E. 392 (Indiana Court of Appeals, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
109 N.E. 797, 59 Ind. App. 472, 1915 Ind. App. LEXIS 217, Counsel Stack Legal Research, https://law.counselstack.com/opinion/julius-keller-construction-co-v-herkless-indctapp-1915.