JSP Silverdale Land LLC et al v. Kitsap County

CourtDistrict Court, W.D. Washington
DecidedMay 6, 2026
Docket3:25-cv-05288
StatusUnknown

This text of JSP Silverdale Land LLC et al v. Kitsap County (JSP Silverdale Land LLC et al v. Kitsap County) is published on Counsel Stack Legal Research, covering District Court, W.D. Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JSP Silverdale Land LLC et al v. Kitsap County, (W.D. Wash. 2026).

Opinion

1 2

3 4 5 UNITED STATES DISTRICT COURT 6 WESTERN DISTRICT OF WASHINGTON AT SEATTLE 7 JSP SILVERDALE LAND LLC et al, CASE NO. 3:25-cv-05288-JNW 8 Plaintiffs/Petitioners, ORDER GRANTING 9 PETITIONER’S LUPA PETITION v. 10 KITSAP COUNTY, 11 Defendant/Respondents. 12

13 1. INTRODUCTION 14 This matter comes before the Court on Plaintiffs JSP Silverdale Land LLC, 15 CG Silverdale Land LLC, and TC Silverdale Land LLC’s (collectively, “Petitioners”) 16 claim under Washington’s Land Use Petition Act (“LUPA”), RCW 36.70C., et seq.1 17 Petitioners challenge the Kitsap County Board of County Commissioners’ (“Board”) 18 decision upholding the Kitsap County Public Works Director’s (“Director”) method 19 of calculating the newcomer’s assessment for Petitioners’ residential development in 20 Silverdale, Washington. 21

22 1 This case was consolidated with a second action, Case No. 3:25-cv-05558-GJL, which included the LUPA claim now before this Court. The Complaint reserves the 23 federal claims to be decided outside the LUPA procedures. 1 At its core, this case presents a question of statutory interpretation: whether 2 the Kitsap County Code required the County to execute a newcomer’s agreement

3 that fixed the assessment rate for Petitioners’ project, or whether the County could 4 instead charge whatever rate happened to be in effect at the time of each sewer 5 connection—a practice that nearly doubled the per-unit assessment over the life of 6 the project. 7 The Court concludes that the Code unambiguously required the County to 8 execute a newcomer’s agreement establishing the assessment amount for the entire

9 project. The Director’s failure to do so, and the resulting practice of imposing mid- 10 project rate increases—which the Board upheld on appeal—constitutes an 11 erroneous interpretation of the law. The petition is GRANTED. 12 2. BACKGROUND 13 Petitioners are property developers that sought to build a residential 14 development, the “Highlands at Silverdale,” in the unincorporated Silverdale area 15 of Kitsap County, Washington. Dkt. No. 26-1 at 6. The Highlands at Silverdale

16 contains 570 apartments in 18 buildings, in addition to community and commercial 17 buildings and facilities. Kitsap County (“County”) through the Public Works Sewer 18 Utility (“Sewer Utility”) provides sewer service to the area. Id. 19 The dispute in this matter arises from the “newcomer’s assessment” that the 20 County’s Sewer Utility charged Petitioners. Under the Kitsap County Code, a 21 newcomer’s assessment “represents the newcomer’s proportionate share for future

22 expansion of the major components of the existing sewage system.” KCC 23 13.14.060(b). The assessment is “held by the county in trust for future expansion of 1 its sewage systems.” KCC 13.14.060(c). The assessment amount is calculated based 2 on “residential equivalent units” (“REUs”), and the per-REU rate is “established

3 from time to time by the [Board of County Commissioners].” KCC 13.14.060(e). A 4 “residential equivalent unit” is a standardized measure of anticipated sewage 5 demand. Under the Code, each dwelling unit constitutes one REU. See KCC 6 13.14.140. 7 The Code provides that “whenever any [] entity desires to connect to an 8 existing county sewage system” that entity “shall be required to subscribe a 9 newcomer’s agreement and pay a newcomer’s assessment” and the “assessment 10 shall be paid prior to any connection to the county’s system.” KCC 13.14.060(a). The 11 newcomer’s agreement “shall memorialize the number of [REUs] which a person or 12 entity is entitled to connect to the county’s sewage system and the amount paid 13 therefor.” KCC 13.14.060(f). 14 No newcomer’s agreement was ever executed here. The newcomer’s 15 assessment rate changed three times during the project:

16 • Effective August 1, 2021: $6,481/REU (Board Resolution 124-2021, 17 effective August 1, 2021). Dkt. No. 28-10 at 2. 18 • Effective August 1, 2022: $7,020/REU (Board Resolution 110-2022, 19 effective August 1, 2022). Dkt. No. 28-11 at 2. 20 • Effective August 1, 2023: $9,939/REU (Board Resolution 131-2023, 21 effective August 1, 2023). Dkt. No. 28-12 at 2.

22 Petitioners submitted their Administrative Conditional Use Permit (“ACUP”) 23 application in March 2021 and submitted building permit applications between 1 April and July 2022. Dkt. No. 26-1 at 12. On August 8, 2022, the ACUP was 2 approved. Dkt. No. 26-1 at 12; Dkt. No. 33-2. Two days later, on August 10, 2022,

3 the County’s Sewer Utility issued a fee letter identifying the REUs for the project at 4 the $7,020/REU rate. Dkt. No. 31 at 6. The Site Development Activity Permit 5 (“SDAP”) was approved on August 9, 2022, and issued on August 25, 2022. Dkt. 6 Nos. 33-3; 33-4. 7 On July 25, 2023, Petitioners paid the newcomer’s assessment for Buildings 1 8 through 11, the clubhouse, and the community building—totaling 278 REUs—at the

9 $7,020/REU rate then in effect. See Dkt. No. 26-1 at 22; see also Dkt. No. 28-1. 10 On February 24, 2024, the parties entered a “Phased Development Contract” 11 under KCC 13.14.160 for the remaining 166 REUs (phases two and three). Dkt. No. 12 28-9. That contract stated that the “amount of newcomer’s assessment attributable 13 to each phase of development or discreet unit is pursuant to the Resolution in effect 14 at the time of connection.” Dkt. No. 28-9 at 3. The first physical sewer connections 15 did not occur until early 2024. Dkt. No. 30 at 5; Dkt. No. 26-1 at 18.

16 Because the connections for the remaining units occurred after August 1, 17 2023, the Sewer Utility applied the $9,939/REU rate—the rate set by Resolution 18 131-2023—to those units. Dkt. No. 26-1 at 18, 23. As a result, Petitioners paid 19 $7,020/REU for the first 278 REUs and were required to pay $9,939/REU for the 20 balance. Dkt. No. 26-1 at 22–23. 21 On March 31, 2025, Petitioners objected to the mid-project rate increase

22 through the dispute resolution process under KCC 13.14.180(c). Dkt. No. 28-4. On 23 April 10, 2025, the Director rejected Petitioners’ objections, maintaining that the 1 newcomer’s assessment are “ultimately valued and due at the time of connection— 2 meaning when a sewer permit is issued allowing a project building to be connected

3 to the utility system.” Dkt. No. 26-1 at 18. Petitioners appealed the Director’s 4 decision to the Board, which held a public meeting on June 9, 2025, and denied the 5 appeal. Dkt. No. 28-8. 6 Under RCW 36.70C.080(5), the parties waived the initial hearing and 7 stipulated to a hearing on the merits, which the Court held on December 29, 2025. 8 Dkt. No. 37. At the hearing, both parties confirmed that there are no factual

9 disputes; this case turns entirely on the interpretation of Kitsap County Code 10 Chapter 13.14. 11 The Court has reviewed the parties’ briefing, the Administrative Record and 12 its supplements, and the hearing transcript. Dkt. Nos. 25-1, 26-1, 27, 28, 30, 31, 32, 13 33, 34, 37. Because this was not a quasi-judicial proceeding, the record may be 14 supplemented under RCW 36.70C.120(3), and the Court has considered the 15 supplemental declarations and exhibits. Dkt. Nos. 28, 31, 33, 34.

16 3. LEGAL STANDARD 17 LUPA governs judicial review of land use decisions. Durland v. San Juan 18 County, 340 P.3d 191, 196 (2014).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whatcom County v. City of Bellingham
909 P.2d 1303 (Washington Supreme Court, 1996)
State v. Krall
881 P.2d 1040 (Washington Supreme Court, 1994)
Tahoma Audubon Society v. PARK JUNCTION
116 P.3d 1046 (Court of Appeals of Washington, 2005)
Sleasman v. City of Lacey
151 P.3d 990 (Washington Supreme Court, 2007)
Ellensburg Cement Products, Inc. v. Kittitas County
317 P.3d 1037 (Washington Supreme Court, 2014)
Durland v. San Juan County
340 P.3d 191 (Washington Supreme Court, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
JSP Silverdale Land LLC et al v. Kitsap County, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jsp-silverdale-land-llc-et-al-v-kitsap-county-wawd-2026.