JSP Silverdale Land LLC et al v. Kitsap County

District Court, W.D. Washington·Decided May 6, 2026·No. 3:25-cv-05288·Unknown

Opinion

UNITED STATES DISTRICT COURT AT SEATTLE JSP SILVERDALE LAND LLC et al, CASE NO. 3:25-cv-05288-JNW Plaintiffs/Petitioners, ORDER GRANTING PETITIONER’S LUPA PETITION v. KITSAP COUNTY, Defendant/Respondents.

1. INTRODUCTION This matter comes before the Court on Plaintiffs JSP Silverdale Land LLC, CG Silverdale Land LLC, and TC Silverdale Land LLC’s (collectively, “Petitioners”) claim under Washington’s Land Use Petition Act (“LUPA”), RCW 36.70C., et seq.1 Petitioners challenge the Kitsap County Board of County Commissioners’ (“Board”) decision upholding the Kitsap County Public Works Director’s (“Director”) method of calculating the newcomer’s assessment for Petitioners’ residential development in Silverdale, Washington.

1 This case was consolidated with a second action, Case No. 3:25-cv-05558-GJL, which included the LUPA claim now before this Court. The Complaint reserves the federal claims to be decided outside the LUPA procedures. At its core, this case presents a question of statutory interpretation: whether the Kitsap County Code required the County to execute a newcomer’s agreement

that fixed the assessment rate for Petitioners’ project, or whether the County could instead charge whatever rate happened to be in effect at the time of each sewer connection—a practice that nearly doubled the per-unit assessment over the life of the project. The Court concludes that the Code unambiguously required the County to execute a newcomer’s agreement establishing the assessment amount for the entire

project. The Director’s failure to do so, and the resulting practice of imposing mid- project rate increases—which the Board upheld on appeal—constitutes an erroneous interpretation of the law. The petition is GRANTED. 2. BACKGROUND Petitioners are property developers that sought to build a residential development, the “Highlands at Silverdale,” in the unincorporated Silverdale area of Kitsap County, Washington. Dkt. No. 26-1 at 6. The Highlands at Silverdale

contains 570 apartments in 18 buildings, in addition to community and commercial buildings and facilities. Kitsap County (“County”) through the Public Works Sewer Utility (“Sewer Utility”) provides sewer service to the area. Id. The dispute in this matter arises from the “newcomer’s assessment” that the County’s Sewer Utility charged Petitioners. Under the Kitsap County Code, a newcomer’s assessment “represents the newcomer’s proportionate share for future

expansion of the major components of the existing sewage system.” KCC 13.14.060(b). The assessment is “held by the county in trust for future expansion of its sewage systems.” KCC 13.14.060(c). The assessment amount is calculated based on “residential equivalent units” (“REUs”), and the per-REU rate is “established

from time to time by the [Board of County Commissioners].” KCC 13.14.060(e). A “residential equivalent unit” is a standardized measure of anticipated sewage demand. Under the Code, each dwelling unit constitutes one REU. See KCC 13.14.140. The Code provides that “whenever any [] entity desires to connect to an existing county sewage system” that entity “shall be required to subscribe a newcomer’s agreement and pay a newcomer’s assessment” and the “assessment shall be paid prior to any connection to the county’s system.” KCC 13.14.060(a). The newcomer’s agreement “shall memorialize the number of [REUs] which a person or entity is entitled to connect to the county’s sewage system and the amount paid therefor.” KCC 13.14.060(f). No newcomer’s agreement was ever executed here. The newcomer’s assessment rate changed three times during the project:

• Effective August 1, 2021: $6,481/REU (Board Resolution 124-2021, effective August 1, 2021). Dkt. No. 28-10 at 2. • Effective August 1, 2022: $7,020/REU (Board Resolution 110-2022, effective August 1, 2022). Dkt. No. 28-11 at 2. • Effective August 1, 2023: $9,939/REU (Board Resolution 131-2023, effective August 1, 2023). Dkt. No. 28-12 at 2.

Petitioners submitted their Administrative Conditional Use Permit (“ACUP”) application in March 2021 and submitted building permit applications between April and July 2022. Dkt. No. 26-1 at 12. On August 8, 2022, the ACUP was approved. Dkt. No. 26-1 at 12; Dkt. No. 33-2. Two days later, on August 10, 2022,

the County’s Sewer Utility issued a fee letter identifying the REUs for the project at the $7,020/REU rate. Dkt. No. 31 at 6. The Site Development Activity Permit (“SDAP”) was approved on August 9, 2022, and issued on August 25, 2022. Dkt. Nos. 33-3; 33-4. On July 25, 2023, Petitioners paid the newcomer’s assessment for Buildings 1 through 11, the clubhouse, and the community building—totaling 278 REUs—at the

$7,020/REU rate then in effect. See Dkt. No. 26-1 at 22; see also Dkt. No. 28-1. On February 24, 2024, the parties entered a “Phased Development Contract” under KCC 13.14.160 for the remaining 166 REUs (phases two and three). Dkt. No. 28-9. That contract stated that the “amount of newcomer’s assessment attributable to each phase of development or discreet unit is pursuant to the Resolution in effect at the time of connection.” Dkt. No. 28-9 at 3. The first physical sewer connections did not occur until early 2024. Dkt. No. 30 at 5; Dkt. No. 26-1 at 18.

Because the connections for the remaining units occurred after August 1, 2023, the Sewer Utility applied the $9,939/REU rate—the rate set by Resolution 131-2023—to those units. Dkt. No. 26-1 at 18, 23. As a result, Petitioners paid $7,020/REU for the first 278 REUs and were required to pay $9,939/REU for the balance. Dkt. No. 26-1 at 22–23. On March 31, 2025, Petitioners objected to the mid-project rate increase

through the dispute resolution process under KCC 13.14.180(c). Dkt. No. 28-4. On April 10, 2025, the Director rejected Petitioners’ objections, maintaining that the newcomer’s assessment are “ultimately valued and due at the time of connection— meaning when a sewer permit is issued allowing a project building to be connected

to the utility system.” Dkt. No. 26-1 at 18. Petitioners appealed the Director’s decision to the Board, which held a public meeting on June 9, 2025, and denied the appeal. Dkt. No. 28-8. Under RCW 36.70C.080(5), the parties waived the initial hearing and stipulated to a hearing on the merits, which the Court held on December 29, 2025. Dkt. No. 37. At the hearing, both parties confirmed that there are no factual

disputes; this case turns entirely on the interpretation of Kitsap County Code Chapter 13.14. The Court has reviewed the parties’ briefing, the Administrative Record and its supplements, and the hearing transcript. Dkt. Nos. 25-1, 26-1, 27, 28, 30, 31, 32, 33, 34, 37. Because this was not a quasi-judicial proceeding, the record may be supplemented under RCW 36.70C.120(3), and the Court has considered the supplemental declarations and exhibits. Dkt. Nos. 28, 31, 33, 34.

Free access — add to your briefcase to read the full text and ask questions with AI

JSP Silverdale Land LLC et al v. Kitsap County, (W.D. Wash. 2026).

JSP Silverdale Land LLC et al v. Kitsap County (JSP Silverdale Land LLC et al v. Kitsap County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Whatcom County v. City of Bellingham
909 P.2d 1303 (Washington Supreme Court, 1996)
State v. Krall
881 P.2d 1040 (Washington Supreme Court, 1994)
Tahoma Audubon Society v. PARK JUNCTION
116 P.3d 1046 (Court of Appeals of Washington, 2005)
Sleasman v. City of Lacey
151 P.3d 990 (Washington Supreme Court, 2007)
Ellensburg Cement Products, Inc. v. Kittitas County
317 P.3d 1037 (Washington Supreme Court, 2014)
Durland v. San Juan County
340 P.3d 191 (Washington Supreme Court, 2014)