King County Department of Development & Environmental Services v. King County

305 P.3d 240, 177 Wash. 2d 636
Washington Supreme Court·Decided June 27, 2013·No. No. 87514-6·Published·Cited by 23 cases

Opinion

C. Johnson, J.

¶1 This land use case requires us to determine how the King County Code provisions allow uses to vest as nonconforming uses. This case began as a challenge to an agency order declaring the use of the property was not compliant with King County zoning ordinances. The applicants’ challenge was based on the assertion that the use was established before revisions to the zoning ordinances characterized the use as nonconforming and, thus, required a permit.

¶2 This case also presents the issue of what effect a nonpermitted activity has on a later claim to a preexisting use when a permit was required for the activity asserted as support for a preexisting use. The hearing examiner found for the landowner on all relevant issues, but the decision was reversed by the superior court. The Court of Appeals reversed the superior court, and we now reverse the Court of Appeals and hold that the landowner’s use was not established within the meaning of the King County Code.

Facts and Procedural History

¶3 The 10-acre parcel of land at issue in this appeal lies in the Green River Valley and is zoned agricultural. The landowner, Jeffrey Spencer, allowed Ronald Shear, who operates a business (BRC), which processes organic materials into animal bedding and fuel, to rent the property.1

¶4 In 2003, Shear was operating a similar processing facility on a one-acre parcel near Spencer’s parcel. In October, the two entered into an oral “lease” agreement whereby Shear began bringing equipment and materials onto Spencer’s parcel for later processing. This operation fit under the definition of an “interim recycling facility” under the then-existing King County Code and required no use-specific permitting. Shear’s activities on the parcel increased throughout 2004, although no actual grinding or [640] processing had begun. Then, in September 2004, King County amended its code to require permitting for operations such as Shear’s, classifying them as “materials processing facilities.”2 There is no dispute that Shear’s current operations constitute a materials processing facility under the code. Nor is it disputed that actual grinding of the organic materials had not commenced before the code revisions. However, the hearing examiner did find that Shear’s operations were continually expanding during the time leading up to the zoning revisions and that the business required three stages for full implementation: site preparation, grinding of raw materials, and transfer of those materials off site. The hearing examiner also found that prior to the zoning change, “all of the essential first-stage site preparation activities were underway.” Clerk’s Papers (CP) at 31.

¶5 Shortly after the zoning change, in late 2004 or early 2005, Shear began actual grinding of organic materials. In response to complaints from a nearby landowner, the Department of Development and Environmental Services (DDES) began to investigate Shear’s operations. Apparently, DDES made multiple informal contacts before ultimately filing an administrative notice and order on October 9, 2006. The administrative order found two violations: the operation of a materials processing facility in a critical area without permit and grading in critical areas (flood hazard area and wetlands) without proper permitting.

¶6 Shear appealed the administrative order, setting off long and contentious proceedings not relevant here. On January 28,2010, the hearing examiner filed his report and decision, which was largely (but not completely) in favor of Shear. In relevant part, the hearing examiner interpreted [641] the following language of the King County Code as expressly recognizing that preexisting uses could vest even if not in full operation:

21A.06.800 Nonconformance. Nonconformance: any use, improvement or structure established in conformance with King County rules and regulations in effect at the time of establishment that no longer conforms to the range of uses permitted in the site’s current zone or to the current development standards of the code due to changes in the code or its application to the subject property.
21A.08.010 Establishment of uses. The use of a property is defined by the activity for which the building or lot is intended, designed, arranged, occupied, or maintained. The use is considered permanently established when that use will or has been in continuous operation for a period exceeding sixty days. A use which will operate for less than sixty days is considered a temporary use, and subject to the requirements of K.C.C. 21A.32 of this title. All applicable requirements of this code, or other applicable state or federal requirements, shall govern a use located in unincorporated King County.

King County Code (KCC) 21A.06.800; KCC 21A.08.010. Thus, the hearing examiner reasoned, Shear’s use as a materials processing facility could be a preexisting use despite the fact that actual grinding had not begun prior to the zoning change. The hearing examiner also found that the King County Code required further actions by the county to designate flood hazard areas and, because it had yet to complete the process, the code contained an unenforceable flood hazard standard. Finally, the hearing examiner found that Shear had engaged in unlawful grading, albeit not in a critical area.3

¶7 Importantly, the hearing examiner recognized that Shear’s use had and would likely continue to expand and required Shear to obtain a conditional use permit for any expansion. He determined that Shear’s use as of September [642]*6422004 (the month King County amended its code) was the baseline level of permitted use. Any expansion after that date would require a conditional use permit. However, given the contentious nature of the proceedings, the hearing examiner also recognized that DDES might abuse the conditional use permit process and imposed several restrictions applicable to the permitting process. He ruled that DDES was not allowed to use the permit process to directly or indirectly prohibit a viable materials processing facility. Moreover, subject to small exceptions, it could not require any further studies on the wetland or flood hazard area issues.

Free access — add to your briefcase to read the full text and ask questions with AI

King County Department of Development & Environmental Services v. King County, 305 P.3d 240, 177 Wash. 2d 636 (Wash. 2013).

305 P.3d 240 (King County Department of Development & Environmental Services v. King County) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Untitled Case
W.D. Washington, 2026
City of Spokane Valley v. Blayne Dutton, et ux
Court of Appeals of Washington, 2024
Tom Latta v. Chelan County
Court of Appeals of Washington, 2023
Seven Hills, LLC v. Chelan County
Washington Supreme Court, 2021
Brown v. Mason County
W.D. Washington, 2021
Cape St. Mary Associates v. San Juan County
Court of Appeals of Washington, 2020
Donald And Kathleen Miller v. City Of Sammamish
447 P.3d 593 (Court of Appeals of Washington, 2019)
One Energy Development, LLC v. Kittitas County
Court of Appeals of Washington, 2019
Kimberlyn Dotson v. Pierce County
Court of Appeals of Washington, 2018
Old Lantern Non-Conforming Use
Vermont Superior Court, 2017
Donald I. Berg, Et Ano. v. City Of Kent
Court of Appeals of Washington, 2016
Wa State Department Of Transporation, Res. v. City Of Seattle, App.
192 Wash. App. 824 (Court of Appeals of Washington, 2016)
Klineburger v. King County
356 P.3d 223 (Court of Appeals of Washington, 2015)
Daniel Duffus v. City Of Seattle
Court of Appeals of Washington, 2015
Kitsap County v. Kitsap Rifle & Revolver Club
337 P.3d 328 (Court of Appeals of Washington, 2014)
Kitsap County v. Kitsap Rifle And Revolver Club
Court of Appeals of Washington, 2014
Race Track, Llc v. King County
Court of Appeals of Washington, 2014