JRS LTD. v. ACE AMERICAN INSURANCE COMPANY

CourtDistrict Court, N.D. New York
DecidedMarch 26, 2026
Docket1:25-cv-00730
StatusUnknown

This text of JRS LTD. v. ACE AMERICAN INSURANCE COMPANY (JRS LTD. v. ACE AMERICAN INSURANCE COMPANY) is published on Counsel Stack Legal Research, covering District Court, N.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JRS LTD. v. ACE AMERICAN INSURANCE COMPANY, (N.D.N.Y. 2026).

Opinion

UNITED STATES DISTRICT COURT NORTHERN DISTRICT OF NEW YORK ____________________________________________

JRS LTD.,

Plaintiff, vs. 1:25-CV-730 (MAD/PJE) ACE AMERICAN INSURANCE COMPANY,

Defendant. ____________________________________________

APPEARANCES: OF COUNSEL:

COHEN ZIFFER FRENCHMAN CHELSEA IRELAND, ESQ. & MCKENNA LLP KENNETH H. FRENCHMAN, ESQ. 1325 Avenue of the Americas, 31st Floor New York, New York 10019 Attorneys for Plaintiff

FORAN GLENNON PALANDECH CHARLES J. ROCCO, ESQ. PONZI & RUDLOFF DAWN M. BREHONY, ESQ. 40 Wall Street, 54th Floor New York, New York 10005 Attorneys for Defendant

CLYDE & CO US LLP GARION T. LIBERTI, ESQ. 2 Grand Central Tower 140 East 45th Street, 26th Floor New York, New York 10017 Attorney for Defendant

Mae A. D'Agostino, U.S. District Judge:

MEMORANDUM-DECISION AND ORDER I. INTRODUCTION On June 9, 2025, JRS Ltd. ("Plaintiff"), as assignee of nonparty Gravity Renewables, Inc. ("Gravity"),1 brought this diversity action against ACE American Insurance Company ("Defendant") for breach of an insurance agreement. See Dkt. No. 1. The complaint lists three causes of action: (1) breach of contract – property damage; (2) breach of contract – business interruption; and (3) consequential damages. See id. On August 7, 2025, Defendant moved to dismiss the complaint under Federal Rule of Civil Procedure 12(b)(6), arguing that Plaintiff's complaint is untimely. See Dkt. No. 12. Plaintiff opposed the motion on September 3, 2025, see Dkt. No. 18, and Defendant filed a reply

on September 19, 2025, see Dkt. No. 21. For the following reasons, Defendant's motion is denied. II. BACKGROUND This action arises out of a large-scale operational failure at Gravity's Dahowa Hydroelectric Plant ("the Plant"), a renewable energy facility in Greenwich, New York. See Dkt. No. 1 at ¶¶ 1-3. The Plant uses waterflow to generate electricity and relies on "various gates and seals" to control the waterflow. Id. at ¶ 13. Two of the apparatuses are tailwater gates and turbine blade seals. See id. Plaintiff alleges that "[i]n December 2020, several turbine blade seals failed, allowing

river water to contaminate the hydraulic power unit . . . system." Id. at ¶ 14. Because of the failure, Gravity shut down the Plant for an emergency repair. See id. During the emergency repair, "Gravity discovered that the tailwater gates were not sealing properly[.]" Id. at ¶ 15. The

1 As alleged in the complaint, on December 4, 2024, Plaintiff, Gravity, and a third party executed an agreement that assigned Gravity's insurance policy claims to Plaintiff. See Dkt. No. 1 at ¶¶ 88- 91. Defendant does not dispute that Plaintiff is the real party in interest with respect to this action or otherwise question Plaintiff's status as a proper litigant. See id. at ¶ 91; see also Dkt. No. 12-1. emergency repair was finished by January 2021, but Gravity determined that further investigation and repairs were needed. See id. at ¶¶ 14-16. Gravity decided to have commercial divers investigate the problem. See id. at ¶ 16. The dive was postponed until August 2021, when water temperatures and river flows were expected to be safer for the divers. See id. at ¶ 18. To facilitate the August 2021 investigation and repairs, Gravity needed to dewater the Plant. See id. at ¶ 19. The divers installed custom aluminum sealing plates on September 9, 2021. See id. at ¶ 21. However, problems persisted because a drain line was clogged with sediment. See id. at ¶ 22. The drain line was cleared on October 7, 2021. See id. at ¶ 23. The

divers eventually completed the seal after several safety-related delays, and the dewatering process began on November 10, 2021. See id. at ¶ 26. On January 12, 2022, Gravity was able to inspect the tailwater gate chambers for the first time since the Plant's construction in 1991. See id. at ¶ 33. The inspection revealed that decades of concrete cracking and deterioration caused the seal issues. See id. at ¶¶ 34-35. Gravity developed a repair plan, completed the necessary repairs, and returned the Plant to service on May 25, 2022. See id. at ¶¶ 36-37. Plaintiff alleges the Plant was inoperable from August 2021 through May 2022, and due to the shutdown, Gravity incurred at least $1,668,313 in repair costs. See id. at ¶¶ 2, 39.

Additionally, Plaintiff claims that Gravity lost at least $3,905,192 of income during that period. See id. at ¶ 39. Gravity had purchased an insurance policy (the "Policy") from Defendant for these types of losses, and the Policy was in effect during the relevant period. See id. at ¶¶ 40-41. Gravity notified Defendant of its claim for coverage under the Policy, see id. at ¶ 52, and Plaintiff alleges that after a "protracted and frustrating investigation[,]" Defendant paid "less than half of the total covered loss to which Gravity was entitled[,]"id. at ¶ 53. According to the complaint, Defendant appointed Sedgwick CMS ("Sedgwick") as its claim adjuster to investigate Gravity's purported loss. See id. Sedgwick began its investigation on March 3, 2022. See id. at ¶ 54. Approximately one month later, on April 4, 2022, Sedgwick sent a letter on Defendant's behalf summarizing Defendant's understanding of the loss. See id. at ¶ 55 (quoting Dkt. No. 1-2 at 2). Defendant also hired an engineering firm and an accounting firm to assist with its investigation. See id. at ¶ 57 (quoting Dkt. No. 1-2 at 2). In May 2023, more than a year later, Defendant valued Gravity's claim at approximately $1,444,897. See id. at ¶ 59. After Defendant and Gravity executed proofs of loss as to that

amount, Defendant paid Gravity $1,176,802 (the valuation amount, minus deductibles). See id. at ¶¶ 60-61. Three months later, in August 2023, Sedgwick wrote to Gravity on Defendant's behalf with an update on the investigation and additional coverage. See id. at ¶ 62. Sedgwick informed Gravity that the Policy covered some of the claimed property damage, but not all. See id. at ¶ 63 (quoting Dkt. No. 1-4 at 2). Sedgwick also stated that "'the period of interruption should be limited to 80-days.'" Id. (quoting Dkt. No. 1-4 at 2). According to Plaintiff, Sedgwick "assured Gravity that" Defendant had not made a final coverage determination and would "continue its investigation." Id. at ¶ 64; Dkt. No. 1-4 at 7. A section of the August 2023 letter labeled "Suit

Limitation Period" reads in part: "You requested a 180-day extension of the Policy's suit limitation period. In response to your request, [Defendant's agent] consents to extend the suit limitation 120 days to March 10, 2024, to the extent that it has not yet expired." Dkt. No. 1-4 at 7. On January 31, 2024, Sedgwick sent another letter as a "supplement" to its August 2023 letter. Dkt. No. 1 at ¶ 65; see Dkt. No. 1-5. Therein, Sedgwick reiterated Defendant's position regarding which costs were covered and agreed to increase the interruption period to 88 days. See Dkt. No. 1 at ¶ 65 (citing Dkt. No. 1-5 at 2-3). Sedgwick re-confirmed that the investigation was ongoing. See id. at ¶ 66; see Dkt. No. 1-5 at 4. On June 10, 2024, Sedgwick sent a letter with what Plaintiff considers to be Defendant's "final coverage position." Dkt. No. 1 at ¶ 67; Dkt. No. 1-6. That coverage position provided for an additional property damage payment of $134,386 and an additional business interruption payment of $145,893. See Dkt. No. 1 at ¶ 68; Dkt. No. 1-6 at 4. The parties executed an updated proof of loss on July 10, 2024. See Dkt. No. 1 at ¶ 68; Dkt. No. 1-7. Plaintiff alleges that Defendant undervalued the covered costs by more than $700,000.2 See Dkt. No. 1 at ¶ 69 (citing

Dkt. No. 1-7).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fabozzi v. Lexington Insurance
601 F.3d 88 (Second Circuit, 2010)
Roth v. Jennings
489 F.3d 499 (Second Circuit, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
In Re Books, Inc.
770 F.2d 288 (Second Circuit, 1985)
Morgan Stanley Group v. New England Ins. Co.
225 F.3d 270 (Second Circuit, 2000)
Patane v. Clark
508 F.3d 106 (Second Circuit, 2007)
ATSI Communications, Inc. v. Shaar Fund, Ltd.
493 F.3d 87 (Second Circuit, 2007)
Mostow v. State Farm Ins. Cos.
668 N.E.2d 392 (New York Court of Appeals, 1996)
Consolidated Edison Co. of New York, Inc. v. Allstate Insurance
774 N.E.2d 687 (New York Court of Appeals, 2002)
County of Columbia v. Continental Insurance
634 N.E.2d 946 (New York Court of Appeals, 1994)
Garcha v. City of Beacon
351 F. Supp. 2d 213 (S.D. New York, 2005)
Wajilam Exports (Singapore) Pte. Ltd. v. ATL Shipping Ltd.
475 F. Supp. 2d 275 (S.D. New York, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
JRS LTD. v. ACE AMERICAN INSURANCE COMPANY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jrs-ltd-v-ace-american-insurance-company-nynd-2026.