J.R.'s Landscaping & Sprinkler Systems, Inc. v. City of Crosbyton

CourtCourt of Appeals of Texas
DecidedSeptember 21, 2015
Docket07-14-00019-CV
StatusPublished

This text of J.R.'s Landscaping & Sprinkler Systems, Inc. v. City of Crosbyton (J.R.'s Landscaping & Sprinkler Systems, Inc. v. City of Crosbyton) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
J.R.'s Landscaping & Sprinkler Systems, Inc. v. City of Crosbyton, (Tex. Ct. App. 2015).

Opinion

In The Court of Appeals Seventh District of Texas at Amarillo

No. 07-14-00019-CV

J.R.'S LANDSCAPING & SPRINKLER SYSTEMS, INC., APPELLANT

V.

CITY OF CROSBYTON, APPELLEE

On Appeal from the 72nd District Court Crosby County, Texas Trial Court No. 2010-7347, Honorable Ruben Gonzales Reyes, Presiding

September 21, 2015

MEMORANDUM OPINION Before CAMPBELL and HANCOCK and PIRTLE, JJ.

Appellant J.R.’s Landscaping & Sprinkler Systems, Inc. brought suit against the

City of Crosbyton, Texas, alleging breach of its construction contract with the City. The

City brought a counterclaim, asserting J.R.’s had failed to perform the contract as

required.1 Each sought damages. After a bench trial, the court awarded the City its

damages for the cost of completion of the project.

1 The elements of a breach of contract claim are: (1) the existence of a valid contract; (2) performance or tendered performance by the plaintiff; (3) breach of the contract by the defendant; and (4) On appeal, J.R.’s brings two issues, one contending the court erred by rejecting

its claim for damages, the second contending it erred by entering judgment for the City.

After we abated the appeal, the court signed findings of fact and conclusions of law. 2

We will affirm.

Background

The contract called for J.R.’s to furnish materials and labor for the construction of

new concrete sidewalks, curbs and gutters, access ramps, handrails and related work at

locations in downtown Crosbyton. The final contract amount was $142,632.80. During

construction J.R.’s requested, and was paid, $64,307.

Chester Carthel of Carthel’s Engineering served as engineer and owner’s

representative. At a point, a difference of opinion arose between Carthel and the City

regarding J.R.’s completion of the work. Carthel received J.R.’s notice that work was

substantially complete, inspected the work, concluded the project was substantially

complete and complied with the contract, and approved J.R.’s application for payment

of the remaining contract amount. At trial, Carthel agreed it was his opinion that the

work was substantially complete and that the application should have been paid.

The City was dissatisfied with the work. The mayor testified he told J.R.’s on

several occasions that he was not satisfied with the appearance of the sidewalks and

complained about defects such as pitting. J.R.’s attempted repairs to several areas by

____________________ damages sustained by the plaintiff as a result of the breach. Wright v. Christian & Smith, 950 S.W.2d 411, 412 (Tex. App.—Houston [1st Dist.] 1997, no writ). 2 See J.R.’s Landscaping & Sprinkler Sys. v. City of Crosbyton, No. 07-14-00019-CV, 2014 Tex. App. LEXIS 12666 (Tex. App.—Amarillo, November 21, 2014, no pet.) (mem. op.).

2 patching the concrete, but the mayor testified the patching was not successful. He said

J.R.’s was “going to get us a proposed way of taking care of the problem. And then we,

the council, would approve.” He testified he never received a proposed plan of action

from J.R.’s, who merely attempted more patches. The City never formally accepted the

work.

The City hired another engineer, Michael Adams, who testified he found several

issues with the concrete, including exposed aggregate rock, spalling, sloping and

rusting of exposed rebar. He expressed the opinion the workmanship was “at a low

level,” and recommended that the areas of concrete containing the defects be torn out

and replaced, at an estimated cost of $160,000.

When the City did not pay its final payment application, J.R.’s filed suit. On the

City’s counterclaim, the court awarded it damages of $160,000, interest and attorney’s

fees.

Analysis

All the trial court’s findings of fact and conclusions of law favor the City. In

support of its first issue, J.R.’s contends the evidence established as a matter of law

that the City breached the contract by failing to pay J.R.’s final invoice. See Dow Chem.

Co. v. Francis, 46 S.W.3d 237, 241 (Tex. 2001) (per curiam); Barnett v. Coppell N. Tex.

Court, Ltd., 123 S.W.3d 804 (Tex. App.—Dallas 2003, pet. denied) (standard of review).

To reach that conclusion, J.R.’s argues that the contract unambiguously provided that

acceptance of the project by the owner’s representative was conclusive and binding on

the City. To sustain its contention, we would be required to agree that J.R.’s reading of

3 the contract is the only reasonable reading. See, e.g., Columbia Gas Trans. Corp. v.

New Ulm Gas, 940 S.W.2d 587, 589 (Tex. 1996); Universal C.I.T. Credit Corp. v.

Daniel, 150 Tex. 513, 517, 243 S.W.2d 154, 157 (Tex. 1951) (ambiguity of contracts).

J.R.’s relies on a section of the contract with the title, “Contract Closeout.”3 Its

subsections include those entitled “substantial completion,” “final inspection,” and “final

payment.” It contains a statement reading, “The Owner's Representative will determine

if the project is Substantially Complete.” It also contains the provision that, within 14

days of notice from the contractor that he believes the work is substantially complete,

the Owner’s Representative will inspect the job and determine if he agrees. The “final

inspection” subsection contains a similar requirement for a response from the Owner’s

Representative to the notice from the contractor.

But the provisions on which J.R.’s relies are not the only contract terms

addressing the subject of payments on completion of the work. The contract’s General

Contract Conditions contain a section entitled “Payments to Contractor,” with

subsections entitled “partial payments,” and “final payment.” As the City points out,

language there appears stating that the contractor’s “requisition for final payment,” will

be prepared “[a]fter final inspection and acceptance by the Owner of all work under the

Contract.” Another provision, contained in the “payment procedures” subsection of a

section entitled “Administrative Requirements,” states that the “Owner’s Representative 3 In addition to several pages of General Contract Conditions, the contract document includes several pages of specifications and other provisions, some of which address topics also addressed in the General Contract Conditions. The General Contract Conditions and these latter provisions appear taken from different contract forms. The language of the General Contract Conditions and these latter provisions of the contract is not consistent, and each contained phrases not used in the other. For example, the General Contract Conditions refer to Carthel as “Engineer,” while the latter contract pages refer to the individual filling his role as the “Owner’s Representative,” a phrase not appearing in the General Contract Conditions. The capitalized, but undefined, phrase “Substantially Complete” appears in the latter provisions but not in the General Contract Conditions.

4 will review pay request [sic] and recommend action to the Owner within 14 calendar

days of submission.”4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Tribble & Stephens Co. v. RGM Constructors, L.P.
154 S.W.3d 639 (Court of Appeals of Texas, 2005)
Barnett v. Coppell North Texas Court, Ltd.
123 S.W.3d 804 (Court of Appeals of Texas, 2004)
Dow Chemical Co. v. Francis
46 S.W.3d 237 (Texas Supreme Court, 2001)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
Wright v. Christian & Smith
950 S.W.2d 411 (Court of Appeals of Texas, 1997)
Columbia Gas Transmission Corp. v. New Ulm Gas, Ltd.
940 S.W.2d 587 (Texas Supreme Court, 1996)
Universal C. I. T. Credit Corp. v. Daniel
243 S.W.2d 154 (Texas Supreme Court, 1951)
State of Texas v. Martin Bros.
160 S.W.2d 58 (Texas Supreme Court, 1942)
City of San Antonio v. McKenzie Construction Co.
150 S.W.2d 989 (Texas Supreme Court, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
J.R.'s Landscaping & Sprinkler Systems, Inc. v. City of Crosbyton, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jrs-landscaping-sprinkler-systems-inc-v-city-of-crosbyton-texapp-2015.