Joshua Williams v. TESCO Services, Inc.

719 F.3d 968, 2013 WL 3333999, 2013 U.S. App. LEXIS 13481
CourtCourt of Appeals for the Eighth Circuit
DecidedJuly 2, 2013
Docket12-2130, 12-2220
StatusPublished
Cited by36 cases

This text of 719 F.3d 968 (Joshua Williams v. TESCO Services, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joshua Williams v. TESCO Services, Inc., 719 F.3d 968, 2013 WL 3333999, 2013 U.S. App. LEXIS 13481 (8th Cir. 2013).

Opinion

LOKEN, Circuit Judge.

Joshua Williams was severely injured while working on an oil and gas rig in Conway County, Arkansas. After recovering workers’ compensation benefits from his employer, DeSoto Drilling, Inc. (“De-Soto”), Williams commenced this diversity action for damages, asserting tort claims against various third parties including rig and drilling equipment manufacturers; TESCO Services, Inc. (“TESCO”), the contractor installing casing pipe in the well-hole at the time of the accident; and Jeffrey Anderson, a TESCO employee. Chartis Casualty Company, DeSoto’s workers’ compensation carrier, intervened in the lawsuit, seeking a statutory lien on Williams’s recovery from third-party tort-feasors. See Ark. Stat. § 11 — 9—410(a)(1).

Williams and two manufacturers settled after the district court 1 denied their cross motions for summary judgment. After further briefing, the court granted summary judgment dismissing negligence claims against Anderson and TESCO on the ground that these defendants’ common law duty of ordinary care to Williams, as informed by the contractual relationships between the parties, did not “require Anderson and TESCO to foresee” that the actions of Williams’s co-workers would result in his tragic injury. Williams v. Anderson, No. 4:09-cv-459, 2012 WL 1314150, at *5 (E.DArk. Apr. 16, 2012). The court also struck an untimely report by Williams’s expert witness and denied his belated motion to amend the complaint to add a failure-to-train claim against TESCO. Williams and Chartis separately appeal these rulings. We consolidated the appeals. Reviewing the grant of summary judgment de novo, we affirm. See Koch v. Sw. Elec. Power Co., 544 F.3d 906, 908 (8th Cir.2008) (standard of review).

I. Background

As we are reviewing the grant of summary judgment in favor of defendants Anderson and TESCO, we state the material facts, when disputed, in the light most favorable to Williams, the non-moving party-

A. The Parties. Southwestern Energy Production Company (“SWE”) was the Owner/Operator of the oil and gas well. SWE hired DeSoto, its wholly-owned sub *971 sidiary, to serve as the Drilling Contractor. DeSoto owned Drilling Rig # 9, on which the accident occurred, and employed a drilling crew that included Williams to operate the rig. MD Cowan, Inc. designed and manufactured Rig # 9. Rig Technology, Ltd. supplied the rig’s hoist system, or drawworks, which raised and lowered a power swivel, or top drive, on the mast of the rig. SWE hired TESCO, an independent contractor, to provide casing services for the well. Installing casing pipe, which preserves the structural integrity of the well-hole, is a specialized service that is often not performed by Operators or Drilling Contractors. For these services, TES-CO provided a “TESCO tool” that DeSoto attached to the rig’s top drive. SWE’s On-Site Representative, Laddy Pender-graff, coordinated and oversaw the operations of DeSoto and TESCO.

DeSoto began drilling the well in early April, 2007. Ten days later, casing operations began. Williams’s expert explained: “DeSoto’s Rig Crew would operate Rig 9 while Tesco’s Casing Crew would control the details of the work with regard to handling, making-up and running the Casing.” To install casing pipe, DeSoto’s Driller, at the time in question Assistant Driller Derrick Long, hoisted the top drive with the attached TESCO tool upward along the rig mast while a pipe boom lifted a 40-foot section of casing pipe into position. After the Driller, operating the drawworks, lowered the TESCO tool over the top of the casing pipe, TESCO’s Casing Drive System Operator, in this' case Jeffrey Anderson, locked the TESCO tool onto the pipe section. The Driller then lowered the casing pipe to the well-hole and, using the TESCO tool, rotated the pipe section, threading it into the existing “string” of casing pipe until firmly connected. The entire string was then lowered into the well-hole and the process repeated until the needed sections of casing pipe were connected and cemented into the well-hole.

B. The Accident. On the morning of the accident, the top drive came out of alignment with the well-hole, causing sections of casing pipe to become “cross-threaded.” Casing operations halted. De-Soto’s rig foreman, Wade Hargis, ordered Williams and another DeSoto employee, Will Cox, to climb the two sides of the rig mast and realign the top drive. Because of inclement weather, Long, Anderson, and Pendergraff went inside a shelter, the “doghouse,” on the floor of the rig.

Some 45 minutes later, Cox climbed down after completing his adjustments and went into the doghouse. Williams testified that he finished his adjustments and started down, but Hargis, standing on the rig floor, told Williams to climb back up and make more adjustments, which he did. In the doghouse, Long asked Cox if they were done; Cox replied he had done all he could. Pendergraff told Long to “get this show on the road” because cement trucks were waiting. Hargis, now inside the doghouse, said, “yeah, let’s go.” Long and Anderson, unaware that Williams was still atop the mast making repairs, went outside to their controls. Each looked up and saw no one on the mast because Williams was behind the top drive. Anderson had a file in his hand to repair a cross-threaded pipe section sitting in the slip, but Long needed to raise the top drive so that Anderson could access the pipe threads. Long asked Anderson if he was ready. Anderson said, “Pick it up,” referring to the top drive. Long engaged the clutch and moved the top drive upward, pinching Williams’s right leg so severely it had to be amputated above the knee.

C. Procedural History. Williams filed this action in June 2009. The complaint alleged negligent design and failure to warn claims against MD Cowan and Rig *972 Tech because DeSoto’s crew did not use the rig’s “Lock Out/Tag Out” system when repairing the top drive misalignment, a system intended to ensure that the hoist cannot be restarted while an employee such as Williams is in harm’s way. Those claims are not before us because Williams settled with Cowan and Rig Tech after discovery closed and the court denied cross motions for summary judgment.

The complaint also asserted negligence claims against Anderson and TESCO, alleging that Anderson negligently “directed that the top drive be moved,” and that TESCO was “vicariously liable to [Williams] because the negligence of Anderson is imputed to it under the doctrine of respondeat superior.” After close of discovery, the parties filed cross motions for summary judgment. Williams argued that Anderson breached a common law duty of care and a duty imposed by the SWE/TESCO contract when he instructed Long to move the top drive when it was unsafe to do so. TESCO and Anderson argued that Anderson owed Williams no common law or contractual duty of care because “the repair work Williams was performing on the top drive was not in any way related to Tesco, and because Anderson had no authority to cause the rig to be restarted after Williams made repairs to the top drive.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
719 F.3d 968, 2013 WL 3333999, 2013 U.S. App. LEXIS 13481, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joshua-williams-v-tesco-services-inc-ca8-2013.