This text of 364 F. App'x 681 (Joseph F. Cooper v. PSI Group, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Second Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joseph F. Cooper v. PSI Group, Inc., 364 F. App'x 681 (2d Cir. 2010).

Opinion

SUMMARY ORDER

Plaintiff Joseph Cooper appeals from (1) the district court’s June 5, 2008 order granting in part defendants’ motion to dismiss, and (2) the district court’s March 23, 2009, 2009 WL 792353, order granting summary judgment to defendants on the remaining claims. We assume the parties’ familiarity with the underlying facts, the procedural history, and the issues presented for review.

We review a district court’s grant of a motion to dismiss de novo, accepting all factual allegations in the complaint as true and drawing all reasonable inferences in the plaintiffs favor. Chambers v. Time Warner, Inc., 282 F.3d 147, 152 (2d Cir.2002). We also review a district court’s grant of summary judgment de novo. Abdu-Brisson v. Delta Air Lines, Inc., 239 F.3d 456, 465 (2d Cir.2001). “Summary judgment is appropriate only when there are no genuine issues of material fact and the movant is entitled to judgment as a matter of law.” Id. When making this determination, the court must view the evidence in the light most favorable to the non-moving party, drawing all reasonable inferences in that party’s favor. Id. at 465-66.

The district court granted Siemens’ motion to dismiss Cooper’s claim under the Connecticut Wage Act, Conn. Gen.Stat. § 31-72, on the ground that a two-year statute of limitations applied. That statute of limitations, Conn. Gen.Stat. § 52-596, provides that “[n]o action for the payment of remuneration for employment payable periodically shall be brought but within two years after the right of action accrues.” Id. (emphasis added). Cooper argues that the district court erred in applying this statute to his claim, which sought to recover unpaid commissions, because those commissions were not “payable periodically.”

We agree. Siemens points to no contractual provision that specifies or requires that Cooper’s commission payments be made on any periodic schedule. The contract appears to be silent as to when Cooper was entitled to receive these commission payments. Accordingly, the district court erred when it concluded that Cooper’s remuneration was “payable periodically” and that his wage act claim against Siemens was therefore barred by the two-year statute of limitations.

Cooper’s remaining claims, however, were properly disposed of by the district court. The letter agreement between Cooper and PSI was integrated on the subject of commissions, both because they were “mentioned, covered, or dealt with in the writing,” Associated Catalog Merchandisers, Inc. v. Chagnon, 210 Conn. 734, 740, 557 A.2d 525 (1989) (internal quotation marks omitted), and because the letter agreement contained a merger clause, which “is conclusive evidence of the parties’ intent to create a fully integrated agreement,” Alstom Power, Inc. v. Balcke-Durr, Inc., 269 Conn. 599, 612, 849 A.2d *683 804 (2004). This integration bars Cooper’s attempt to introduce evidence of a conflicting conversation he had with a PSI manager prior to being hired, and thus bars his assertion that he should have been paid commissions “in accordance with the [Siemens] Employment Agreement.”

Cooper’s claims against Siemens and PSI based on a theory of unjust enrichment are also without merit. “[A]n express contract between the parties precludes recognition of an implied-in-law contract governing the same subject matter,” Meaney v. Connecticut Hosp. Ass’n, Inc., 250 Conn. 500, 517, 735 A.2d 813 (1999) (internal quotation marks omitted), and thus precludes recovery for unjust enrichment. See Vertex, Inc. v. City of Waterbury, 278 Conn. 557, 574, 898 A.2d 178 (2006). Cooper entered into written employment agreements with both PSI and Siemens, and those agreements addressed the' subject of commissions. Accordingly, Cooper cannot recover on a theory of unjust enrichment.

For the foregoing reasons, the judgment of the district court is hereby AFFIRMED in part, VACATED in part, and REMANDED for further proceedings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Abdu-Brisson v. Delta Air Lines, Inc.
239 F.3d 456 (Second Circuit, 2001)
Chambers v. Time Warner, Inc.
282 F.3d 147 (Second Circuit, 2002)
Associated Catalog Merchandisers, Inc. v. Chagnon
557 A.2d 525 (Supreme Court of Connecticut, 1989)
Meaney v. Connecticut Hospital Ass'n
735 A.2d 813 (Supreme Court of Connecticut, 1999)
Alstom Power, Inc. v. Balcke-Durr, Inc.
849 A.2d 804 (Supreme Court of Connecticut, 2004)
Vertex, Inc. v. City of Waterbury
898 A.2d 178 (Supreme Court of Connecticut, 2006)