Joseph Amedson v. Puget Sound Electric Company

Court of Appeals of Washington·Decided March 22, 2016·No. 47195-7·Unpublished

Opinion

Filed

Washington State

Court of Appeals

Division Two

March 22, 2016

IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON

DIVISION II

JOSEPH R. AMEDSON, No. 47195-7-II

Respondent,

v.

PUGET SOUND ELECTRIC COMPANY, a UNPUBLISHED OPINION Washington corporation; CHARLES W. CLARK and “JANE DOE” CLARK, husband and wife, both individually and jointly as a marital community; and TRAVELERS CASUALTY AND SURETY COMPANY, BOND #105336057,

Appellants.

MAXA, J. – Puget Sound Electric Company (Puget Sound), Charles Clark and Travelers Casualty and Surety Company (Travelers) appeal the trial court’s order granting summary judgment in favor of homebuilder Joseph Amedson on his claim against Puget Sound’s electrical contractor’s bond issued by Travelers.

Amedson hired Puget Sound to perform electrical work on three houses he was building.

Puget Sound’s work on the project ended after it had completed the “rough-in” electrical work but before it had the chance to perform the “trim” work and complete the project. Amedson determined that Puget Sound’s work was deficient and violated the electrical code in several respects. He filed suit for breach of contract and for recovery against Puget Sound’s bond. The trial court granted summary judgment in favor of Amedson on the bond claim.

Amedson argues that summary judgment was proper because Puget Sound failed to make its electrical installation in accordance with the applicable electrical code, which was a condition of the bond. Puget Sound argues that summary judgment was improper because (1) all the alleged deficiencies either were part of the trim work or would have been corrected easily during performance of the trim work, and it was not allowed to complete the trim work; and (2) other electricians worked on the job after Puget Sound stopped work but before the deficiencies were discovered, and therefore it is unclear whether the deficiencies were caused by Puget Sound. As a result, Puget Sound argues that a genuine issue of material fact exists regarding whether it failed to perform its work in accordance with the applicable electrical code.

We hold that the trial court erred in granting summary judgment because a genuine issue of material fact exists regarding whether Puget Sound failed to make an installation in accordance with the applicable electrical code. Accordingly, we reverse and remand for further proceedings.

FACTS

In November 2012, Amedson contracted Puget Sound to install the rough-in and trim electrical work on three homes that Amedson was building. The contracts specified that payment for the work on each home would come in three installments: (1) initial payment of $2,000 to cover material and permit costs, (2) payment of $4,500 when the rough-in work passed inspection, and (3) final payment of $2,000 plus sales tax after the trim work passed final inspection.

“Rough-in” work refers to the electrical work that will be covered by drywall such as wiring and plug boxes. “Trim” work refers to the electrical work done after the drywall is

installed and includes what will be seen by the homeowner, such as light fixtures, outlets, and switches. A Labor and Industries (L&I) electrical inspector must inspect and approve the rough- in work before drywall may be installed. RCW 19.28.101(4). After the trim work is installed, an L&I inspector conducts a final inspection. RCW 19.28.101(5). Typically, the same electrical contractor completes both stages of installation because the contractor needs to have knowledge of what was installed behind the wall during rough-in in order to do the trim work.

According to Clark, Puget Sound’s president and sole shareholder, Puget Sound completed the rough-in by late December. L&I electrical inspector Greg Harris inspected Puget Sound’s rough-in work on December 28 and approved each home. After the rough-in work passed inspection, general contractors began installing the drywall and painting, but work was delayed because of water intrusion and subcontractor problems.

At some point after the rough-in inspection, Clark and Amedson had an extended dispute over sales tax and minor contract changes, which was resolved in April 2013. On April 12, Clark received a letter from Amedson’s lawyer regarding the dispute, which indicated that (1) Puget Sound had not yet begun the trim work at that time, (2) there was not much work remaining to complete the scope of the contract, and (3) Clark should meet with Amedson to discuss fixtures and materials for trim in order to complete the work. The letter did not indicate that there were any issues with the quality of Puget Sound’s work.

After the rough-in inspection, Puget Sound did some additional work, but Puget Sound never completed the trim work and Puget Sound was not paid for any trim work. Puget Sound last worked on the job on April 17. Amedson alleges that Puget Sound simply ceased working and represented that it had completed the scope of the contract at that time. But Clark alleges

that Amedson terminated Puget Sound and hired new electrical contractors to complete the trim work.

Amedson hired a new electrical contractor, CTI Construction Services LLC (CTI), to complete the trim work. Later, Amedson hired SIRB Electric LLC (SIRB Electric) to troubleshoot defects and deficiencies in the electrical work. Sam Sirb of SIRB Electric compiled a report for Amedson listing all the defects and code violations that SIRB Electric corrected. Amedson and Sirb attributed the electrical deficiencies to the rough-in work done by Puget Sound.

Amedson filed suit against Puget Sound, Clark, and Travelers, asserting multiple contract claims as well as a claim against Puget Sound’s bond. Amedson filed a summary judgment motion on the bond claim, arguing that Puget Sound’s rough-in work did not comply with applicable codes and standards as required by the bond conditions.

Amedson provided his own declaration in support of his summary judgment motion as well as declarations from Sirb and Harris that discussed the alleged deficiencies in Puget Sound’s rough-in work. Sirb identified several deficiencies in the electrical work: (1) circuit load calculation errors and overloading of circuit breakers, (2) discontinuity in branch circuits, (3) incomplete circuits to all rooms and missing ground fault circuit interrupter protection, (4) poor workmanship, and (5) improper placement of or missing receptacles and/or junction boxes. Harris’s declaration stated that the defects listed by Sirb violated specific provisions of the 2008 National Electric Code (2008 NEC).

In opposition to summary judgment, Puget Sound and Travelers filed declarations by Clark and electrical contractor Mark James. Both Clark and James stated that the alleged

deficiencies were all items that normally would be completed during the trim phase or easily corrected during that phase. Clark stated, “I did all rough in work properly and anything else would have been completed in the trim phase.” Clerk’s Papers (CP) at 156. James stated that the deficiencies Sirb described “are well within the range of the work quality typically found on a residential job site.” CP at 197. James also concluded that “the alleged deficiencies could easily have been completed in a short period of time” if the rough-in electrician had been allowed to complete the job. CP at 197.

Clark and James also noted that it was unclear who caused the deficiencies because more than one electrical contractor performed work on the project before SIRB Electric became involved. Clark stated, “I cannot determine the extent of nor whether the alleged deficiencies (incomplete work) are attributable by me or the other three contractors on site.” CP at 155.

The trial court granted summary judgment in favor of Amedson and awarded Amedson $4,000, the amount of the Travelers bond held by Puget Sound.1 Travelers filed a motion to reconsider, which the trial court denied. Puget Sound, Clark and Travelers appeal.

ANALYSIS

Free access — add to your briefcase to read the full text and ask questions with AI

Joseph Amedson v. Puget Sound Electric Company, (Wash. Ct. App. 2016).

Joseph Amedson v. Puget Sound Electric Company (Joseph Amedson v. Puget Sound Electric Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of Seattle v. Koh
614 P.2d 665 (Court of Appeals of Washington, 1980)
Elcon Construction, Inc. v. Eastern Washington University
273 P.3d 965 (Washington Supreme Court, 2012)
Keck v. Collins
357 P.3d 1080 (Washington Supreme Court, 2015)
Sutton v. Tacoma School District No. 10
324 P.3d 763 (Court of Appeals of Washington, 2014)