Jordan Jones & Goulding, Inc. v. Newell Recycling of Atlanta, Inc.

682 S.E.2d 666, 299 Ga. App. 294, 2009 Fulton County D. Rep. 2673, 2009 Ga. App. LEXIS 878
CourtCourt of Appeals of Georgia
DecidedJuly 21, 2009
DocketA09A1397
StatusPublished
Cited by5 cases

This text of 682 S.E.2d 666 (Jordan Jones & Goulding, Inc. v. Newell Recycling of Atlanta, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jordan Jones & Goulding, Inc. v. Newell Recycling of Atlanta, Inc., 682 S.E.2d 666, 299 Ga. App. 294, 2009 Fulton County D. Rep. 2673, 2009 Ga. App. LEXIS 878 (Ga. Ct. App. 2009).

Opinion

BLACKBURN, Presiding Judge.

Jordan Jones and Goulding, Inc. (“JJ&G”), a professional engineering firm, appeals from the trial court’s denial of its motion for summary judgment on the breach of contract claim asserted against it by Newell Recycling of Atlanta, Inc. (“Newell”). JJ&G asserts that the trial court erred in finding that Newell’s claims were subject to the six-year statute of limitation applicable to actions on written contracts, as opposed to the four-year statute of limitation applicable to claims of professional malpractice sounding in contract. Alternatively, JJ&G argues that even if viewed as strictly a breach of contract action, Newell’s claim is subject to the four-year limitation period applicable to contracts that are partly in writing and partly in parol. We find that the record shows unequivocally that Newell is asserting a professional malpractice claim, based upon JJ&G’s alleged breach of its contractual duties to provide competent, professional design and engineering services. Thus, because Newell failed to file suit within the applicable, four-year limitation period, we reverse the trial court’s order.

Summary judgment is proper when there is no genuine issue of material fact and the movant is entitled to judgment as a matter of law. On appeal from the grant or denial of a motion for summary judgment, we review the evidence de novo, and all reasonable conclusions and inferences drawn from the evidence are construed in the light most favorable to the nonmovant.

(Citations and punctuation omitted.) Iwan Renovations, Inc. v. North Atlanta Nat. Bank. 1

So viewed, the record shows that Newell is a corporation in the business of purchasing and processing scrap metal, which it then re-sells. In 1997, Newell contacted JJ&G about providing design and engineering services for a new automobile shredding facility it *295 wanted to build in Gwinnett County. After several meetings with representatives from Newell, JJ&G prepared a proposal for the project, titled “Draft Scope of Work[:] Newell Recycling of Atlanta[,] New Site — Duluth, Georgia,” and forwarded the same to Newell on August 15, 1997. 2 (Emphasis in original.) The Draft Scope of Work outlined six different project phases that JJ&G proposed to work on and attached thereto was a detailed, five-page task list related to the first project phase, environmental site assessment. The cover letter that JJ&G sent to Newell with these documents explained:

We are enclosing a draft Scope of Work which [we] feel addresses our environmental assessment and permitting needs as well as facilities planning/design and bidding/ construction phase needs for the New Recycling Facility in Duluth. We welcome your input ... to ensure that we have covered all the bases. While you are reviewing this Scope of Work for completeness, we will be developing a budget estimate.

On August 22,1997, JJ&G sent Newell a second letter, providing them with a cost estimate for the first three project phases outlined in the Draft Scope of Work. The letter further stated:

The [cost of the] remaining 3 [phases] can not be accurately estimated until some definition of your proposed facilities can be developed and a site visit of the existing buildings and features can be arranged. We would propose to perform this work on an hourly bases [sic] and would only bill you for completed task.

Representatives of Newell and JJ&G thereafter met several times to discuss and plan the details of the new facility and the engineering services that JJ&G would provide in connection with the project. By the spring of 1998, the parties had verbally agreed that there would be concrete pavement around the shredding machine to act as a work platform and to control drainage. JJ&G, therefore, developed a design for these pavements, which specified sub-grade *296 preparation, concrete mix, and concrete thickness, and added this design to the site plans and specifications. Site construction began in the fall of 1998, with a firm other than JJ&G acting as the construction manager. During the course of construction, JJ&G made several revisions to the plans and specifications, including changes to the concrete pavement design. JJ&G made the last change to the concrete pavement design in June 1999, and completed all engineering work for such pavements by the end of July 1999. All engineering and construction work on the project was completed by the end of September 1999.

After the project was completed and the facility became operational, the concrete paving surrounding the shredder began to crack. In May 2000, Newell informed JJ&G that the concrete pavement was failing. Blaming that failure on alleged inadequacies in JJ&G’s design of the concrete pavement, Newell initiated the current litigation against JJ&G in August 2004. Newell’s complaint asserts a single claim for breach of contract, and alleges that “[b]y entering into the [cjontract with Newell to provide the design of the Project, JJ&G contracted to perform its required services with that degree of care, skill, and ability ordinarily expected of prudent design professionals and civil engineers under similar circumstances. . . .” The complaint sets forth nine alleged contractual breaches, and states that these acts

constitute [d] the performance of design professional services under the [cjontract with Newell in a manner which was in breach of said [cjontract because such services were below that degree of care, skill, and diligence commonly possessed [and] exercised by reasonably skillful and prudent design professionals in Georgia . . . under the same or similar circumstances and said breaches of the [cjontract with Newell constitute design professional negligence and malpractice.

To comply with the requirement of OCGA § 9-11-9.1, which applies to all claims for professional malpractice, Newell attached to its complaint the affidavit of an engineering expert.

JJ&G moved for summary judgment, arguing that Newell’s complaint asserted a claim for either professional malpractice, breach of an oral contract, or breach of a contract that was partly in writing and partly in parol, and that each of these claims was subject to a four-year statute of limitation. JJ&G argued that any contractual breach occurred either at the time the concrete paving was designed (June 1999) or when the engineering work on such paving was completed (July 1999), and that Newell was aware of the *297 problems with the concrete paving no later than May 2000. Thus, Newell’s failure to file suit until August 2004 meant that its claim was time-barred.

The trial court denied JJ&G’s summary judgment motion, finding: (1) that while a four-year statute of limitation applied to claims for legal

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Newell Recycling of Atlanta, Inc. v. Jordan Jones
Court of Appeals of Georgia, 2012
Newell Recycling of Atlanta, Inc. v. Jordan Jones & Goulding, Inc.
731 S.E.2d 361 (Court of Appeals of Georgia, 2012)
Saiia Construction, LLC v. Terracon Consultants, Inc.
714 S.E.2d 3 (Court of Appeals of Georgia, 2011)
Jordan, Jones & Goulding, Inc. v. NEWELL RECYCLING OF ATLANTA, INC.
710 S.E.2d 915 (Court of Appeals of Georgia, 2011)
Newell Recycling of Atlanta, Inc. v. Jordan Jones & Goulding, Inc.
703 S.E.2d 323 (Supreme Court of Georgia, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
682 S.E.2d 666, 299 Ga. App. 294, 2009 Fulton County D. Rep. 2673, 2009 Ga. App. LEXIS 878, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jordan-jones-goulding-inc-v-newell-recycling-of-atlanta-inc-gactapp-2009.