Jones v. Sharpe
This text of 99 A.D.2d 859 (Jones v. Sharpe) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinions
Appeals from a judgment of the Supreme Court in favor of plaintiff, entered February 28,1983 in Albany County, upon a decision of the court at Trial Term (Conway, J.), without a jury. Defendant contends that the trial court erred in finding defendant liable to plaintiff for the cost of certain repair work done by plaintiff on three different types of heat exchangers, which plaintiff had previously installed at the State University of New York at Stony Brook. The third-party defendant maintains that the trial court erred in imposing liability over against it on defendant’s third-party claim. We find ample evidence in the record to support the trial court’s findings and, therefore, affirm the judgment. Pursuant to a contract with defendant, entered into in the fall of 1973, plaintiff agreed to install a high temperature hot water distribution system at the Stony Brook campus. The third-party defendant (engineer), primarily a firm of mechanical engineers, was engaged by plaintiff to provide the professional services necessary to complete the design and construction of the project. The system required three types of heat exchangers, which used high temperature hot water produced by a centralized boiler, to generate steam, hot water for heating purposes and hot water for domestic needs. The engineer’s design manual originally specified that the heat exchangers be manufactured by Aereo or an approved equivalent, but at defendant’s request, two other manufacturers were specified as acceptable, including Taylor, from which plaintiff ultimately obtained the equipment. After plaintiff accepted Taylor’s bid on the heat exchangers, Taylor submitted shop drawings of the equipment, which the engineer disapproved, and revised shop drawings were thereafter submitted and approved by the engineer. Plaintiff installed the sealed units as they were delivered to the job site by Taylor. Defendant accepted the completed work in January, 1976, and shortly thereafter directed plaintiff to repair all of the Taylor units, a substantial number of which had developed leaks. Plaintiff did so and commenced the instant action when defendant refused to pay for the repairs. Defendant impleaded the engineer. Based upon the testimony of [861]*861plaintiff’s expert, the trial court found that the sole proximate cause of the leaks in the Taylor units was the use of “non-compatible metals” for the internal parts. Plaintiff’s expert explained that the use of unprotected dissimilar metals resulted in a galvanic corrosion mechanism that virtually guaranteed leakage. He further opined that the selection of such materials was “a design failure” and was “strongly in violation of good practice”. Contrary to defendant’s argument, the trial court’s conclusion which relieved plaintiff of any responsibility for the leakage was not against the weight of the evidence. As noted above, the manufacturer with which plaintiff dealt was one of those specifically approved by the engineer, and the manufacturer’s shop drawings were ultimately approved by the engineer. When delivered to the job site, the units were sealed, and there is evidence in the record that the manufacturer’s warranty
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
99 A.D.2d 859, 472 N.Y.S.2d 779, 1984 N.Y. App. Div. LEXIS 17273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-v-sharpe-nyappdiv-1984.