Jones v. Celotex Corp.

683 F. Supp. 555, 1987 U.S. Dist. LEXIS 10160, 1987 WL 45317
CourtDistrict Court, E.D. Louisiana
DecidedOctober 30, 1987
DocketCiv. A. No. 85-0491
StatusPublished
Cited by2 cases

This text of 683 F. Supp. 555 (Jones v. Celotex Corp.) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Jones v. Celotex Corp., 683 F. Supp. 555, 1987 U.S. Dist. LEXIS 10160, 1987 WL 45317 (E.D. La. 1987).

Opinion

ROBERT F. COLLINS, District Judge.

Defendants, Celotex Corporation (Celo-tex) and Aetna Casualty and Surety Company (Aetna), have moved the Court for Judgment Notwithstanding the Verdict or, in the alternative, for a new trial in the [556]*556above captioned case. For the following reasons, that motion is GRANTED.

Facts

This matter was tried on March 30, 1987 before a jury. The jury returned a verdict in favor of plaintiff and against defendants. They found Celotex to be negligent and awarded damages of $670,000.00 to plaintiff. The Court adopted the verdict of the jury and entered judgment. Defendants now argue that there was insufficient evidence by which the jury could reasonably reach their verdict and pray that the Court grant their Motion for Judgment Notwithstanding the Verdict.

The following facts are undisputed by the parties. Celotex is the owner and operator of a manufacturing plant located in Marrero, Louisiana. Plaintiff, Edward G. Jones (Jones), was an employee of Salvage One Demolition Company, Inc. a/k/a Southern States Demolition Company, Inc. (Salvage One). Salvage One contracted with Celotex to demolish certain buildings at the aforementioned location. On or about September 17, 1984, plaintiff was working inside a structure identified at trial as “Dryer Building No. 1.” At that time, plaintiff was in the process of dismantling a self contained dryer unit, commonly called an “oven”, and was cutting steel beams which spanned the top of the oven. As each beam was cut, it was allowed to fall free, but was restricted from total collapse due to restrictions imposed by a beam-to-girder connection at the opposite wall of the oven. After an undetermined number of the steel beams had been cut, the added weight and stress imposed on the wall which supported the beams caused the structure to collapse. This in turn caused plaintiff to fall and sustain injuries and damages. During the trial, plaintiff attempted to show that Celo-tex controlled the method and means by which Salvage One performed its job. Cel-otex, on the other hand, produced evidence to prove that Salvage One carried out its function as an independent contractor and made all material decisions as to how the buildings would be demolished.

Law

The Court has jurisdiction over this action by virtue of the diversity of citizenship between the parties. 28 U.S.C. § 1332. In diversity actions, the trial court must apply a federal rather than a state test for the sufficiency of evidence to create a jury question. Foster v. Ford Motor Co., 616 F.2d 1304 (5th Cir.1980). The case of Boeing Co. v. Shipman, 411 F.2d 365 (5th Cir.1969) sets out the applicable standard.

“On motions for directed verdict and for judgment notwithstanding the verdict the Court should consider all of the evidence — not just that evidence which supports the non-mover’s case — but in the light and with all reasonable inferences most favorable to the party opposed to the motion. If the facts and inferences point so strongly and overwhelmingly in favor of one party that the Court believes that reasonable men could not arrive at a contrary verdict, granting of the motions is proper. On the other hand, if there is substantial evidence opposed to the motions, that is, evidence of such quality and weight that reasonable and fair-minded men in the exercise of impartial judgment might reach different conclusions, the motions should be denied, and the case submitted to the jury. A mere scintilla of evidence is insufficient to present a question for the jury. The motions for directed verdict and judgment n.o.v. should not be decided by which side has the better of the case, nor should they be granted only when there is a complete absence of probative facts to support a jury verdict. There must be a conflict in substantial evidence to create a jury question.”

411 F.2d at 374, 375. Quite simply, the Court must decide whether reasonable minds could not differ as to the issues presented in the case, so that a jury question does not exist. It is a stringent standard and reflects the general policy that trial judges should rarely take issues away from juries or upset their verdicts. In re Letterman Bros. Energy Securities Litigation, 799 F.2d 967, 972 (5th Cir.1986). A judge’s decision to enter judgment notwith[557]*557standing a jury verdict is not a matter of discretion, but a conclusion of law based upon a finding that there is insufficient evidence to create a fact question for the jury. Lubbock Feed Lots, Inc. v. Iowa Beef Processors, Inc., 630 F.2d 250, 269 n. 22 (5th Cir.1980).

Operational Control

It is a fundamental principal of tort law that one who employs an independent contractor is not responsible for his actions if he simply gives the contractor plans for the job without specifying the method. If the principal exerts no control over the operations, he will not be liable to third persons who may be injured through fault of the contractor or his employees. Daroca v. Metropolitan Life Insurance Company, 121 F.2d 917 (5th Cir.1941); Stoute v. Mobile Oil Corp., 297 So.2d 276 (La.App. 3rd Cir.1974); Matthews v. Southern Amusement Company, 199 So.2d 403 (La.App. 3rd Cir.1967); Henson v. Travelers Insurance Company, 208 So.2d 366 (La.App. 1st Cir.1968).

The jury was properly instructed that in order to impose any liability upon defendant, plaintiff must prove that defendant actually controlled the method and means by which the demolition operation was conducted. Stoute v. Mobil Oil Corp., 297 So.2d 276. This burden of proof is basically the linchpin by which liability can be imposed on Celotex. In his attempt to meet this burden, plaintiff produced several witnesses to reconstruct the chain of events leading up to plaintiffs accident. Their testimony established the following facts.

Celotex and Salvage One entered into a contract for the demolition of ten buildings and various machinery. Under that agreement, Salvage One was to

“Furnish all supervision, labor, materials, tools, equipment, hauling, taxes, permits, license and all things necessary unless otherwise excepted to complete the demolition work as described below, at the Celotex Corporation, Marrero, Louisiana, Plant.”

Plaintiffs Exhibit 12.

Celotex was responsible for disconnecting electric lines and shutting off water and gas pipe lines prior to the start of demolition. All debris and salvageable materials were to be disposed of at an offsite location, and the contractor was to leave the demolished premises free of all debris and in a broom-clean condition upon completion of the contract.

On the reverse of the contract, it was also provided that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Celotex
857 F.2d 273 (Fifth Circuit, 1988)
Jones v. Celotex Corp.
857 F.2d 273 (Fifth Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
683 F. Supp. 555, 1987 U.S. Dist. LEXIS 10160, 1987 WL 45317, Counsel Stack Legal Research, https://law.counselstack.com/opinion/jones-v-celotex-corp-laed-1987.