Joint Venture of Domenech, Hicks & Krockmalnic v. Massachusetts Housing Finance Agency

25 Mass. L. Rptr. 396
CourtMassachusetts Superior Court
DecidedMay 27, 2009
DocketNo. SUCV200805618E
StatusPublished

This text of 25 Mass. L. Rptr. 396 (Joint Venture of Domenech, Hicks & Krockmalnic v. Massachusetts Housing Finance Agency) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joint Venture of Domenech, Hicks & Krockmalnic v. Massachusetts Housing Finance Agency, 25 Mass. L. Rptr. 396 (Mass. Ct. App. 2009).

Opinion

Macdonald, D. Lloyd, J.

The plaintiff here is the Joint Venture of Domenech, Hicks and Krockmalnic and Hezekiah Pratt Associates, Inc. (“Plaintiff’). Before the Court is the Plaintiffs Application for an Order Vacating the Arbitration Award pursuant to G.L.c. 251, §§12(3) and 12(5). The essence of the Plaintiffs claim is that the defendant Massachusetts Housing Finance Agency (“MHFA”) is not the real party in interest to the agreement underlying the dispute as required by Mass.R.Civ.P. 17(a). The MHFA opposes the application and has moved under G.L.c. 231, §6F for fees and costs incurred in doing so. The MHFA alleges that the application is insubstantial and frivolous. The Court DENIES the Plaintiffs application and ALLOWS MHFA’s cross-application and its 231, §6F request.

Background

The Plaintiff is a joint venture entity comprised of two architectural firms. The dispute arises from an agreement (the “Agreement”) between the Plaintiff and the MHFA in its capacity as Interim Asset Manager for the United States Department of Housing and Urban Development (“HUD”). The Agreement is one for architectural and related services in connection with the construction of an affordable housing project in Boston known as Camfield Gardens (the “Project”). The Agreement contained the following arbitration clause:

Claims, disputes, or other matters in question between the parties to this Agreement arising out of or relating to this Agreement or breach thereof shall be subject to and decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association currently in effect unless the parties mutually agree otherwise.

After what appears to have been substantial completion of the Project, the MHFA complained of the quality of the Plaintiffs services. The parties initially executed a tolling agreement and attempted to settle the dispute. However, in November 2003 the MHFA filed a Demand for Arbitration pursuant to the Agreement’s arbitration clause. The Demand asserted claims for breach of contract, breach of implied and express warranties and negligence in connection with the design and contract administration of the Project.

The Plaintiff responded with its Answering Statement and Counterclaim. The Plaintiffs response did not include any objection to the MHFA’s standing to bring the claim as a real party in interest to the arbitration agreement.

Apparently at a glacial pace, the arbitration proceeding thereafter moved forward, and it wasn’t until March 2008 that a pre-hearing conference was held. The Plaintiff made no objection to the MHFA’s real party in interest standing at that time, either.

The arbitration hearings began on May 28, 2008 and continued for eleven separate days through August 4, 2008. The details are not important, but the MHFA’s claims were comprised of what the parties generically referred to as the “Round I” and “Round II” claims.

On the first day of testimony on May 29, 2008, the Plaintiff filed a Motion to Dismiss or Preclude Evidence of MHFA’s so-called “Round II” claims. The motion was predicated in part on a challenge to the MHFA’s standing on account of the MHFA having allegedly assigned its interests implicated by the Round II claims to the Camfield Tenants Association. The arbitrator denied the Plaintiffs motion.

[397]*397Approximately a month later, the Plaintiff filed a Motion for a Directed Award claiming for the first time as to the Round I claims that the real party in interest was HUD and that because HUD was not a party to the Agreement the MHFA could not compel the Plaintiff to arbitrate claims that properly belonged to HUD. In July, the Arbitrator heard arguments on the motions. By letter dated July 23, 2008, the Arbitrator denied the Plaintiffs motion.

On November 19, 2008, the Arbitrator issued the award. The Arbitrator awarded MHFA all of the damages it sought with respect to the Round I claims ($603,887) but denied any damages to the MHFA on the Round II claims. The Arbitrator also denied the Plaintiffs counterclaim. The arbitrator further denied MHFA’s request for attorneys fees or prejudgment interest.

Legal Standards

A. Scope of Review

“The role of courts in reviewing an arbitrator’s award is limited.” Concerned Minority Educators of Worcester v. School Comm. of Worcester, 392 Mass. 184, 187 (1984). A court is “strictly bound by an arbitrator’s findings and legal conclusions, even if they appear erroneous, inconsistent, or unsupported by the record at the arbitration hearing.” City of Lynn v. Thompson, 435 Mass. 54, 61 (2001). Courts are not permitted to review errors of law or fact or overrule an arbitrator based on a different interpretation of a contract. See Concerned Minority Educators of Worcester, 392 Mass. at 187-88. Absent fraud, a court’s review is limited to whether the arbitrator exceeded the scope of reference or awarded relief in excess of his authority. School Committee of Waltham v. Waltham Educators Ass'n, 398 Mass. 703, 705-06 (1986).

Further, under both Massachusetts and federal law, an arbitrator may properly decide issues that are procedural in nature. Mass. Highway Dep’t v. Perini Corp., 444 Mass. 366, 377 (2005), quoting Howsam v. Dean Witter Reynolds, Inc., 537 U.S. 79, 85 (2002) (procedural questions include “time limits, notice, la-ches, estoppel, and other conditions precedent to an obligation to arbitrate” [emphasis omitted]). Indeed, “(o]nce it is determined . . . that the parties are obligated to submit the subject matter of a dispute to arbitration, ‘procedural’ questions which grow out of the dispute and bear on its final disposition should be left to the arbitrator”). Bedford v. AFSCME, 69 Mass.App.Ct. 110, 112 (2007), quoting John Wiley & Sons v. Livingston, 376 U.S. 543, 557 (1964). Moreover, “(o]nly those contracts with arbitration clauses that expressly preclude arbitrators from deciding . . . procedural disputes will support judicial intervention”). Mass. Highway Dep’t, 444 Mass. at 376, n.11.

The limited scope of review reflects the Commonwealth’s longstanding strong public policy favoring arbitration. Superadio Ltd. Partnership v. Winstar Radio Prods., LLC, 446 Mass. 330, 333 (2006).

B. G.L.c. 251, §12(3) and §12(5)

General Laws chapter 251 §12(3) and §12(5) provides that “[u]pon application of a party, the court shall vacate an award if . . . (3) the arbitrators exceeded their powers . . . [or] (5) there was no arbitration agreement and the issue was not adversely determined in proceedings under section two and the party did not participate in the arbitration hearing without raising the objection; but the fact that the relief was such that it could not or would not be granted by a court of law or equity is not ground for vacating or refusing to confirm the award.” G.L.c. 251, §12(3) and (5). The court will uphold an arbitrator’s award even where the performance of the contract which contained the arbitration clause is deemed illegal. See Lawrence v. Falzarano, 380 Mass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John Wiley & Sons, Inc. v. Livingston
376 U.S. 543 (Supreme Court, 1964)
Thorpe v. Housing Authority of Durham
393 U.S. 268 (Supreme Court, 1969)
Howsam v. Dean Witter Reynolds, Inc.
537 U.S. 79 (Supreme Court, 2002)
School Committee of Waltham v. Waltham Educators Ass'n
500 N.E.2d 1312 (Massachusetts Supreme Judicial Court, 1986)
City of Lawrence v. Falzarano
402 N.E.2d 1017 (Massachusetts Supreme Judicial Court, 1980)
CONCERNED MIN. EDUCATORS v. Sch. Comm. of Worcester
466 N.E.2d 114 (Massachusetts Supreme Judicial Court, 1984)
City of Lynn v. Thompson
754 N.E.2d 54 (Massachusetts Supreme Judicial Court, 2001)
Massachusetts Highway Department v. Perini Corp.
444 Mass. 366 (Massachusetts Supreme Judicial Court, 2005)
Superadio Ltd. Partnership v. Winstar Radio Productions, LLC
844 N.E.2d 246 (Massachusetts Supreme Judicial Court, 2006)
Town of Watertown v. Watertown Municipal Employees Ass'n
825 N.E.2d 572 (Massachusetts Appeals Court, 2005)
Town of Bedford v. AFSCME Council 93, Local 1703
866 N.E.2d 936 (Massachusetts Appeals Court, 2007)
Housing Authority of Bluefield v. Boggess
233 S.E.2d 740 (West Virginia Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
25 Mass. L. Rptr. 396, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joint-venture-of-domenech-hicks-krockmalnic-v-massachusetts-housing-masssuperct-2009.