Johnson's Wholesale Plumbing, Inc. v. Holloway
This text of 563 P.2d 1294 (Johnson's Wholesale Plumbing, Inc. v. Holloway) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinions
Appellant, Johnson's Wholesale Plumbing, Inc., brought an action to foreclose a materialman's lien. Appellant was granted a summary judgment against two defendants,1 but the trial court granted NuWestern American, Inc.'s2 motion to dismiss at the end of appellant's case and entered findings of fact and conclusions of law and a judgment in accordance therewith; this appeal followed. The sole issue is whether the notice requirement of RCW 60.04.020 applies to the material shipped after a telephone conversation with the general contractor, i.e., was that a, specific order by the owner? The trial court found there was no such order. We affirm.
NuWestern American, Inc. (NuWestern), the owner, contracted to have American Contracting and Design, Inc., build an apartment house in Spokane. Patrick R. Jeppesen owned almost all the stock of American Contracting and Design, Inc., and was a 25 percent stockholder and a director of NuWestern. One of the subcontractors, Tilman O. Holloway and his wife, d/b/a Joleda Plumbing & Heating [451]*451(Joleda), had ordered from appellant materials to be used in the construction of the apartment house project. Appellant began shipping the materials on November 15, 1970, but did not give any notice to NuWestern until October 4, 1971. Cf. RCW 60.04.020. Appellant stopped shipment to Joleda in May 1971 for failure to receive payment for prior deliveries. When the goods failed to arrive, inquiry was made by an employee of Joleda. After several telephone conversations, Jeppesen talked directly to appellant's credit manager; after some discussion, Jeppesen assured appellant that payment for Joleda's materials would be no problem. Jeppesen testified that this assurance of payment was based upon his belief that there was sufficient retainage withheld from Joleda's contract to cover the cost of these materials. Appellant renewed the shipments to Joleda and billed Joleda for the cost of the materials. Although Joleda was later paid in full, appellant was never paid for the goods shipped subsequent to the telephone conversation. Appellant then sued NuWestern under the lien statute (RCW 60.04), recognizing that it had not met the statutory notice requirement but contending that Jeppesen's conversation constituted an order by NuWestern to appellant for the goods.
Any right arising as part of a materialman's lien is a statutorily created right and will be strictly construed. Dean v. McFarland, 81 Wn.2d 215, 500 P.2d 1244 (1972); Westinghouse Elec. Supply Co. v. Hawthorne, 21 Wn.2d 74, 150 P.2d 55 (1944); De Gooyer v. Northwest Trust & State Bank, 130 Wash. 652, 228 P. 835 (1924). Generally, in order to claim the remedies under the materialman's lien statute, a materialman supplying materials to be used in the construction of a building must give written notice to the owner of that building that he is supplying such materials and that he intends to claim a lien. RCW 60.04.020. Appellánt correctly asserts that an exception to this general rule exists if the owner or his agent orders the materials from the materialman. Hayes v. Gwinn, 49 Wn.2d 908, 307 P.2d 1063 (1957); Brace & Hergert Mill Co. v. Burbank, 87 [452]*452Wash. 356, 151 P. 803 (1915).3 In findings of fact properly challenged by the appellant, the trial court found (1) although Jeppesen did orally assure appellant a portion of Joleda's account would be paid if Joleda failed to pay it, the appellant "consistently sold, invoiced and delivered" its materials to Joleda; and (2) neither Jeppesen, NuWestern, American Contracting and Design, Inc., nor any of their agents had at any time ordered or purchased any materials or fixtures from appellant. These findings were supported by substantial evidence and are not subject to review or revision by this court. Thorndike v. Hesperian Orchards, Inc., 54 Wn.2d 570, 343 P.2d 183 (1959).
Appellant next contends that the effect of the phone conversation with Jeppesen was to establish an independent contract between appellant and NuWestern for the value of the goods delivered. Appellant acknowledges that a promise to pay the debt of another is within the statute of frauds (RCW 19.36.010), but argues that this conversation constituted a direct contract between the parties. Appellant explicitly relies upon R.H. Freitag Mfg. Co. v. Boeing Airplane Co., 55 Wn.2d 334, 347 P.2d 1074 (1959). The trial court found to the contrary in finding of fact No. 4. That finding is supported by substantial evidence. Appellant, recognizing this possible consequence, seeks to have this court find an implied contract to purchase. Ross v. Raymer, 32 Wn.2d 128, 201 P.2d 129 (1948). It does not appear that this issue was raised at the trial court level and thus cannot [453]*453be considered on appeal. Matthias v. Lehn & Fink Prods. Corp., 70 Wn.2d 541, 424 P.2d 284 (1967).
Notwithstanding the above, the appellant has assigned error to the conclusion that he is "not entitled to have a lien imposed on the property of NuWestern American, Inc." Finding of fact No. 2, to which no error has been assigned, states that the last delivery by the appellant was made on August 16, 1971, and that the first written notice of delivery of materials was given on October 4, 1971. RCW 60.04.020 states in part:
[A] notice in writing, which notice shall cover the material, supplies or equipment furnished . . . during the sixty days preceding the giving of such notice as well as all subsequent materials, . . .
Appellant's answers to NuWestern's interrogatories, as found on page 55 of the first supplemental transcript, contain two invoices, one dated August 5, 1971, in the amount of $1,727.36, and another dated August 16, 1971, in the amount of $341.81. Both invoices are dated within the statutory period of "sixty days preceding the giving of such notice" and, at least prima facie, indicate that conclusion of law No. 4 may be in error as to that $2,069.17. Cf. Building Supplies, Inc. v. Gillingham, 17 Wn.2d 489, 135 P.2d 832 (1943). However, the record does not indicate whether these goods were shipped on the days of the billing or prior thereto.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
563 P.2d 1294, 17 Wash. App. 449, 1977 Wash. App. LEXIS 1592, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnsons-wholesale-plumbing-inc-v-holloway-washctapp-1977.