Johnson v. Whitman

463 P.2d 207, 1 Wash. App. 540, 1969 Wash. App. LEXIS 367
CourtCourt of Appeals of Washington
DecidedDecember 22, 1969
Docket51-40377-1
StatusPublished
Cited by22 cases

This text of 463 P.2d 207 (Johnson v. Whitman) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Whitman, 463 P.2d 207, 1 Wash. App. 540, 1969 Wash. App. LEXIS 367 (Wash. Ct. App. 1969).

Opinion

Swanson, J.

Defendant, E. Dale Whitman, headmaster and private elementary school proprietor, decided to build *541 a new schoolhouse. He consulted with the plaintiff, Harvey H. Johnson, a professional engineer, and asked for his services in designing the building. After Whitman assured Johnson that he had the money to construct the school, the parties entered into a written contract on February 13, 1963. The contract established Johnson’s compensation in this manner:

Basic fee 6% of market cost. Market cost to be arrived at as total actual cost including labor (excluding owner’s labor), material, equipment rental, and subcontracts, plus 25% for owner’s services as general contractor, expeditor and such labors as he performs himself.

The school was not built. Johnson sued for and obtained a judgment for his fees.

The court found that Johnson completed the work required of him under the contract in a highly skillful and professional manner. Through no fault of plaintiff, the contemplated improvements were never placed on defendant’s property. Johnson submitted statements of account to the defendant Whitman for the preliminary drawings and for portions of the working drawings. A final bill dated December 27, 1963, was sent. In 1964, the parties met on several occasions, but the first time the defendant questioned the amount due for plaintiff’s services was on January 28, 1965, when he wrote the plaintiff and referred to the “still undetermined balance.” No error is assigned to these findings, and they become the accepted facts on appeal. CAROA 43; Pier 67, Inc. v. King County, 71 Wn.2d 92, 426 P.2d 610 (1967).

Defendant’s assignments of error 1 and 5 are to quoted portions of the trial court’s oral opinion. Such statements are not rulings which can be appealed or assigned as error. A trial court’s oral opinion is only an indication of the court’s views or thinking, and does not become final until or unless it is incorporated in written findings or conclusions of law. Ferree v. Doric Co., 62 Wn.2d 561, 383 P.2d 900 (1963); Dillenburg v. Maxwell, 70 Wn.2d 331, 413 P.2d 940, 422 P.2d 783 (1966). The second assignment of error challenges the court’s finding that reasonable com *542 pensation for the professional work of plaintiff and his associates is $9,308. This assignment is without merit. The finding is supported by substantial evidence in the record and will not be disturbed. Thorndike v. Hesperian Orchards, Inc., 54 Wn.2d 570, 343 P.2d 183 (1959); United Pac. Ins. Co. v. Lundstrom, 11 W.D.2d 157, 459 P.2d 930 (1969).

The remaining assignments of error 3, 4 and 6 challenge the basis of plaintiff’s recovery. First, defendant claims the contract was contingent upon the happening of a condition precedent—obtaining financing. Thus, since financing was not obtained and the building not constructed, the condition precedent was not satisfied.

If this contract was contingent upon Whitman obtaining financing, this court need go no further. The contingent nature of the contract is apparent, Whitman says, from the plain language of the agreement making “Q% of actual cost” the only basis of compensation to Johnson. The trial court concluded otherwise, 1 and we agree. A review of the record discloses Johnson’s testimony with regard to the matter of financing:

Q Now, prior to your signing the contract do you recall any conversation with Whitman regarding the subject of financing for the contemplated structures? A Yes. Q What in general would you recall was said? A Well, I asked him about this, this was a substantial venture for an individual to undertake, and I asked him specifically if he did have the ability to pay for it and build it, and he said he did. He had not at that time, did not elaborate where the funds were to come from or anything else. He assured me that he did have the funds to complete the project.

The defendant Whitman testified on the same subject as follows:

Q . . . And did you have any conversations with *543 Johnson prior to the signing of the contract referable to what would, happen if financing fell through? A No.
Q Now at any time prior to the time you did give up, did you ever tell Johnson that he wasn’t going to be able to be paid if you couldn’t get financing? A No. No, I don’t think that ever came up.

There is substantial evidence by both parties on which the trial court properly concluded that plaintiffs compensation was not contingent upon defendant obtaining financing.

Second, Whitman challenges plaintiff’s recovery by arguing it is improperly based on quantum meruit, or implied contract. Defendant contends the written contract, which the court concluded was valid and enforceable, provided for a fee if the building was constructed, but was silent as to compensation if the school was not built. Defendant argues that since the school was not built, the express contract contains no provision for compensation and precludes any recovery. Under such circumstances, none can be allowed, defendant says, on the basis employed by the trial court.

Arguably, statements in the trial court’s oral opinion support defendant’s position that recovery was on the basis of quantum meruit:

The Court is of the opinion that under the rules of civil procedure and the authorities in the State of Washington that an action of contract such as this is also a proceeding in equity and that under the theory of quantum meruit —the Latin expression we have all bandied about in the courtroom—that one party to a proceeding may not be enriched at the expense of another party to a proceeding who is himself not at fault.

Defendant relies upon a proposition stated in Chandler v. Washington Toll Bridge Authority, 17 Wn.2d 591, 604, 137 P.2d 97 (1943), that:

A party to a valid express contract is bound by the provisions of that contract, and may not disregard the same and bring an action on an implied contract relating to the same matter, in contravention of the express contract.

*544 A close examination of Chandler shows it to be inapposite. The plaintiff in that case, by an express contract, agreed to furnish certain engineering services to Pierce County and certain franchise holders, contingent upon the county’s ability to finance the project. Financing was not obtained, and the contract terminated. A newly created agency of state government used his work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Leslie Tullis v. Golden Tullis
Court of Appeals of Washington, 2020
State of Washington v. John Mark Hamilton
Court of Appeals of Washington, 2017
In re the Welfare of: R.L.
Court of Appeals of Washington, 2015
Rekhter v. Dep't of Soc. & Health Servs.
Washington Supreme Court, 2014
Rekhter v. Department of Social & Health Services
323 P.3d 1036 (Washington Supreme Court, 2014)
Mogavero v. Silverstein
790 A.2d 43 (Court of Special Appeals of Maryland, 2002)
State v. Reynolds
912 P.2d 494 (Court of Appeals of Washington, 1996)
Mairs v. Department of Licensing
854 P.2d 665 (Court of Appeals of Washington, 1993)
Bennion v. Hansen
699 P.2d 757 (Utah Supreme Court, 1985)
Penberthy Electromelt International, Inc. v. United States Gypsum Co.
686 P.2d 1138 (Court of Appeals of Washington, 1984)
Sweeten v. Kauzlarich
684 P.2d 789 (Court of Appeals of Washington, 1984)
Eaton v. Engelcke Manufacturing, Inc.
681 P.2d 1312 (Court of Appeals of Washington, 1984)
Washington Ass'n of Child Care Agencies v. Thompson
660 P.2d 1129 (Court of Appeals of Washington, 1983)
Wolf v. Department of Motor Vehicles
616 P.2d 688 (Court of Appeals of Washington, 1980)
Barros v. Barros
613 P.2d 547 (Court of Appeals of Washington, 1980)
Steed v. Busby
593 S.W.2d 34 (Supreme Court of Arkansas, 1980)
Diel v. Beekman
499 P.2d 37 (Court of Appeals of Washington, 1972)
Peterson v. Peterson
475 P.2d 576 (Court of Appeals of Washington, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
463 P.2d 207, 1 Wash. App. 540, 1969 Wash. App. LEXIS 367, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-whitman-washctapp-1969.