Johnson v. Detroit Edison Co.

795 N.W.2d 161, 288 Mich. App. 688
CourtMichigan Court of Appeals
DecidedJune 15, 2010
DocketDocket No. 289763
StatusPublished
Cited by24 cases

This text of 795 N.W.2d 161 (Johnson v. Detroit Edison Co.) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson v. Detroit Edison Co., 795 N.W.2d 161, 288 Mich. App. 688 (Mich. Ct. App. 2010).

Opinion

PER CURIAM.

This action requires us to determine whether plaintiffs, Sandra Johnson and Hiram Jones, proffered sufficient circumstantial evidence that defendant, Detroit Edison Company, committed an intentional tort under the exception to the exclusive remedy of the Worker’s Disability Compensation Act (WDCA) found in MCL 418.131(1). For the purpose of summaiy disposition, we conclude that plaintiffs met their burden. Specifically, we hold that a jury may conclude that an employer knew an injury was “certain to occur” under MCL 418.131(1) if a plaintiff can show that (1) the employer subjected the plaintiff to a continuously operative dangerous condition that it knew would cause an injury, (2) that the employer knew that its employees were taking insufficient precautions to protect themselves against that danger, and (3) that the employer did nothing to remedy the situation. The trial court properly denied defendant’s motion for summaiy disposition under MCR 2.116(0(10).

I. BASIC FACTS

At the time relevant to this lawsuit, plaintiffs were employed as power plant operators by Detroit Edison Company. In this capacity, plaintiffs were required to dump bottom ash from four industrial furnaces, or boilers, including Boiler No. 19 (Boiler 19). The boilers’ byproducts, including hot ash and unbumed coals, were typically emptied once a day. An operator would open the boiler’s ash gate, and the ash would fall through a sluice trough and be carried away by running water. If, after opening the boiler’s ash gate, large coals, or “clinkers,” remained, the operator would be required to break them loose with a long poker in order to sufficiently clear the boiler. Employees engaged in bottom-ash dumping were required to wear safety glasses, hardhats, earplugs, cotton gloves, jeans, a shirt, and work shoes.

[691]*691On April 28, 2007, plaintiffs were in the process of emptying bottom ash from Boiler 19 when hot ash exploded from it and covered plaintiffs. Johnson suffered serious burns, and Jones suffered minor ones. Plaintiffs then brought this action, alleging that defendant was liable under the intentional tort exception to the WDCA’s exclusive-remedy provision.

At her deposition, Johnson testified that at the time of the incident, two of Boiler 19’s five ash gates, Nos. 2 and 3, had been broken for several months to a year and that some of the doors’ seams were corroded and could not be closed all the way.1 According to Johnson and other employees, this caused ash to build up behind the improperly operating gates, which would then tumble over to the gates that operated properly and build up there as well; this buildup would cause a blowout, or explosion, of ash through any opening, including the defective boiler doors, which would be forced open. Johnson testified that employees regularly suffered minor “prickly” burns because of the mist of hot-ash spew that would cover them as they operated the boilers and that operators regularly ran from the boilers to avoid getting burned. Johnson indicated that she suffered a burn injury from operating a broken boiler in 1999 or 2000 that was reported to management. According to Johnson, in 2004 or 2005, one of her coworkers also had to be hospitalized for a burn injury he received as a result of a hot-ash spew from Boiler 19.

Johnson further testified that, before the incident, she and other employees had expressed concerns regarding the broken ash gates to management on numerous occasions at preshift meetings, that she had had [692]*692individual discussions with Daniel Braker and Mary Webb, plant manager and production manager, respectively, regarding the safety issues caused by the broken boiler doors, and that she had also specifically told her shift supervisor, Melvin Werner, that Boiler 19’s ash gates were broken. In addition, Johnson had informed Webb of an injury she suffered in 2006 when the corroded seams of a boiler caused ash to blow into her eye and she had to go to the hospital. Thereafter, Johnson and other employees, at Webb’s request, showed Webb and other members of management the safety problems in the ash-dumping process. According to Johnson, management acknowledged the dangers associated with the broken boilers, but later explained that there was no money to fix the problem.

John Bost, defendant’s union field-safety specialist, testified that he received many complaints from plant operators regarding the safety issues associated with bottom-ash dumping, that he had seen operators run from hot-ash spews on multiple occasions, and that it was common knowledge to anyone in the plant that the boilers were broken and in need of repair. He informed management of these complaints at least a year before plaintiffs’ injuries. Bost indicated that these problems were addressed in a Plant Safety Committee2 meeting before the April 2007 incident, at which it was discussed how to repair the system and also how to complete the job in a safer manner. According to Bost, management agreed that something had to be done, but indicated that the repairs were not in the budget. Bost also noted that repairs for boilers were to be made only in the event of an outage, i.e., when the system was “offline.” Bost [693]*693testified that such an outage occurred a month before the incident, but Boiler 19’s broken doors were not repaired at that time.

Edward Wacasey, another of defendant’s plant operators, participated in the Plant Safety Committee meeting. Wacasey performed a demonstration for management, showing them the broken condition of the boilers, how ash would puff, and how employees attempted to break up clinkers with long rods. According to Wacasey, defendant’s fuel supply manager, Tara Daly, told him, after viewing the demonstration, that she would not do bottom-ash dumping because it was too dangerous. Wacasey made numerous recommendations for safer operation, including fixing the boilers, squirting water into the boilers from a safer distance, and wearing safer apparel, including face shields and high-cutoff gloves, but management did not adopt any of these measures. Notes from the meeting corroborated Wacasey’s deposition testimony that management knew that Boiler 19 was in disrepair and that the hazards of the job included hot material flying out of the boiler.

Defendant’s plant manager, Braker, averred that he was not familiar with bottom-ash dumping and was unaware of any complaints related to it. He indicated that he was also not aware of any prior serious injuries related to bottom-ash dumping. Webb attested that she was aware of Johnson’s prior eye injury related to bottom-ash dumping. Webb, however, indicated that she believed bottom-ash dumping to be safe, on the basis of her conversations with shift supervisors. Plaintiffs’ immediate supervisor on the day of the incident, Douglas Struble, also attested that he did not believe the condition of Boiler 19 to be unsafe.

Defendant moved for summary disposition under MCR 2.116(0(10). The trial court denied defendant’s motion under the following reasoning:

[694]*694As I understand TRAVIS [v Dreis & Krump Mfg Co, 453 Mich 149; 551 NW2d 132 (1996)], the only way for the plaintiff[s] to maintain the tort action is if the facts that plaintiff[s] plead make out actual knowledge on the part of the employer that an injury was certain to occur that the employer willfully disregarded.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Neil Nyber v. City of Battle Creek
Michigan Court of Appeals, 2026
20250218_C366945_38_366945.Opn.Pdf
Michigan Court of Appeals, 2025
20241127_C365607_49_365607.Opn.Pdf
Michigan Court of Appeals, 2024
Luanne Kozma v. Scott Law
Michigan Court of Appeals, 2024
Rogelio Ruiz v. Benteler Automotive Corp
Michigan Court of Appeals, 2024
Jonathan Roach v. Detroit Community Schools
Michigan Court of Appeals, 2022
D John Doe v. General Motors LLC
Michigan Court of Appeals, 2021
Zafer J Ali v. Siblini Bakery Inc
Michigan Court of Appeals, 2019
Troy Williams v. City of East Lansing
Michigan Court of Appeals, 2018
Spencer Shumaker v. Meritt Tool & Die
Michigan Court of Appeals, 2018
Gloria Barnes v. Sun Chemical Corp.
657 F. App'x 469 (Sixth Circuit, 2016)
Luce v. Kent Foundry Co.
890 N.W.2d 908 (Michigan Court of Appeals, 2016)
Colby Smith v. Michigan Pallet Incorporated
Michigan Court of Appeals, 2015
Bagby v. Detroit Edison Company
865 N.W.2d 59 (Michigan Court of Appeals, 2014)
Barrow v. City of Detroit Election Commission
836 N.W.2d 498 (Michigan Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
795 N.W.2d 161, 288 Mich. App. 688, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-v-detroit-edison-co-michctapp-2010.