Johnson, Jeffrey v. Pachmayer, Robert

CourtDistrict Court, W.D. Wisconsin
DecidedSeptember 14, 2021
Docket3:20-cv-00170
StatusUnknown

This text of Johnson, Jeffrey v. Pachmayer, Robert (Johnson, Jeffrey v. Pachmayer, Robert) is published on Counsel Stack Legal Research, covering District Court, W.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson, Jeffrey v. Pachmayer, Robert, (W.D. Wis. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF WISCONSIN

JEFFREY L. JOHNSON and JOANNE S. JOHNSON,

Plaintiffs, OPINION AND ORDER v. 20-cv-170-wmc ROBERT J. PACHMAYER and BENSON BUILDERS, LLC,

Defendants.

Plaintiffs and spouses Jeffrey L. Johnson and Joanne S. Johnson assert a variety of claims against defendants Robert J. Pachmayer and Benson Builders, LLC, relating to their role as contractor for the construction of the Johnsons’ house and boathouse in Lac du Flambeau, Wisconsin. Before the court is defendants’ motion to dismiss under Rule 12(b)(3) for improper venue, seeking to compel arbitration, and a motion to dismiss under Rule 12(b)(6), as to certain claims. (Dkt. #10.) Because the court concludes that a provision in the construction contract at issue in this case requires arbitration of all claims asserted by plaintiffs, the court will grant defendants’ Rule 12(b)(3) motion and dismiss this case.1 BACKGROUND2 On or around June 21, 2017, plaintiff Jeffrey Johnson signed a cost-plus contract

1 There are a number of other pending motions, but the court’s decision to compel arbitration and dismiss this case moots those other motions.

2 The following facts are drawn from the complaint and its attachments. with defendant Benson Builders for construction of a house and boathouse for the Johnsons at 13400 and 13402 Sand Creek Lane, Lac du Flambeau, Wisconsin. Joanne is the co-owner of one parcel and her trust is the sole owner of the other parcel comprising

“the property.”3 (Compl. (dkt. #1) ¶ 8; Compl., Ex. A (dkt. #1) pp.16-44 (“Contract”).) The Contract was countersigned by defendant Robert Pachmayer, as President of Benson Builders. Under the terms of the Contract, Benson Builders was to construct a new home and boathouse, as well as rebuild an existing boathouse on the property. The “pre- construction estimate to complete the work” was $2,454,675, although this number was

described as “merely an estimate, and the actual price would vary depending on the actual cost for labor and materials to complete the work.” (Contract (dkt. #1) § 2.) In exchange for Benson Builders’ work on the property, Jeffrey agreed to pay Benson Builders “the actual cost incurred to complete the work plus a Contractor’s Fee of fifteen percent (15%) of the cost of the Work” and to pay “5% on costs above the initial preconstruction estimates price plus any change order, customer selection, contingency

amounts or approved bid costs.” (Id.) The Contract contained the following provision describing the review, approval and payment process: Architect will review and approve amounts to be paid and notify Contractor of any amounts to be withheld and the reason(s) thereof. Architect will notify homeowner of approved amounts and homeowner will make payments to Contractor within two days. (Id. § 5(A).)

3 For ease of reference, the court will refer to the individual plaintiffs by their first names going forward. Material to the present motions, the Contract also contains the following arbitration provision: Any dispute or controversy between Builder and Owner arising out of or related to the Contract shall be decided through binding arbitration, based on the final decision of a neutral arbitrator agreed to by the parties. If the parties cannot agree on an arbitrator, each party shall name one attorney unrelated to this matter (an attorney not representing either party) who is a member of the Wisconsin State Bar. The two named attorneys shall then select another attorney who is experienced in construction law to act as the arbitrator. Judgment on an arbitration award may be entered in any court of competent jurisdiction. Once an arbitrator is selected, the parties shall agree to the rules to govern the arbitration; provided, however, if the parties cannot agree to such rules, then the arbitration shall be conducted pursuant to the Construction Industry Arbitration Rules and Mediation Procedures of the American Arbitration Association. If either party refuses to submit a claim to arbitration, or fails to abide by all the rules adopted, the nonbreaching party shall be entitled to recover all costs, including reasonable, actual attorneys’ fees, incurred in seeking further action to enforce the terms of this provision and/or to compel arbitration. Nothing in this section precludes or requires the parties to mediate this matter prior to invoking their right to arbitrate. Arbitration to take place in Milwaukee, WI unless otherwise agreed to by the parties. (Contract (dkt. #1) § 10.) Benson Builder began work on the property in August 2017 and ceased work in March 2019. During the course of the project, the Johnsons paid Benson Builders $2,610,787.04. The Johnsons claim that: (1) they were overbilled by Benson Builders for work on the project; and (2) Benson Builders failed to account for charges incurred during the project. Moreover, they claim that they hired another builder to complete the project, who estimated that it was only 50% complete and charged an additional $2,061.200.00 to do so. The Johnsons further claim that Benson Builders’ work was defective, and they ultimately paid an additional $257,700.00 to repair the defects. More formally, plaintiffs assert the following causes of action:

• Count I: breach of contract claim by Jeffrey Johnson against Benson Builders; • Count II: breach of duty of good faith claim by Jeffrey against Benson Builders; • Count III: unjust enrichment by both plaintiffs against both defendants; • Count IV: violation of Wis. Stat. § 779.02(5) by both plaintiffs against both defendants; • Count V: breach of fiduciary duty by both plaintiffs against both defendants; and • Count VI: accounting by both plaintiffs against both defendants. (Compl. (dkt. #1).) OPINION A motion to compel arbitration is reviewed in a manner similar to one for summary judgment: the court considers all evidence in the record and draws all reasonable inferences in the light most favorable to the non-moving party. Tinder v. Pinkerton Sec., 305 F.3d 728, 735 (7th Cir. 2002); Scheurer v. Fromm Family Foods LLC, No. 15-CV-770-JDP, 2016 WL 4398548, at *1 (W.D. Wis. Aug. 18, 2016). “A district court must promptly compel arbitration once it is satisfied that the parties agreed to arbitrate.” Tinder, 305 F.3d at 735 (citing 9 U.S.C. § 4). However, the party moving to compel arbitration has the burden of

demonstrating that the applicable agreement requires the parties to arbitrate the claims before the court. Scheurer, 2016 WL 4398548, at *1. As an initial point, defendants invoke the Federal Arbitration Act (“FAA”), 9 U.S.C. § 1, et seq., in support of their motion, and plaintiffs do not appear to contest its application. (See Pls.’ Opp’n (dkt. #15) 25 (relying on the FAA to argue that arbitration is not appropriate here).) Moreover, the parties’ reliance on the application of FAA is

appropriate here, since it applies to transactions involving interstate commerce, Malone v. Hoogland Foods, LLC, No. 19-CV-891-WMC, 2020 WL 6158201, at *3 (W.D. Wis. Oct. 21, 2020), and the contract at issue concerns building of a $2.5 million house and boathouse, making it reasonable to infer that interstate commerce is implicated. See Circuit City Stores, Inc. v. Adams, 532 U.S. 105, 111 (2001) (the FAA “requires judicial

enforcement of a wide range of written arbitration agreements”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

At&T Technologies, Inc. v. Communications Workers
475 U.S. 643 (Supreme Court, 1986)
First Options of Chicago, Inc. v. Kaplan
514 U.S. 938 (Supreme Court, 1995)
Circuit City Stores, Inc. v. Adams
532 U.S. 105 (Supreme Court, 2001)
Alfred Janiga v. Questar Capital Co
615 F.3d 735 (Seventh Circuit, 2010)
Kiefer Specialty Flooring, Inc. v. Tarkett, Inc.
174 F.3d 907 (Seventh Circuit, 1999)
Ilah M. Tinder v. Pinkerton Security
305 F.3d 728 (Seventh Circuit, 2002)
Zurich American Insurance Company v. Watts Industries
417 F.3d 682 (Seventh Circuit, 2005)
Renee Everett v. Paul Davis Restoration, Incorp
771 F.3d 380 (Seventh Circuit, 2014)
Zurich American Insurance v. Watts Industries, Inc.
466 F.3d 577 (Seventh Circuit, 2006)
Brickstructures, Inc. v. Coaster Dynamix, Inc.
952 F.3d 887 (Seventh Circuit, 2020)
Scheurer v. Fromm Family Foods LLC
202 F. Supp. 3d 1040 (W.D. Wisconsin, 2016)
Kalahari Development, LLC v. Iconica, Inc.
2012 WI App 34 (Court of Appeals of Wisconsin, 2012)
Grasty v. Colorado Technical University
599 F. App'x 596 (Seventh Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
Johnson, Jeffrey v. Pachmayer, Robert, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-jeffrey-v-pachmayer-robert-wiwd-2021.