Johnson Controls, Inc. v. Norair Engineering Corp.

86 Va. Cir. 138, 2013 WL 7897867, 2013 Va. Cir. LEXIS 3
CourtFairfax County Circuit Court
DecidedJanuary 10, 2013
DocketCase No. CL-2012-0006504
StatusPublished
Cited by4 cases

This text of 86 Va. Cir. 138 (Johnson Controls, Inc. v. Norair Engineering Corp.) is published on Counsel Stack Legal Research, covering Fairfax County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Controls, Inc. v. Norair Engineering Corp., 86 Va. Cir. 138, 2013 WL 7897867, 2013 Va. Cir. LEXIS 3 (Va. Super. Ct. 2013).

Opinion

By Judge Michael F. Devine

On December 14, 2012, this case came before the Court on the Defendant’s Motion to Dismiss for Failure to Name a Necessary Party and Plea in Bar. After considering the parties’ arguments and the applicable provisions of law, the Court grants die motion to dismiss Count IV of the Amended Complaint.

Background

The facts relevant to this motion are undisputed. On February 8,2011, Johnson Controls, Inc. (“JCI”) entered into a Purchase Order (the “PO”) with Norair Engineering Corp. (“Norair”). Pursuant to the PO, JCI provided fan coil units and related equipment and materials to Norair, which used them in a construction project for which Norair was a subcontractor.

After Norair failed to pay JCI pursuant to the PO, JCI filed a mechanic’s lien on November 1, 2011. On November 29, 2011, Norair petitioned the Court to substitute a bond for the lien pursuant to Va. Code § 43-71. That Code provision states as follows:

At any time after the perfecting of any such lien and before a suit be brought for the enforcement thereof. . . parties in [139]*139interest may, after five days’ notice to the lienor, apply to the court... for permission to make such payment into court, or to file such bond, as prescribed in § 43-70.. .. Upon the granting of such permission, and the payment of such money into court, or the filing of such bond, as the case may be, the property affected thereby shall stand released from such lien.

Va. Code § 43-71.

The Court granted the petition, and a bond was issued with Norair as principal and Travelers Casualty and Surety Company of America (“Travelers”) as surety.

JCI then brought this case against Norair and Travelers. After a demurrer and motion for leave to amend were filed and heard, JCI filed its Amended Complaint. The Amended Complaint alleges four causes of action, breach of contract, quantum meruit, and unjust enrichment against Norair (Counts I, n, and IE), and a bond claim against Travelers (Count IV).

Travelers argues that the Court must dismiss the bond claim because Norair is a necessary party to the claim and JCI is barred from now adding Norair as a party to that count. JCI filed its response to the motion, and after oral argument, the Court took the matter under advisement.

Analysis

A motion to dismiss and plea in bar reduces the case to “a distinct issue of fact which, if proven, creates a bar to the plaintiffs right of recovery.” Tomlin v. McKenzie, 251 Va. 478, 480, 468 S.E.2d 882, 884 (1996). The moving party carries the burden in proving the issue. Id. at 480, 468 S.E.2d at 884. The Court must draw reasonable factual inferences in favor of the non-moving party. Davey Tree Expert Co. v. Jackson, 69 Va. Cir. 350, 351-52 (Fairfax 2005). Indeed, the facts alleged in the complaint are taken as true. See Tomlin, 251 Va. at 480, 468 S.E.2d at 884.

Travelers’ motion raises two issues this Court must decide. First, the Court must determine whether Norair is a necessaiy party to the bond claim. Second, if Norair is a necessaiy party, the Court must determine whether JCI can now add Norair to the claim.

A. Necessary Parties

The Court must first determine whether Norair, the bond principal, is a necessary party to Count IV, which is JCI’s attempt to enforce the bond. “A court is powerless to proceed with a suit unless all necessary parties are properly before the court.” Mendenhall v. Douglas L. Cooper, Inc., 239 Va. 71, 74, 387 S.E.2d 468, 470 (1990). Necessary parties are defined as follows:

[140]*140Where an individual is in the actual enjoyment of the subject matter, or has an interest in it, either in possession or expectancy, which is likely either to be defeated or diminished by the plaintiff’s claim, in such case he has an immediate interest in resisting the demand, and all persons who have such immediate interests are necessary parties to the suit.

Id. at 75, 387 S.E.2d at 470 (quoting Raney v. Four Thirty Seven Land Co., 233 Va. 513, 519-20, 357 S.E.2d 733, 736 (198)).

In the context of mechanic’s liens, the Supreme Court of Virginia has held that the beneficiaries and trustees of a deed of trust on the property subject to the lien are necessary parties to a lawsuit to enforce die lien. Walt Robbins, Inc. v. Damon Corp., 232 Va. 43, 48, 348 S.E.2d 223, 227 (1986). The property owners are also necessary parties to such a lawsuit. See Mendenhall, 239 Va. at 75, 387 S.E.2d at 470. The Supreme Court found these parties necessary because of due process principles. Walt Robbins, 232 Va. at 47, 348 S.E.2d at 226. Specifically, the necessary parties have “a property right which entitles [them] to notice and an opportunity to challenge the perfection of the mechanic’s lien or to invoke the forfeiture provisions of Va. Code § 43-23.1.” Id. at 47, 348 S.E.2d at 226 (emphasis added).

When a mechanic’s lien is bonded off pursuant to the Code, these due process considerations lead to different necessary parties. Unlike lawsuits to enforce the lien itself, the property owners and the beneficiaries and trustees of die deed of trust are not necessary parties to a lawsuit to enforce the bond. George W. Kane, Inc. v. NuScope, Inc., 243 Va. 503, 510, 416 S.E.2d 701, 705 (1992). Instead, the bond principal and surety are necessary parties. Id. at 509-10, 416 S.E.2d at 705.

In the present case, JCI seeks to enforce the bond through Count IV of the Amended Complaint. Count IV names Travelers, the surety on the bond, as the only defendant. Norair, the bond principal, is not named. Thus, Count IV does not include all necessary parties. JCI contends, however, that the prior cases only require JCI to name the bond principal as a party to the lawsuit. According to JCI, it is not necessarily to name the bond principal as a defendant on the specific count relating to the bond.

The Court finds this argument unpersuasive. The cases do state that necessary parties must be made parties to the lawsuit. See Mendenhall, 239 Va. at 75, 387 S.E.2d at 470 (stating that “the new defendants were necessary parties in the suit to enforce”); Walt Robbins, 232 Va. at 48, 348 S.E.2d at 227 (stating that “the trustees and the beneficiary of the deed of trust were not made parties to the suits to enforce”). In both of these cases, however, the missing necessary parties were not named defendants at all in the lawsuits. See Mendenhall, 239 Va. at 74, 387 S.E.2d at 469-70; Walt [141]*141Robbins, 232 Va. at 44-45, 348 S.E.2d at 224-25. Further, in NuScope, the necessary parties were properly named to the bond claim action. 243 Va. at 505,416 S.E.2d at 702.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Inland Empire Dry Wall Supply Co. v. Western Surety Company
389 P.3d 717 (Court of Appeals of Washington, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
86 Va. Cir. 138, 2013 WL 7897867, 2013 Va. Cir. LEXIS 3, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-controls-inc-v-norair-engineering-corp-vaccfairfax-2013.